US interconnection study stages answer three questions in order: can the grid take the plant, what does it do to the system, and what must be built to connect it. The older names are feasibility, system impact and facilities study. Under FERC Order No. 2023 the transmission process uses a cluster study, a restudy and a facilities study, but many state and utility processes still use the older sequence.
Short answer
Interconnection study stages are a sequence of three questions. First, can the grid take a plant of this size at this point? Second, what does the plant do to the system and what fixes it? Third, what exactly must be built, and what does it cost? The classic names are feasibility study, system impact study (SIS) and facilities study. The Federal Energy Regulatory Commission (FERC) changed the transmission process in Order No. 2023, which is covered in the Order 2023 cluster study guide. The wider map of US rules is in the US electrical codes and grid interconnection guide, and the comparison with other countries is in which interconnection study each market requires.
The three classic stages
Feasibility study. A fast, high-level screen. It looks at the connection point with a simplified model and answers whether the plant is likely to cause thermal overloads or a large voltage change, and what the short-circuit level is near the site. It gives a rough list of what a later study should look at. It is the cheapest and quickest step.
System impact study. The core technical study. The operator models the grid with and without the plant and runs power flow, contingency analysis (loss of a line or transformer), short-circuit and, for inverter-based plants, dynamic or transient checks. The result is a list of violations the plant causes and the network upgrades that remove them.
Facilities study. The engineering and estimating step. It defines the interconnection facilities at the plant boundary, such as breaker, metering, protection and communications, and the network upgrades from the SIS. It produces the scope and the cost estimate that go into the interconnection agreement.
What changed under Order No. 2023
For transmission-level generators in FERC-jurisdictional regions, Order No. 2023 moved the process to a cluster study, an optional restudy when requests withdraw or change, and a facilities study. The feasibility step is not part of the pro forma process. Studies are grouped, so the cost of a shared upgrade is split among requests in the cluster. Each operator files its own version of the rules, so the stage names and timing depend on the region. Texas, outside FERC’s interconnection rules, is covered separately in the ERCOT guide. The regional operators, independent system operators and regional transmission organizations (ISO/RTO), are covered in the guides on CAISO, PJM and MISO.
Distribution-level connections follow state and utility rules. California’s version is explained in the Rule 21 guide.
What data you owe at each stage
- Early: site, point of interconnection, voltage, maximum output and a single-line diagram.
- System impact: inverter or generator model files, reactive capability, transformer data, collector system data and the control mode.
- Facilities: protection scheme, relay settings basis, metering, communications and station layout.
Model quality matters. The operator cannot rely on a model that does not match the equipment you will install. The model requirements for inverter plants are discussed in IEEE 2800 model and simulation requirements and in NERC MOD-026 and MOD-027.
Worked example (illustrative)
The numbers are assumptions chosen to show the logic, not data from any project or tariff.
Assumptions. Five requests in the same study group are tested against one overloaded 138 kV line. The distribution factor (DF) is the share of each plant’s output that flows on that line.
| Request | Size (MW) | DF | Flow on line (MW) |
|---|---|---|---|
| A | 100 | 0.10 | 10 |
| B | 150 | 0.06 | 9 |
| C | 50 | 0.20 | 10 |
| D | 200 | 0.04 | 8 |
| E | 100 | 0.15 | 15 |
Step 1. Flow added to the line. 10 + 9 + 10 + 8 + 15 = 52 MW.
Step 2. Overload. If the line has 300 MW of emergency rating and carries 270 MW before the cluster, the loading becomes 270 + 52 = 322 MW, which is 22 MW over the rating.
Step 3. Share of the upgrade, if split by flow. Each share is the request’s flow divided by 52 MW: A 19.2 percent, B 17.3, C 19.2, D 15.4, E 28.8. The shares add to 100 percent, within rounding.
Step 4. Reading the result. Request C is only 50 MW but pays as much as the 100 MW request A, because its DF is higher. Real tariffs set their own allocation method, so this split shows only the idea that location matters as much as size.
Checklist for the engineer
- Confirm which operator owns the connection point and which tariff and study sequence applies.
- Confirm whether the request is transmission or distribution, and which stage you enter.
- Prepare a single-line diagram, equipment data and verified model files.
- Screen the voltage change and fault level before filing.
- List deposits, milestones and the consequence of withdrawing at each stage.
- Keep a record of every data change after filing, with its date.
- Have the study results reviewed by the engineer of record before any decision.
Legal frame
The stages above are general orientation, not advice on a specific tariff. The operator’s published rules decide the process. Tiza does not sign, seal or certify work in the United States. Our studies and engineering are ready for your engineer of record to review and stamp.
How Tiza can help
Before you file, a screening of voltage, fault level and dynamic behavior shows what the operator is likely to find. Tiza runs power-system studies for generation and storage, delivered ready for your engineer of record to review and stamp. Contact us with your single-line diagram and the point of interconnection.
Figure: flow chart of the three study stages, with the inputs the developer provides and the output of each stage.
Related guides
- How to commission remote design and studies for foreign projects
- Electrical codes and grid connection compared by country
- IEEE 2800-2022 for inverter-based resources
- NERC MOD-032 and MOD-033 steady-state and dynamic data
References
- FERC Order No. 2023, Improvements to Generator Interconnection Procedures and Agreements, and the pro forma Large Generator Interconnection Procedures.
- The interconnection tariff of the transmission provider or utility that owns the connection point.
Frequently asked questions
What is the difference between a system impact study and a facilities study?
A system impact study finds what the new plant does to the grid, such as overloads, voltage problems and short-circuit duty, and names the network upgrades that fix them. A facilities study then designs and estimates the physical work: the connection facilities and the upgrades.
Is the feasibility study still required?
Not in the pro forma transmission process under FERC Order No. 2023, which replaced it with the cluster study. Many utility and state processes, and some distribution programs, still use a feasibility step. Check the tariff of the operator that owns the connection point.
Which data does the developer owe at each stage?
Early studies need location, size, voltage and a single-line diagram. Later studies need the inverter or generator model, protection and control details, and settings. Incomplete or changed data is a common reason a study is restarted or a request is removed.