Tiza Group

Home / Guides / Codes and grid connection: US, UK, CA, AU

NEC 705.13 Power Control Systems: How They Limit Current

How NEC 705.13 power control systems limit solar and battery current so a busbar needs no upgrade. Includes a worked example and an engineer's checklist.

By Shadai García, CEO and protection engineer at Tiza Group.

utilitymain 200 ACT=~PV 10 kW=~battery 7.6 kWPCS controllersetpoint 40 Apowercontrolcommssolar 41.7 + battery 31.7 A73.3 x 1.25 = 91.7 A: failsPCS holds 40 A = 9.6 kW8.0 kW curtailed (45 %)source current (A)40 A room73.3 Anameplate91.7 Ax 1.2540 Awith PCSControlCurrent sensorControllerSetpointInvertersLimit© tizagrp.comutilitymain 200 ACT=~PV 10 kW=~battery 7.6 kWPCS controllersetpoint 40 Apowercontrolcommssolar 41.7 + battery 31.7 A73.3 x 1.25 = 91.7 A: failsPCS holds 40 A = 9.6 kW8.0 kW curtailed (45 %)source current (A)40 A room73.3 Anameplate91.7 Ax 1.2540 Awith PCSControlCurrent sensorControllerSetpointInvertersLimit© tizagrp.com
A power control system holding solar and battery current at 40 A: the CT on the monitored conductor, the PCS controller and the 73.3 A nameplate sum against the room left on a 200 A busbar. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

A power control system under NEC 705.13 monitors current on a busbar or conductor and limits the output of connected sources, so the design can be based on the limited current instead of the combined nameplate output. It can avoid a panel upgrade, but it adds a listed device, a verified setpoint, restricted access to the setting and marking.

Adding a battery to a house with solar often runs into the same wall: the panel cannot take the extra source breakers. A power control system gives the designer another route. It does not make the busbar bigger. It makes sure the busbar never sees more current than the design allows.

Section numbers in this guide follow the 2023 edition of the NEC (NFPA 70). NFPA issued the 2026 edition in 2025. Many jurisdictions still enforce an earlier edition, so confirm the one adopted where you build.

Short answer

A power control system (PCS) under NEC 705.13 is a listed system that monitors current and limits connected sources so that a busbar or conductor is not overloaded. The designer sizes the busbar check or the conductor from the limited current, not from the combined output of every source. The design must show the setpoint, the listing, the restricted access to the setting and the marking on the controlled circuits.

Figure: a service panel with a current transformer on the monitored conductor feeding a power control device that limits the inverter output.

The wider framework is in the US electrical codes and grid interconnection guide. The simpler rule a PCS can replace is in the guide on the NEC 705.12 busbar 120% rule.

How the edition matters

The place where the NEC keeps these rules has moved between editions. The 2020 edition put the detailed power control system text in 705.13. The 2023 edition retitled that section for energy management systems and pointed to Article 750. The 2026 edition refocuses 705.13 on power control systems again, with the general rules in Article 130 and informational notes that refer to both UL 3141 and UL 1741. Read the section and its informational notes in the edition your authority enforces before you rely on a clause number.

The practical lesson is simple. A drawing note that cites a clause should name the edition. A reviewer under one edition may look for the rule in a different place from a reviewer under another.

How a power control system works

A PCS has three parts: a measurement, a control action and a set limit.

  1. Measurement. A current sensor on the monitored busbar or conductor reports the actual current.
  2. Control action. When the current approaches the limit, the PCS reduces the output of the sources it controls, or turns off loads, or both.
  3. Set limit. The setpoint is the current the PCS holds the circuit to. It is chosen by a qualified person and must stay within the rating of the overcurrent device that protects the circuit.

Sources fall into two groups. A source the PCS can curtail counts at its controlled value. A source the PCS cannot curtail counts at its full output. The design must keep the controlled current, plus the current from the uncontrolled sources, within the ampacity of the busbar or conductor.

What the PCS does not do

  • It does not increase the ampacity of the busbar or conductor.
  • It does not replace the overcurrent device that protects the conductor.
  • It does not remove the listing, marking and documentation requirements.
  • It does not apply when the utility or the authority has not accepted the control method.

