Interconnection Study Scope Checklist for Developers

A checklist of what a developer should settle before an interconnection study: data, models, operating modes and scenarios, with a hybrid plant example.

By Shadai García, CEO and protection engineer at Tiza Group.

Data request1 Pointbus, voltage, owner2 Capacitylimit vs nameplate3 Configurationsingle line = data4 Operating modesmodes, curtailment5 Models and datapower flow, EMT6 Studieslist and criteriaAll checksclosed?yesApplication filednoclose the open itemProcess flownameplate: 100 + 50 = 150 MW, request 120 MWswing at the point: -50 to +120 = 170 MWbattery: 200 / 50 = 4 hoursgrid energy: 200 / 0.922 = 216.9 MWhfour minimum casessolar 100 + battery 50 = 150 MW120 MW requestswing: -50 to +120 = 170 MW-50050100150 MWbattery duration: 200 / 50 = 4 hoursgrid energy to fill the battery200 MWh216.9 MWh1 solar full, battery discharging to the limit2 solar zero, battery discharging 50 MW3 solar zero, battery charging 50 MW4 midday, battery charging from solarillustrative values; charge efficiency 0.922ScopePointCapacityConfigurationModesModelsStudies© tizagrp.comData request1 Pointbus, voltage, owner2 Capacitylimit vs nameplate3 Configurationsingle line = data4 Operating modesmodes, curtailment5 Models and datapower flow, EMT6 Studieslist and criteriaAll checksclosed?yesApplication filednoclose the open itemProcess flownameplate: 100 + 50 = 150 MW, request 120 MWswing at the point: -50 to +120 = 170 MWbattery: 200 / 50 = 4 hoursgrid energy: 200 / 0.922 = 216.9 MWhfour minimum casessolar 100 + battery 50 = 150 MW120 MW requestswing: -50 to +120 = 170 MW-50050100150 MWbattery duration: 200 / 50 = 4 hoursgrid energy to fill the battery200 MWh216.9 MWh1 solar full, battery discharging to the limit2 solar zero, battery discharging 50 MW3 solar zero, battery charging 50 MW4 midday, battery charging from solarillustrative values; charge efficiency 0.922ScopePointCapacityConfigurationModesModelsStudies© tizagrp.com
Interconnection study scope checklist as a flow chart: the first data request, the six decisions of point of interconnection, requested capacity, configuration, operating modes, models and data, and studies and criteria with the check closed at each step, a decision on whether all checks are closed with the open item looping back, and the filed application, with the worked hybrid plant example of 100 megawatts of solar and a 50 megawatt, 200 megawatt-hour battery against 120 megawatts requested: a 150 megawatt nameplate, a 170 megawatt swing at the point, 4 hours of duration and 216.9 megawatt-hours from the grid. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

An interconnection study can stall on the application rather than on the grid: missing data, a plant description that changes, or operating modes that were never defined. A developer who fixes the scope first, with the point of interconnection, the capacity, the operating modes and the models, gets fewer questions and fewer restudies. This checklist covers what to settle before filing.

An interconnection study answers the question the developer asked. If the question changes midway, the answer is thrown away. Settling the scope before filing is the cheapest way to shorten the process.

Short answer

A good study scope fixes six things. They are the point of interconnection, the requested capacity and its limit, the plant configuration, the operating modes, the equipment and model data, and the studies the operator will run. The operator’s rules decide the details, so the checklist below is a way to organize questions, not a replacement for the tariff. The process is explained in the study stages guide and in the FERC Order 2023 guide.

The wider framework is in the US electrical codes and grid interconnection guide.

Figure: flow chart from the first data request to the filed application, with the checks the developer closes at each step.

The six decisions

1. Point of interconnection. The exact bus or line, the voltage level and the owner. The point decides which operator, which tariff and which studies apply. See the guides on PJM, CAISO and ERCOT.

2. Requested capacity. The maximum injection at the point of interconnection, and the maximum withdrawal for storage. The nameplate of the equipment may be larger than the capacity requested, as the example below shows.

3. Configuration. Generator type, inverter and transformer data, collector layout, and for hybrid plants whether solar and storage share one connection. The single-line diagram has to match the data.

