NEC Article 240 protects conductors by matching each conductor to an overcurrent device. Section 240.4 states the general rule, 240.6 lists the standard ratings, 240.4(B) allows the next higher standard rating in limited cases and 240.21 permits shorter conductors to connect to a larger feeder under tap rules. Sections 240.67 and 240.87 add arc energy reduction for large devices.
Article 240 is where the NEC explains what protects a wire. Almost every other article refers back to it. A reviewer who finds a conductor protected by the wrong device does not need to read any other part of the design to ask for a change.
Section numbers in this guide follow the 2023 edition of the NEC (NFPA 70). NFPA issued the 2026 edition in 2025. Many jurisdictions still enforce an earlier edition, so confirm the edition and local amendments adopted where you build.
Short answer
NEC Article 240 sets how overcurrent devices, meaning fuses and circuit breakers, protect conductors and equipment. The general rule in 240.4 is that a conductor is protected at its ampacity. Section 240.6 lists the standard device ratings. Section 240.4(B) lets the designer round up to the next standard rating in limited cases. Section 240.21 allows tap conductors that are shorter than the main feeder and protected differently. Arc energy reduction for large devices is in 240.67 for fuses and 240.87 for circuit breakers.
Figure: a feeder with its overcurrent device, a tap leaving the feeder and a second device at the tap’s end.
The wider framework is in the US electrical codes and grid interconnection guide. The arc energy rule has its own guide on NEC 240.87 arc energy reduction.
The three questions of Article 240
Almost every use of Article 240 answers one of three questions.
- What is the allowable ampacity of the conductor? This comes from the ampacity tables and the correction factors for temperature and number of conductors, in Article 310. Article 240 does not set it.
- What is the load, and is it continuous? A continuous load runs for three hours or more. The device is sized above the load, with a 125% factor on the continuous part.
- What device rating is available? The standard ratings in 240.6 are the only values a standard fuse or inverse-time breaker comes in.
A conductor has to pass all three questions. The device must be large enough to carry the load, small enough to protect the conductor and one of the ratings that exist.
Standard ratings and the next-size-up rule
The standard ratings run in steps, for example 90, 100, 110, 125, 150, 175 and 200 A. Many conductors have ampacities that fall between two steps. Section 240.4(B) allows the next higher standard rating for a device of 800 A or less. This applies when the conductor ampacity does not match a standard rating and some further conditions are met. One of those conditions excludes branch circuits that supply more than one receptacle for cord-and-plug-connected portable loads.
The permission does not apply above 800 A. For a large device, the conductor must have an ampacity at or above the rating, or the design must use another method.
Taps
A tap is a conductor connected to a feeder that is smaller than the feeder. The feeder’s device protects the feeder, and the tap would be unprotected if no rule covered it. Section 240.21 gives the rules. The best known are the 10-foot tap, the 25-foot tap and the rules for transformer secondary conductors. Each one fixes a maximum length, a minimum ampacity relative to the feeder device and what the tap must end in. The conditions are strict because a tap conductor can see fault current that the feeder device was never meant to clear.
Taps are checked closely in review because they are easy to get wrong. A tap that is one foot too long does not meet the rule, even if the cable would survive the fault in practice.
Where Article 240 meets solar and storage
Inverter circuits follow the same logic with their own inputs. The output of an inverter is treated as continuous, so the device is sized at 125% of the maximum output current. The guide on PV conductor sizing and raceways walks through the dc and ac circuits, and the guide on gPV fuses and DC disconnects covers the dc side. Where the circuit connects to a panel, the busbar check is in the guide on the NEC 705.12 120% rule.
Worked example
Illustrative data, not from any project. A feeder serves a panel with 60 A of continuous load and 20 A of non-continuous load.
- Continuous part: 60 A x 1.25 = 75 A.
- Add the non-continuous part: 75 A + 20 A = 95 A.
- The minimum overcurrent device is 95 A. The standard ratings near it are 90 A and 100 A. 90 A is too small, so the next standard rating is 100 A.
- The conductor must be able to carry at least 95 A at its terminal temperature rating, after corrections. Assume that the corrected ampacity of the chosen conductor is 95 A.
- A 95 A ampacity does not match a standard rating, so 240.4(B) lets the designer use the 100 A device, subject to its other conditions.
Now add a tap. The feeder is protected by a 400 A device. A 25-foot tap must have an ampacity of at least one third of the device rating: 400 A / 3 = 133.3 A. A tap conductor with 125 A of ampacity fails, and one with 140 A passes this check. The tap must also meet the length, termination and protection conditions in the section. The arithmetic is only the first screen.
Common mistakes
- Using the load current alone, with no 125% factor on the continuous part.
- Using a device rating that does not exist as a standard rating.
- Applying 240.4(B) to a device above 800 A.
- Stretching a tap beyond the length limit.
- Forgetting that fault current at the tap may exceed what the tap conductor withstands.
- Selecting a device without checking its interrupting rating against the available fault current. The guide on low-voltage breaker interrupting rating explains the difference.
Checklist for the engineer
- Identify the NEC edition and local amendments the authority enforces.
- Calculate the load, separating continuous and non-continuous parts.
- Find the conductor ampacity from the tables, with the correction factors applied.
- Select a device from the standard ratings and check it against the load and the conductor.
- If you round up under 240.4(B), confirm that every condition is met.
- For each tap, record the length, the ampacity ratio and what the tap ends in.
- Check the interrupting rating of each device against the fault current at its location.
- For devices of 1,200 A or more, check the arc energy reduction requirement.
- Show the device ratings and the conductor sizes on the single-line diagram.
Who signs and seals
A design package of this kind is normally signed and sealed by a professional engineer licensed in the state of the project. Tiza delivers engineering design and studies ready for your engineer of record to review and stamp. Tiza does not sign, seal or certify work in the United States.
How Tiza can help
If your project needs the short-circuit and coordination studies behind the device selection, Tiza delivers power-system studies. They are ready for your engineer of record to review and stamp, remotely and in English. Send us the single-line diagram and the equipment data, and we will scope the work with you. Contact us to start.
Frequently asked questions
What does NEC 240.4 require?
It requires conductors to be protected against overcurrent at their ampacity, with specific exceptions for particular circuits and applications. In practice, each conductor is matched to a device rated to protect it, and the device is sized with the load and the continuous-load rules in mind.
Can I use the next higher standard breaker size?
Often yes, when the conductor ampacity does not match a standard rating, the device is rated 800 A or less and the other conditions in 240.4(B) are met. The permission does not apply to every circuit and it does not remove the continuous-load requirement.
What is a tap rule?
A tap rule allows a conductor connected to a feeder to be protected by the feeder's device even though that device is larger than the tap conductor's ampacity. The rules in 240.21 set the conditions, such as length, minimum ampacity and where the tap ends. They are exceptions to the general rule and are checked closely in review.