A PCS is also a point of failure. If the sensor or the controller fails, the design must say what happens: the sources should drop to a safe output, not run free. Ask for the failure behavior in the equipment documentation.

Worked example

Illustrative data, not from any project. A single-phase 240 V home has a 200 A busbar and a 200 A main breaker. The owner wants a 10 kW solar inverter and a 7.6 kW battery inverter on the same panel.

  1. Solar output current: 10,000 W / 240 V = 41.7 A.
  2. Battery output current: 7,600 W / 240 V = 31.7 A.
  3. Combined nameplate current: 41.7 A + 31.7 A = 73.3 A.
  4. Without a PCS, the 120% rule uses 125% of the source current: 1.25 × 73.3 = 91.7 A. The room on a 200 A panel with a 200 A main is only 40 A, so the design fails.
  5. Suppose a PCS is set to hold the combined source current at 40 A, the room left under the rule. At 240 V, that is 9.6 kW.
  6. Compared with the nameplate total of 17.6 kW (10 kW + 7.6 kW), the limited total of 9.6 kW is 8.0 kW lower, or about 45% lower.

The design now rests on a controlled 40 A instead of an uncontrolled 73.3 A. The owner pays for it with curtailment: at full sun and a full battery, up to 8 kW of capability cannot be used. The designer must explain that trade to the owner. The final busbar evaluation under 705.13 is for the engineer of record, using the text of the adopted edition.

When a PCS fits and when it does not

A PCS fits when the panel is full but the real peak load is low. It also fits when a service upgrade would be slow or costly, or when the sources rarely run at full output together. It fits poorly when the sources must run at full output together, such as a backup system serving all loads in an outage. It also fits poorly where the utility does not accept the control scheme.

A PCS also touches other parts of the project. The utility may ask how the setting is protected from tampering. The manufacturer may require specific firmware. The monitored circuit’s current sensor must be installed where the code and the manufacturer say.

Common mistakes

  • Treating the PCS as a way to ignore the busbar rating.
  • Citing a clause number without naming the NEC edition.
  • Leaving the setpoint off the drawings, or letting it differ from the commissioned value.
  • Forgetting that an uncontrolled source counts at its full output.
  • Placing the current sensor on the wrong conductor.
  • Assuming the owner will accept curtailment without explaining it.

Checklist for the engineer

  • Confirm the NEC edition, the local amendments and whether the authority accepts a PCS for this project.
  • Confirm that the utility accepts the control method for the interconnection.
  • Identify the busbar or conductor the PCS monitors and the overcurrent device that protects it.
  • List every source and decide whether the PCS controls it.
  • Calculate the controlled current and the total, and compare it with the ampacity.
  • Check the listing of the equipment against the edition.
  • Record the setpoint on the drawings and the commissioning report.
  • Restrict access to the setting to qualified persons and mark the controlled circuits.
  • Ask the manufacturer what happens when the sensor or controller fails.
  • Explain the curtailment to the owner in writing.

For the control side of solar, see the guide on zero export in solar. For battery systems in the same installation, see NEC Article 706 and AC-coupled versus DC-coupled BESS.

Who signs and seals

A design package that relies on a PCS is normally signed and sealed by a professional engineer licensed in the state of the project. Tiza delivers engineering design ready for your engineer of record to review and stamp. Tiza does not sign, seal or certify work in the United States.

How Tiza can help

If your project relies on a PCS to avoid a panel upgrade, Tiza delivers engineering design ready for your engineer of record to review and stamp. It includes the single-line diagram, the control scheme and the calculations, delivered remotely and in English. Send us the panel data and the equipment specification, and we will scope the work with you. Contact us to start.

Frequently asked questions

What is a power control system under the NEC?

It is a system that monitors current on a busbar or conductor and controls connected sources or loads so that current stays at or below a set limit. The design then uses the limited current rather than the sum of the equipment's nameplate ratings.

Does a power control system replace the 120% busbar rule?

It offers a different way to show that the busbar or conductor is not overloaded. Instead of adding breaker ratings, the design relies on a controlled current. The device must be listed, set by a qualified person and documented. Your authority and utility decide whether they accept this path for a given project.

Who can change the power control system setting?

Only a qualified person, with access restricted so that the limit cannot be raised by accident. The setting shown on the drawings should match the commissioned value, and the circuits it controls are marked.

WhatsApp