Tiza Group

Home / Guides / Codes and grid connection: US, UK, CA, AU

NEC Article 706 Energy Storage: What a BESS Design Needs

What NEC Article 706 asks of a battery storage design: disconnects, overcurrent protection, listing and interconnection, with a worked sizing example.

By Shadai García, CEO and protection engineer at Tiza Group.

battery bank 800 Vdc disconnectdc fuse=~PCS 250 kWac 400 AbreakerutilityBMSEMSdc: 257.7 kW / 800 V = 322.1 Aac: 250,000 / (1.732 x 480) = 300.7 Apowersignalscommsac current: 300.7 Ax 1.25 = 375.9 A, so 400 A350 A is too smalldc: 322.1 A at 800 Vcurrent (A)350 A300.7ac375.9x 1.25400device322.1dcPower pathBatteryDC fusePCSAC breakerUtility© tizagrp.combattery bank 800 Vdc disconnectdc fuse=~PCS 250 kWac 400 AbreakerutilityBMSEMSdc: 257.7 kW / 800 V = 322.1 Aac: 250,000 / (1.732 x 480) = 300.7 Apowersignalscommsac current: 300.7 Ax 1.25 = 375.9 A, so 400 A350 A is too smalldc: 322.1 A at 800 Vcurrent (A)350 A300.7ac375.9x 1.25400device322.1dcPower pathBatteryDC fusePCSAC breakerUtility© tizagrp.com
A 250 kW battery system: battery bank with BMS, dc disconnect and fuse, power conversion system and 400 A ac breaker to the utility, with the ac and dc currents of the sizing example. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

NEC Article 706 covers the electrical installation of energy storage systems such as batteries behind a power conversion system. It works with Article 705 for the interconnection, with Article 240 for overcurrent protection and with the equipment listing and fire code for the system itself. A good design shows the ratings, the disconnects and the protection on the single-line diagram.

A battery system looks simple on a sales sheet: a cabinet, an inverter and a cable. The code review is not simple. The system is a source, a load and a stored-energy hazard at the same time, and different rules cover each role.

Section numbers in this guide follow the 2023 edition of the NEC (NFPA 70). NFPA issued the 2026 edition in 2025. Article 706 changed in the 2026 edition, so read the article in the edition your jurisdiction enforces.

Short answer

NEC Article 706 is the part of the code that covers energy storage systems: batteries with the equipment that charges and discharges them. It sets out what the installation needs, such as disconnecting means, overcurrent protection and marking. It does not work alone. The interconnection with the utility and other sources is in Article 705, the protection of conductors is in Article 240 and the grounding is in Article 250. The fire code covers siting and fire safety.

Figure: a battery system on a dc bus, a power conversion system, an ac breaker and a utility connection, with the control and communication links to the battery management system.

The wider framework is in the US electrical codes and grid interconnection guide. Related guides cover NEC 705.13 power control systems and NEC Article 240.

What a storage system is made of

The parts matter because the code treats them differently. The guide on BESS parts and standards describes them in detail. In short:

  • Battery modules and racks, with a battery management system that watches cell voltage and temperature.
  • A power conversion system, the inverter that converts between the battery’s direct current and alternating current.
  • An energy management system that sets when to charge and discharge.
  • Disconnects and overcurrent devices on the dc and ac sides.
  • Enclosures and ventilation, often part of the listed product.

Whether the system is AC-coupled or DC-coupled changes where the conversion happens and how many conversion stages the energy passes through. It also changes which conductors the code review focuses on.

What the code review looks at

A reviewer reading Article 706 on a project usually checks the following.

  1. Ratings. The maximum charge and discharge current, the voltage range and the short-circuit current of the battery, all from the manufacturer’s data.
  2. Disconnecting means. A way to disconnect the battery from the rest of the system and from the utility, located and labeled as the code requires.
  3. Overcurrent protection. Devices on the dc and ac sides sized for the current and for the available fault current.
  4. Listing. Product evaluation to the relevant UL standards, commonly UL 9540 for the system, and the grid-support listing of the inverter under UL 1741.
  5. Marking. Labels that identify the system, its sources and its disconnects.
  6. Interconnection. Whether the system exports, what limits the export and how it fits the panel or the service.

