NERC now registers owners and operators of inverter-based resources that sit outside the bulk electric system. The test is an aggregate gross nameplate of 20 MVA or more through a system designed to deliver that capacity to a common point at 60 kV or above. Resources that share a point and together pass the threshold are all Category 2, and each owner and operator registers. The effective registration date for the first wave was May 15, 2026, and later projects should open the process with the Regional Entity early.
Short answer: who registers inverter-based resources with NERC
An owner or operator of an inverter-based resource (IBR) may have to register with the North American Electric Reliability Corporation (NERC). It registers as a Category 2 generator owner (GO) or generator operator (GOP) when the resource is outside the bulk electric system (BES). The test is an aggregate gross nameplate of 20 MVA or more, through a system designed primarily to deliver that capacity to a common point at 60 kV or above. The BES split is explained in what applies to your plant: BES or non-BES. The wider frame is in the US electrical codes and grid interconnection guide.
Where the rule comes from
Registration is governed by the NERC Rules of Procedure (ROP): Section 500 and Appendices 2, 5A, 5B and 5C. The Federal Energy Regulatory Commission (FERC) approved the revised registry criteria, which created Category 2 GO and GOP, on June 27, 2024. NERC runs the change as its IBR Registration Initiative, in three milestones.
Registration took place in the third and final milestone, which began in May 2025. Per NERC’s FAQ, the Regional Entities processed Category 2 registrations in batches from August 2025 through April 2026, and the listed entities received an effective registration date of May 15, 2026. Category 2 entities had no obligation to submit generating availability data before that date.
How the test works
Four points decide a case:
- Gross nameplate means the apparent power rating in MVA, taken from the inverters.
- Common point of connection: where the individual elements of the collector system join and connect to the grid.
- Aggregation: resources that share a common point and together reach 20 MVA at 60 kV or above are all Category 2, even if each is smaller than 20 MVA. Every owner and operator registers.
- Hybrids: only inverter-based resources are added. A synchronous generator at the same site does not count toward the 20 MVA.
If a project is built in phases and may later become BES, NERC’s FAQ tells the owner to start the conversation with the Regional Entity and give application data as early as possible. The Regional Entity is chosen by the place where the plant connects to the grid.
What you file
NERC’s FAQ lists the documents the owner provides through a secure site or through its registration system, the Centralized Organization Registration ERO System (CORES):
- A completed ERO Enterprise GO/GOP asset verification form.
- The interconnection agreement and its amendments.
- Operating or third-party agreements.
- Operating one-line diagrams from the generation resources to the point of interconnection.
- Nameplate data for the individual inverters or turbines.
An owner who believes the plant is below the threshold still sends the documents, and the Regional Entity then confirms whether the criteria are met. If no operator has been chosen yet, the Regional Entity advises the owner to register as both GO and GOP until one is.
After registration
Registration is the start, not the end. The standards that apply to Category 2 entities are listed in NERC’s document on compliance dates for generator owners and operators, which NERC updates quarterly. The standards on ride-through, disturbance monitoring and model verification for inverter-based plants are covered in NERC PRC-029, PRC-028 and PRC-030 and MOD-026 and MOD-027. A Category 2 plant is not a BES facility, so whether cyber security rules for BES cyber systems reach it is a separate question. Confirm it with your Regional Entity; the BES case is in NERC CIP for solar and BESS plants.
Worked example (illustrative)
Three owners build three solar plants that join one 69 kV common point: plant A with 8 MVA, plant B with 7 MVA and plant C with 6 MVA of inverters.
- Each plant alone is below 20 MVA.
- At the common point: 8 + 7 + 6 = 21 MVA, which is 20 MVA or more, at 69 kV, which is above 60 kV.
- Result: all three plants are Category 2, and each owner registers. Each also names an operator.
If plant C were replaced by a 10 MVA gas turbine, the inverter-based total would be 8 + 7 = 15 MVA. The turbine does not count toward Category 2, so no plant would meet the test.
Checklist for the engineer
- Tabulate inverter nameplates in MVA per owner and per common point.
- Confirm the voltage at the common point and who owns the connecting facilities.
- Mark which resources are inverter-based and which are synchronous.
- Decide who will be the GOP and document the operating agreement.
- Collect the five documents above before the Regional Entity asks.
- Check the phasing plan against the 75 MVA and 100 kV thresholds that make a plant BES.
- Reconfirm with the Regional Entity if the nameplate or the point of connection changes.
Legal frame
Registration and every compliance filing belong to the registered owner and operator. Tiza prepares engineering and studies ready for your engineer of record, a professional engineer licensed in the state of the project, to review and stamp. Tiza does not stamp, sign or certify, and it does not sell any NERC certification.
From registration to a design your engineer can stamp
The one-line diagram, nameplate data and operating model that NERC asks for are the same documents a connection design produces. We prepare the engineering design and the power-system studies behind them, ready for your engineer of record to review and stamp. Contact us with the plant layout and the point of connection.
Figure: three plants sharing one 69 kV common point, with the 21 MVA aggregate marked.
Related guides
- NERC reliability standards map for new generation
- NERC reliability standards in Canada: provincial adoption
- NERC MOD-032 and MOD-033: model data submission
- NERC CIP requirements: what they ask and what to reuse
References
- NERC, Rules of Procedure, Section 500 and Appendices 2, 5A, 5B and 5C.
- ERO Enterprise, FAQ: Inverter-Based Resource Registration Initiative, Category 2 GO and GOP Registration Process.
- ERO Enterprise, Application of the Registration Criteria for Category 2 Generator Owner and Generator Operator Inverter-Based Resources, version 2, April 30, 2026.
Frequently asked questions
Who has to register as a Category 2 generator owner?
The owner of a non-BES inverter-based resource that has, or contributes to, an aggregate gross nameplate of 20 MVA or more, connected through a system designed to deliver that capacity to a common point at 60 kV or above. The operator registers as Category 2 generator operator or designates another entity to do it.
Do synchronous machines count toward the 20 MVA?
No. The Category 2 criteria are limited to inverter-based resources, so for a hybrid plant NERC adds only the inverter-based nameplates. Synchronous machines count only toward the bulk electric system thresholds.
Are battery systems covered by Category 2?
Yes. NERC's April 2026 guide treats solar, wind and battery storage alike and includes plants that combine them, with examples of solar plus storage as Category 2.