A new generating plant meets NERC reliability standards in a fixed order: classify the plant, register, supply model data, design to the ride-through and protection standards, install monitoring, and apply cyber security if the plant is in the bulk electric system. US effective dates include October 1, 2026 for PRC-024-4, PRC-029-1 and PRC-030-1, April 1, 2028 for MOD-032-2 and July 1, 2028 for the next CIP versions. Dates are phased, so the commercial operation date sets the real deadline.
Short answer: the NERC standards a new generator meets, in order
A new generating plant meets NERC reliability standards in a sequence tied to the project timeline: classify, register, supply data, design, monitor and secure. The North American Electric Reliability Corporation (NERC) writes the standards, the Federal Energy Regulatory Commission (FERC) approves them, and the Regional Entities enforce them on registered owners and operators. Each step below links to the guide that explains it, within the US electrical codes and grid interconnection guide.
Step 1: classify and register
Classification comes first, because it decides which standards apply. Resources connected at 100 kV or above are bulk electric system (BES) when a unit exceeds 20 MVA, a plant exceeds 75 MVA, or dispersed resources aggregate above 75 MVA. Inverter-based plants of 20 MVA or more at 60 kV or above that are not BES are Category 2. The test is explained in what applies to your plant, and the process in NERC registration of inverter-based resources. The standards that bind a Category 2 owner are listed in NERC’s document on compliance dates for generator owners and operators.
Step 2: model data and model verification
The planning coordinator defines the data it needs, and the owner submits steady-state, dynamic and short-circuit data. MOD-032-2 sets that process and MOD-033-3 sets how planners validate their models, as in NERC MOD-032 and MOD-033. MOD-026-2 covers verification of the dynamic models submitted by owners of BES inverter-based resources and certain non-BES ones, as in NERC MOD-026 and MOD-027. The IEEE 2800 view of the same models is in IEEE 2800 model and simulation requirements.
Step 3: design to ride-through and protection standards
For inverter-based plants, ride-through performance is set by PRC-029 (NERC PRC-029). For synchronous machines and some wind types, protection settings follow PRC-024-4 (NERC PRC-024). Voltage-regulating controls and relay loadability have their own standards, such as PRC-019 and PRC-025. Because inverter settings and relay settings have to agree with each other, they are set together in the design.
Step 4: monitoring and event mitigation
PRC-028 requires monitoring and reporting data from inverter-based resources, and PRC-030 requires mitigation of unexpected events, as in NERC PRC-028 and PRC-030. The recorders and communication paths have to be in the design, not added later.
Step 5: cyber security
NERC CIP applies to BES cyber systems. CIP-002-5.1a and CIP-003-9 are the versions in force. A BES solar or battery plant is usually low impact, as in NERC CIP for solar and BESS plants.
What the planner does with it all
TPL-001 sets planning studies for planning coordinators and transmission planners, not for the plant owner. The owner meets it indirectly through the data and models in step 2, as in NERC TPL-001 transmission planning studies.
How the map fits with the interconnection agreement
The interconnection agreement and the utility’s technical requirements stay in force whatever the NERC standards say. The usual result is that a plant meets the stricter of the two on each point. A utility can require a ride-through curve or a reactive range that is wider than a NERC minimum, and the plant design has to satisfy both. Write the combined requirement once in the design basis, with the source of each line, so that the settings file and the studies share one list.
US effective dates
NERC publishes these US effective dates in its weekly standards bulletin (July 27 to August 2, 2026):
| Effective date | Standard | Phased in |
|---|---|---|
| October 1, 2026 | PRC-024-4 | No |
| October 1, 2026 | PRC-029-1 | Yes |
| October 1, 2026 | PRC-030-1 | Yes |
| April 1, 2028 | MOD-032-2 | Yes |
| July 1, 2028 | CIP-002-7, CIP-002-8, CIP-003-10 and the rest of the virtualization package | No |
| October 1, 2028 | CIP-015-1 | No |
| July 1, 2029 | CIP-003-11 | No |
Later versions may replace these. Phased-in means that individual requirements have their own dates inside the implementation plan, so read the plan for the requirement you need.
Worked example (illustrative)
A plant is expected to reach commercial operation on March 15, 2027.
- PRC-024-4, PRC-029 and PRC-030 are effective from October 1, 2026, so the plant is designed to them from the start. The date is 165 days before operation (October 1 to March 15).
- MOD-032-2 is effective on April 1, 2028, which is 383 days after operation. The plant should still answer the planner’s data requests received before then.
- The CIP versions of July 1, 2028 come 474 days after operation. The plant starts under the versions in force on March 15, 2027 and changes later.
A design that waits for the later dates has to be reopened. A design based on the earliest date does not.
Checklist for the engineer
- Classify the plant: BES, Category 2 or neither.
- Register, and name the generator operator.
- Ask the planning coordinator for its data requirements and reporting procedures.
- Fix inverter and relay settings together against the ride-through and protection standards.
- Place the recorders for event monitoring in the design.
- Assign an impact level to cyber systems and write the controls.
- Put every date against the commercial operation date and re-check each quarter.
Legal frame
Compliance with NERC standards belongs to the registered owner and operator. Tiza prepares engineering and studies ready for your engineer of record, a professional engineer licensed in the state of the project, to review and stamp. Tiza does not stamp, sign or certify, and it does not sell a NERC certification.
From the map to your design
The standards above translate into settings, models and drawings. We prepare the engineering design and the power-system studies that carry them, ready for your engineer of record to review and stamp. Contact us with the plant type, size and point of connection.
Figure: timeline of a project from classification to operation, with each standard placed at its step.
Related guides
- NERC reliability standards in Canada: provincial adoption
- Interconnection study stages: feasibility, SIS, facilities
- NERC CIP requirements: what they ask and what to reuse
References
- NERC, Standards, Compliance, and Enforcement Bulletin, July 27 to August 2, 2026, U.S. effective dates.
- NERC reliability standards PRC-024-4, PRC-028-1, PRC-029, PRC-030-1, MOD-026-2, MOD-032-2 and MOD-033-3.
- NERC, Reliability Standards Compliance Dates for Generator Owners and Generator Operators.
Frequently asked questions
Which NERC standards apply to a new solar plant?
It depends on whether the plant is bulk electric system or Category 2 non-BES. Inverter-based plants typically meet ride-through (PRC-029), disturbance monitoring (PRC-028), unexpected event mitigation (PRC-030), model data (MOD-032) and model verification (MOD-026). Check NERC's compliance-dates document for the exact list per category.
Who must meet TPL-001 on a new generation project?
Planning coordinators and transmission planners, not the generator owner. The plant owner meets TPL-001 indirectly by supplying the data and models the planner uses.
Do these standards replace the interconnection agreement?
No. The interconnection agreement and the utility technical requirements stay in force. The NERC standards add obligations that attach to the registered owner and operator.