Outsourcing electrical design engineering to a remote team works when four things are fixed before work starts: a scope broken into reviewable packages, a data package from the owner, deliverables in formats the local engineer can check, and a licensed engineer of record in the project's jurisdiction who reviews and stamps the result. Time zones, standards editions and review rounds go into the schedule from the first day.
Short answer
How to commission remote design and studies for foreign projects: break the work into reviewable packages, give the remote team complete data, agree the format of every deliverable, and put the licensed engineer of record of the project’s jurisdiction in the loop before work starts. The remote team prepares the engineering; the local engineer reviews and stamps it. The licensing side is explained in who must stamp, sign or certify the design, and the whole picture sits within the electrical codes and grid connection comparison.
Step 1: define the scope in packages
A single request for the complete design is hard to review. Split it into packages that each end in a deliverable the engineer of record can check:
- Basis of design: codes and editions, voltage levels, operator requirements and assumptions.
- Single-line diagram and equipment schedule.
- Power-system studies: load flow, short-circuit and, where required, protection coordination, arc flash or dynamic studies. See what to specify for studies with software.
- Protection and control design and settings proposal.
- Construction drawings and cable schedules.
Each package has an owner on both sides and an approval step before the next one starts.
Step 2: prepare the data package
Remote work is only as good as the data that arrives. Typical items are the site location and the connection point, the operator’s connection requirements and its fault level, the equipment datasheets, the codes adopted locally, and the contact of the engineer of record. For studies, the list in equipment data for a short-circuit study is a good template. Anything assumed instead of supplied is written down and marked for the engineer to confirm.
Step 3: fix the deliverables and formats
Ask for deliverables the local engineer can verify: calculation reports with inputs and results, drawings in an editable format as well as PDF, study model files, and a record of the standards and editions used. A package that cannot be checked cannot be stamped.
Step 4: bring in the engineer of record early
The engineer of record chosen in the project’s jurisdiction decides what must be sealed and how. Include that engineer in the kick-off and agree the review rounds. In Queensland, regulator guidance indicates that the registration rules reach design prepared elsewhere for a Queensland project, so the work must be under the responsibility of a registered engineer there. Elsewhere the rules differ, as described in the licensing guide.
Step 5: plan the calendar
Time zones decide how much conversation is live. Review calls need an overlap, and written packages cover the rest. The operator’s own study timeline also sits on the critical path: see which interconnection study each market requires.
A numeric example
A remote team works from Colombia, UTC−5, with a working day of 08:00 to 17:00. The reviewing engineer works 09:00 to 17:00 local time. The examples use November, when the UK is on GMT, US Eastern is on EST and Queensland does not observe daylight saving.
- UK (UTC+0): the team’s day is 13:00 to 22:00 UK time. The overlap with 09:00 to 17:00 is 13:00 to 17:00, 4 hours.
- US Eastern (UTC−5): same offset as Colombia, so the reviewer’s whole 09:00 to 17:00 day overlaps with the team’s day: 8 hours.
- Queensland (UTC+10): the team’s 08:00 is 23:00 Queensland time and its 17:00 is 08:00 the next morning. The Queensland working day 09:00 to 17:00 does not overlap with it, so all communication is written, with one scheduled call at the edge of a day.
- A change of daylight saving in the other country moves the overlap by one hour twice a year; note the dates in the schedule.
The design consequence is simple. With 4 hours of overlap, a weekly review call and daily written updates are enough. With no overlap, each package must carry its own list of questions and assumptions so that a round trip takes one day rather than three.
Common mistakes
- Starting without the operator’s requirements, then redesigning when they arrive.
- Sending data in pieces over weeks, so each study is run twice.
- Agreeing a fixed price for the whole design without defining the packages and the number of review rounds.
- Treating the stamp as a formality at the end instead of a review that can change the design.
- Leaving the standards editions undefined, so the remote team and the local engineer work to different documents.
- Using chat messages for decisions that need to be recorded. Decisions about assumptions belong in the basis of design.
Checklist for the engineer
- Scope broken into packages, each with a clear deliverable and approver.
- Data package complete, with assumptions marked.
- Codes, editions and operator requirements listed in the basis of design.
- Formats for deliverables agreed with the engineer of record.
- Engineer of record identified and involved from kick-off.
- Review rounds and review time in the schedule.
- Time-zone overlap calculated, with a communication rhythm agreed.
- Responsibility for changes after review assigned to the engineer of record.
Legal frame
This guide is general orientation, not legal advice. The rules where the project is located decide who must review, stamp or certify the design. Our engineering and studies are delivered ready for your engineer of record to review and stamp; in Australia, ready for your RPEQ or chartered engineer to review and certify.
How we can help
We prepare engineering design and power-system studies from Colombia for projects in other countries, as packages with calculation files and editable drawings ready for your engineer of record to review and stamp. See engineering design and studies and contact us with the project location, the connection point and the schedule.
Related guides
- Electrical codes and grid connection compared by country
- Who must stamp, sign or certify electrical design by country
- Which interconnection study each market requires
- Power system studies with software: what to specify
- Equipment data for a short-circuit study
- What a protection coordination study needs
References
- Board of Professional Engineers of Queensland, guidance on professional engineering services; business.gov.au registration service.
- Rules of the engineering regulator where the project is located.
- Network operator connection requirements for the project.
Frequently asked questions
Can electrical design be done remotely for a project in another country?
Yes. Calculations, drawings and studies can be prepared remotely. What stays local is the licensed engineer of record who reviews and stamps the work under the rules of the jurisdiction, and the network operator submissions that the owner or its representative makes.
What information does a remote team need to start?
The site and the point of connection, the single-line diagram if one exists, equipment datasheets, the operator's connection requirements and short-circuit data, the codes and editions adopted locally, and the contact details of the engineer of record. Missing data is the most common cause of delay.
How do time zones affect a remote engineering project?
They determine how many hours of live conversation are available in a working day. With a small overlap, work is organised in written packages and scheduled review calls, and questions are batched so a reply can arrive before the next working day starts.