NERC PRC-029-1 sets ride-through performance for transmission-connected inverter-based resources: they must stay connected through defined frequency and voltage excursions, and inverter and plant settings must not trip them inside those limits. A documented hardware limitation can be an exemption, with evidence the operator can review.
Short answer
NERC PRC-029 is the ride-through standard for inverter-based resources (IBR): solar, battery and Type 3 and Type 4 wind plants connected to the bulk power system. NERC is the North American Electric Reliability Corporation. The Federal Energy Regulatory Commission (FERC) approved PRC-029-1 in Order No. 909, published in July 2025. It requires these plants to stay connected and keep injecting current through defined frequency and voltage disturbances.
Before PRC-029, ride-through for these plants was handled in PRC-024. That standard was narrowed to synchronous machines and wind Type 1 and 2, as explained in the PRC-024 guide. The wider context is in the US electrical codes and grid interconnection guide.
Why NERC wrote a separate standard
Events on the bulk system showed that inverter-based plants can lose a large amount of output in seconds when their controls trip on a voltage dip or a phase shift. The inverter does not rotate, so it does not ride through the way a synchronous machine does. It follows its control logic. If the logic or its settings are wrong, a short fault can remove hundreds of megawatts.
PRC-029 turns that lesson into a performance requirement. Instead of only setting the relay, the owner shows that the plant as a whole stays online. That includes inverter settings, plant controller logic, protection and any other function that can trip.
How the standard is built
PRC-029-1 places four requirements on the Generator Owner (GO). The design and operation of each IBR must meet them. In plain terms:
- R1, voltage ride-through. The IBR stays connected inside the must ride-through zone of Attachment 1, with a few listed exceptions, such as disconnecting to clear a fault. Voltage is measured at the high side of the main power transformer.
- R2, voltage performance. During a voltage excursion the IBR must keep the current and power behavior the requirement sets.
- R3, frequency ride-through. The IBR stays connected inside the must ride-through zone of Attachment 2, for rates of change of frequency up to 5 Hz per second.
- R4, documented hardware limitation. An IBR in service by the effective date with a known hardware limit can claim an exemption from specific criteria. The owner documents the limit and submits it.
Inverter and plant protective functions must not trip the resource inside those zones. The exemption is limited to resources in service by the effective date of PRC-029-1. A new plant cannot use it. Read the current standard text and its implementation plan on NERC’s site for dates and for the exact applicability of each requirement.
Relationship with IEEE 2800 and IEEE 1547
IEEE 2800 describes how transmission-connected plants should perform. PRC-029-1 borrows some of its terms but does not adopt the whole standard. For distribution-connected inverters, IEEE 1547 applies instead, and the two standards are not interchangeable. Treat PRC-029 as the compliance rule and IEEE 2800 as one way to design to it.
Worked example (illustrative)
The plant and the event are illustrative assumptions that show why settings matter.
Assumptions. A solar plant has 40 inverters of 2.5 MW, so 100 MW installed. Before a fault it produces 2.0 MW per inverter, which is 80 MW. A grid fault causes a voltage dip, and one phase-locked-loop protection setting trips 18 inverters. Assume the dip stays inside the must ride-through zone.
Step 1. Output before the event. 40 × 2.0 MW = 80 MW.
Step 2. Output lost. 18 × 2.0 MW = 36 MW.
Step 3. Share of plant output. 36 ÷ 80 = 0.45, so 45 percent of the plant output disappears for a disturbance the plant should have ridden through.
Step 4. Share of capacity. 36 ÷ 100 = 36 percent of installed capacity.
Step 5. What the owner must show. The unexpected trip means a setting sits inside the ride-through region. The fix is to change the setting or, if the hardware cannot support it, to document the limitation as the standard allows.
Use real plant data in a real study. The numbers here only show the logic.
Where plants usually go wrong
Inverter settings left at factory defaults. An inverter may ship with protective functions set for distribution rules, such as tight voltage and frequency trips. A transmission-connected plant has to change them to match its ride-through needs. The change is made in the inverter, and it must also be reflected in the plant documentation.
Plant controller logic that blocks or ramps output. After a disturbance the plant controller may hold, ramp or reset the power reference. The inverters ride through, but the plant output still drops. The test of success is the output at the point of interconnection, not at one inverter.
Auxiliary supply and communications. An inverter that rides through its own grid disturbance can still stop if its auxiliary supply or its communications fail. Check what happens to cooling, controls and the plant network during a voltage dip.
Mixed fleets. A plant that adds a new inverter model beside an older one can have two behaviors under the same event. Keep a settings table per model, and test each.
No evidence. An owner may believe the plant rides through because the manufacturer said so. The standard works with evidence: study results, factory test reports or recorded events. Keep them in one place so an operator’s question can be answered without digging through old emails.
The data that proves ride-through is the same data that PRC-028 monitoring is meant to collect, so plan the two together.
Checklist for the engineer
- Identify every IBR facility and its in-service date.
- Download the current standard text and implementation plan from NERC.
- List all inverter and plant functions that can trip the resource.
- Compare each setting against the ride-through regions.
- Ask the inverter manufacturer for written capability limits.
- Prepare limitation documentation early, with evidence, if a limit exists.
- Plan a test or simulation that shows the plant stays connected.
- Keep a record of every settings change and firmware version.
Who signs and seals
In the United States, plant design is normally signed and sealed by a professional engineer licensed in the state of the project. Our work is delivered ready for your engineer of record to review and stamp. Tiza does not sign, seal or certify work in the United States. Compliance with a NERC standard stays with the registered owner; our studies support its analysis and evidence.
How Tiza can help
If your inverter plant needs its settings reviewed against ride-through requirements, Tiza provides remote relay and inverter configuration in English, ready for your engineer of record to review and stamp. Contact us with the inverter and plant controller settings.
Figure: block diagram of an inverter plant showing the functions that can trip it and the ride-through regions they must respect.
Frequently asked questions
What is the exemption in PRC-029?
A resource that cannot meet the ride-through curves because of a documented hardware limitation can ask for an exemption. The documentation shows what the limit is and why it cannot be removed. It applies only to resources in service by the effective date of PRC-029-1, not to new designs.
Is PRC-029 the same as IEEE 2800?
No. PRC-029 is a mandatory NERC reliability standard with compliance obligations. IEEE 2800 is an industry engineering standard that a plant can be designed to. PRC-029-1, approved in FERC Order 909, borrows some IEEE 2800 terms but does not adopt the full standard.
Does PRC-029 replace PRC-024?
For inverter-based resources, yes in practice. PRC-024-4 now covers synchronous generators, Type 1 and Type 2 wind and synchronous condensers, and PRC-029-1 covers inverter-based resources.