The system can also be used for backup power. In that case the backup loads and the transfer to island operation fall under other articles and are not covered by Article 706 alone. The guide on lithium-ion battery safety and service life covers what sits behind the listing: thermal runaway, cell chemistry and aging.

Worked example

Illustrative data, not from any project. A 250 kW power conversion system connects to a 480 V three-phase bus. The battery bank has a nominal dc voltage of 800 V, and the converter has an assumed discharge efficiency of 97%.

  1. AC output current: 250,000 W / (1.732 x 480 V) = 300.7 A.
  2. The output is continuous, so size the overcurrent device at no less than 125% of that current: 300.7 A x 1.25 = 375.9 A.
  3. Standard overcurrent ratings include 350 A and 400 A. 350 A is below 375.9 A, so the next rating is 400 A.
  4. DC input power at full discharge: 250 kW / 0.97 = 257.7 kW.
  5. DC current at the nominal voltage: 257,700 W / 800 V = 322.1 A. The dc conductors, the dc overcurrent device and the dc disconnect must be rated for at least this current at the lowest battery voltage in service, which is higher still, and for the fault current the battery can deliver.
  6. Energy for a two-hour duration at full power: 250 kW x 2 h = 500 kWh of usable energy, before any allowance for aging.

The reviewer will check the ac device at 400 A, the dc side against the manufacturer’s maximum, and the conductor ampacity against both. The dc current rises as the battery discharges and voltage falls, which is why the nominal voltage is not the design point.

Where designs go wrong

  • Sizing the dc side at nominal voltage instead of at the lowest operating voltage.
  • Ignoring the fault current the battery itself can supply, which can exceed the rating of devices selected for the inverter.
  • Treating the listing as proof of the installation.
  • Placing the disconnect where it is not readily accessible or not labeled.
  • Mixing up the NEC and the fire code. A design can meet one and fail the other.
  • Skipping the communication and control interface, which the cybersecurity of a BESS depends on.

Commissioning and what the authority will ask

Before energizing, the authority and the utility usually ask for several documents. They are the single-line diagram, the data sheets, the listing evidence, the power conversion settings and the commissioning plan. The guide on BESS commissioning tests lists the tests and the records that normally follow.

Checklist for the engineer

  • Identify the NEC edition, the fire code edition and the local amendments adopted by the authority.
  • Collect the battery’s maximum charge and discharge current, voltage range and fault current.
  • Size the ac and dc overcurrent devices and conductors from those values.
  • Show the disconnects, their locations and their labels on the single-line diagram.
  • Confirm the system listing and the inverter’s grid-support listing.
  • Confirm how the system connects under Article 705 and what limits export.
  • Check the siting, separation and ventilation requirements of the fire code with the authority.
  • Document the control and communication interface and who can change settings.
  • Keep the calculation package with the drawings for the reviewer.

Who signs and seals

A storage system design for a US project is normally signed and sealed by a professional engineer licensed in the state of the project. Tiza delivers engineering design ready for your engineer of record to review and stamp. Tiza does not sign, seal or certify work in the United States.

How Tiza can help

If you are preparing a battery storage project for a permit or a utility submittal, Tiza delivers engineering design ready for your engineer of record to review and stamp. It includes the single-line diagram, the protection scheme and the sizing calculations, delivered remotely and in English. Send us the equipment data and the site requirements, and we will scope the work with you. Contact us to start.

Frequently asked questions

What does NEC Article 706 cover?

It covers the installation of energy storage systems, such as batteries with a power conversion system, including disconnecting means and overcurrent protection. The interconnection to the utility or to other sources falls under Article 705. Fire safety and siting rules usually come from a separate fire code and local rules.

Is a UL 9540 listing enough for approval?

A listing shows that the energy storage system was evaluated as a product. It does not replace the installation review. The authority still checks the installation against the NEC, the fire code and the manufacturer's instructions. Ask the authority which edition and which local amendments apply.

Where does the NEC end and the fire code begin for batteries?

The NEC governs the electrical installation. Fire protection, spacing, separation, ventilation and location limits for a battery system usually come from a fire code and from local rules, with NFPA 855 as the common reference. The authority having jurisdiction decides which edition applies.

WhatsApp