4. Operating modes. Voltage control, power factor or reactive power mode, curtailment, charging from the grid and the response to operator commands. The NEC 705.13 guide covers how a control system limits export.

5. Models and data. A power flow model, a short-circuit model and, for inverter plants, dynamic and EMT models. See the IEEE 2800 model guide and NERC MOD-032 and MOD-033.

6. Studies and criteria. The list of studies the operator will run: power flow and short circuit, stability and EMT, and in some cases deliverability or protection studies.

Data request checklist

  • Single-line diagram with ratings and the point of interconnection.
  • Site control evidence and the plant location.
  • Generator or inverter data sheets and the manufacturer’s models.
  • Main transformer rating, impedance, connection and taps.
  • Collector and gen-tie data: length, conductor and impedance.
  • Reactive capability curve at the point of interconnection.
  • Protection concept and the communication to the operator.
  • For storage: power, energy, charge mode and efficiency data.
  • Requested in-service date and the phases if the project is built in stages.

Worked example (illustrative)

Illustrative data, not from any project. A hybrid plant has 100 MW of solar and a 50 MW, 200 MWh battery. The requested interconnection capacity is 120 MW of injection.

  1. Nameplate sum: 100 + 50 = 150 MW. This is above 120 MW, so the plant controller must hold injection at 120 MW.
  2. Withdrawal: the battery can charge at 50 MW. The plant swings from -50 MW to +120 MW at the point, a range of 170 MW.
  3. Battery duration: 200 / 50 = 4 hours.
  4. Grid energy needed to fill the battery, assuming a charge efficiency of 0.922 (the square root of an 85% round-trip efficiency): 200 / 0.922 = 216.9 MWh.
  5. Minimum cases: solar at full output with the battery discharging up to the limit; solar at zero with the battery discharging at 50 MW; solar at zero with the battery charging at 50 MW; midday with the battery charging from solar.

If the application states only 150 MW, the operator will study more injection than needed and may assign upgrades the project does not need. If it states 120 MW without defining the controller limit, the operator may ask for proof that the limit holds. Both situations are avoided by a clear scope.

Keeping the scope stable

Once the application is in, treat the scope as controlled. Name one person who approves changes. Before any change, ask whether it alters the capacity, the point of interconnection, the electrical characteristics or the in-service date, since those are the changes operators usually judge as material. Keep a dated log of each decision. The log also helps when the operator’s questions arrive months later and the team that wrote the application has moved on.

Where scopes fail

  • The capacity on the application differs from the capacity on the drawings.
  • The storage is studied as a generator only, without the charging case.
  • The model is not the version that will be installed.
  • Changes after filing are not checked against the operator’s material change rules.
  • The data are consistent in one document but not across the single-line diagram, the models and the data sheets.

Checklist for the engineer

  • Read the operator’s tariff, business practice manual and study guidelines.
  • Confirm the point of interconnection and the owner of the facilities.
  • Fix the requested capacity, the limit and the operating modes.
  • Check the single-line diagram, the data sheets and the models against each other.
  • Request the manufacturer models and confirm the format.
  • Run a screening of fault level, voltage and weak grid before filing.
  • Define who handles the operator’s questions and how fast.
  • Record every change to the project with a date.

Who signs and seals

Drawings and studies for a US project are normally reviewed and sealed by a professional engineer licensed in the state of the project. Tiza delivers engineering and studies ready for your engineer of record to review and stamp. Tiza does not sign, seal or certify work in the United States.

How Tiza can help

Before you file, Tiza reviews the scope and data of a generation or storage project and delivers the single-line diagram, the data package and a screening of fault level and voltage. These power-system studies and the engineering design are delivered remotely, in English, ready for your engineer of record to review and stamp. Contact us with your project data.

Frequently asked questions

What should a developer define before filing an interconnection request?

The point of interconnection, the requested capacity, the plant type and configuration, the operating modes, the equipment data and the models the operator accepts. A change to any of them after filing can force a restudy.

Why does the operating mode of a storage plant matter?

A storage plant can inject and absorb power, so the study must cover both directions and the transitions. The mode also decides whether the plant can charge from the grid and how export is limited.

Can the plant change size after the study starts?

Changes are limited. Under most processes a material change after a certain stage loses the queue position or triggers a restudy. Ask the operator what counts as a material change in its rules.