MISO Definitive Planning Phase (DPP) Explained

MISO's Definitive Planning Phase explained: the three DPP study phases, decision points, milestone payments and how withdrawals change a project's costs.

By Shadai García, CEO and protection engineer at Tiza Group.

DPP cycle, such as DPP-2026Phase I: preliminarysystem impact studyStay: pay thenext milestone?Phase II: revised systemimpact + facilities studyStay: pay thenext milestone?Phase III: final systemimpact + facilities studyThree-party GIAwithdrawWithdrawwithdrawWithdrawthe cost of leavinggrows as the phasesadvancePhase I: 1,000 MW100100200300300oursPhase II: 700 MWleavesour share10.014.3100 / 1,000 MW = 0.100 units per MWour share: 100 x 0.100 = 10.0 unitsa 300 MW project leaves: 700 MW remain100 / 700 = 0.143: share 14.3, +43%DPPPhase IDecidesPhase IIDecidesPhase III© tizagrp.comDPP cycle, such as DPP-2026Phase I: preliminarysystem impact studyStay: pay thenext milestone?Phase II: revised systemimpact + facilities studyStay: pay thenext milestone?Phase III: final systemimpact + facilities studyThree-party GIAwithdrawWithdrawwithdrawWithdrawthe cost of leavinggrows as the phasesadvancePhase I: 1,000 MW100100200300300oursPhase II: 700 MWleavesour share10.014.3100 / 1,000 MW = 0.100 units per MWour share: 100 x 0.100 = 10.0 unitsa 300 MW project leaves: 700 MW remain100 / 700 = 0.143: share 14.3, +43%DPPPhase IDecidesPhase IIDecidesPhase III© tizagrp.com
MISO Definitive Planning Phase: a flow chart of Phase I with a preliminary system impact study, Phase II with a revised system impact study and a facilities study, and Phase III with the final studies, the stay-or-withdraw decision after Phases I and II and the three-party agreement, and a worked example in which a 300 MW withdrawal raises a 100 MW project share of a 100-unit upgrade from 10.0 to 14.3 units. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

MISO's Definitive Planning Phase is the study part of its generator interconnection process. It has three sequential phases, each with a system impact study, and the second and third add a facilities study. After the first two phases the developer decides whether to stay in the queue by paying the next milestone or to withdraw. A project's cost share can change when other projects withdraw.

Short answer

The Definitive Planning Phase (DPP) is the study stage of the generator interconnection process of MISO, the Midcontinent Independent System Operator. It has three sequential phases. Each phase includes a system impact study: preliminary in Phase I, revised in Phase II and final in Phase III. Phase II and Phase III also include a facilities study. After Phase I and Phase II there is a decision point where the developer stays by paying the next milestone, or withdraws. This follows the cluster logic of Order No. 2023 of the Federal Energy Regulatory Commission, FERC Order 2023. For the wider US framework see the US electrical codes and grid interconnection guide.

Where the DPP sits

MISO’s process has five steps: pre-queue, application submission, application review, the DPP and the interconnection agreement. After the DPP, the developer, MISO and the transmission owner sign a three-party generator interconnection agreement (GIA). The process runs in numbered DPP cycles, such as DPP-2026. A queue cap limits how many MW each MISO region admits per cycle, and MISO publishes a queue cap tracker. MISO also publishes a project status tool and an active queue overview, which show the projects ahead of yours.

Process details have been revised in recent years. A schedule needs the current Attachment X of the MISO tariff and the rules of the open cycle.

What each phase answers

Phase I. A preliminary system impact study. It finds the first picture of the overloads and voltage issues the cluster causes and the upgrades that would fix them. This is the earliest estimate of a project’s share.

Phase II. A revised system impact study, which uses the projects that stayed, and a facilities study. The picture becomes tighter because withdrawals are reflected.

Phase III. A final system impact study and a facilities study for the network upgrades. The result feeds the agreement.

Before each phase the developer pays a milestone payment. The decision points after Phases I and II are where the developer sees results and chooses to continue or leave. The cost of leaving grows as the phases advance, so the early results matter most. For the general logic of the stages, see interconnection study stages explained. For the other operators, see PJM, CAISO and ERCOT.

What the study needs from the developer

  • Models. Power flow and dynamic models of the inverter or generator, kept consistent with the equipment. See IEEE 2800 model and simulation requirements.
  • Ride-through and control behavior. The plant must meet the ride-through requirements in force, discussed in NERC PRC-029.
  • Deposits and milestone payments at the dates the tariff sets.
  • Site control and a defined point of interconnection.

Worked example (illustrative)

The units are fictional. They show how a withdrawal moves a project’s share of a network upgrade.

Assumptions. A network upgrade costs 100 units. It is shared by projects in proportion to their MW. Phase I has five projects: 100, 100, 200, 300 and 300 MW, a total of 1,000 MW. Our project is a 100 MW project.

Step 1. Cost per MW in Phase I. 100 units ÷ 1,000 MW = 0.100 units per MW.

Step 2. Our share in Phase I. 100 MW × 0.100 = 10.0 units.

Step 3. A 300 MW project withdraws. The cluster now has 700 MW. If the upgrade is still needed in full, the cost per MW becomes 100 ÷ 700 = 0.143 units per MW.

Step 4. Our share in Phase II. 100 MW × 0.143 = 14.3 units, an increase of 43 percent.

Step 5. Reading the result. The project did not change, yet its cost share rose. If the withdrawal also removed the need for the upgrade, the opposite could occur. A developer should model both outcomes before it pays the next milestone. Real allocation follows the tariff, not a simple split by MW.

Checklist for the engineer

  • Confirm the open DPP cycle and the tariff attachment that governs it.
  • Prepare site control, models and equipment data before the application window.
  • List milestone payments, dates and what is refundable at each.
  • Read each phase result against the assumptions in the project case.
  • Test the project’s sensitivity to withdrawals of other projects.
  • Track the active queue for projects near your point of interconnection.
  • Have the engineer of record review each result before a decision.

The phases above are general orientation. MISO’s tariff and notices decide each case, and they change often. Tiza does not sign, seal or certify work in the United States. We deliver studies and engineering ready for your engineer of record to review and stamp.

How Tiza can help

If a study result looks wrong, or you need to know how sensitive your case is to other withdrawals, an independent review of the results can help before you pay the next milestone. Tiza provides independent review of study results and models, ready for your engineer of record to review and stamp. Contact us with the MISO phase report and your single-line diagram.

Figure: diagram of the DPP with its three phases, the study in each one and the decision points after Phases I and II.

References

  • MISO Generator Interconnection Queue pages (queue cap tracker, project status tool, active queue overview).
  • MISO Open Access Transmission Tariff, Attachment X, Generator Interconnection Procedures, sections on the DPP.
  • FERC filings and orders on MISO interconnection queue reforms.

Frequently asked questions

What does DPP stand for in MISO?

Definitive Planning Phase. It is the fourth step in the interconnection process of the Midcontinent Independent System Operator (MISO), after pre-queue, application and application review, and it leads to the generator interconnection agreement.

What is studied in each DPP phase?

Phase I has a preliminary system impact study, Phase II a revised system impact study and a facilities study, and Phase III a final system impact study and a facilities study for network upgrades. The scope and timing are set in the tariff.

Why do withdrawals matter to my project?

Network upgrade costs are shared among the projects that need them. When a project withdraws, the same upgrade can be shared by fewer projects, so the remaining shares can go up. Each later phase narrows the uncertainty.