NEC Article 705 covers how a solar array, storage system or other power source connects to a premises wiring system that also has a utility. A source connects on the supply side of the service disconnect under 705.11 or on the load side under 705.12, where the busbar rules, including the 120% method, apply. Disconnects are in 705.20 and power control systems in 705.13.
NEC Article 705 is the part of the National Electrical Code (NFPA 70, NEC) on interconnected power sources. It says how a PV inverter or a storage system connects to a premises wiring system that a utility also feeds. The two connection methods, the busbar check and the disconnect rules are the core of it. The wider US framework is in the US electrical codes and grid interconnection guide.
Short answer
Under Article 705 a source connects in one of two places:
- Supply side of the service disconnect, to the service conductors, under 705.11.
- Load side, to a busbar or feeder in the premises, under 705.12.
On the load side, the busbar is the limit. Section 705.12(B) offers methods that cap the sum of the source and the main protection against the busbar rating. One of them is the 120% method. The source breaker and the main sit at opposite ends of the bus. Then 125% of the source output current plus the main breaker rating may not exceed 120% of the busbar rating.
The disconnecting means for the source is in 705.20, and power control systems, which limit export or manage load, are in 705.13. Which edition applies depends on your authority having jurisdiction (AHJ). The 2026 vs 2023 comparison lists what moved.
Supply side: 705.11
A supply-side connection taps the service conductors between the utility service point and the service disconnect. Because the source feeds ahead of the main, the busbar of the panel is not stressed by backfeed. The connection requires its own overcurrent protection, disconnecting means and bonding.
The 2023 edition expanded 705.11 with provisions for splices and taps and for connections to existing and utility-controlled equipment. The 2026 edition streamlined 705.11, with fewer subsections and more cross-references to the general rules. It also restored in 705.11(C)(1) a limit on conductor length between the connection and the first overcurrent device inside a building. The limit applies along the conductor, not in a straight line.
Load side: 705.12
A load-side connection feeds a busbar that also carries loads. The check protects the busbar from carrying more than its rating when the source and the grid both push current toward the same bus.
Section 705.12(B) allows a few approaches, including:
- a check that 125% of the source output current plus the main protection stays within the busbar rating,
- the 120% method for sources at the opposite end of the bus from the main, and
- a check that the sum of all overcurrent devices on the panel, excluding the main, stays within the busbar rating.
The method’s subsection number differs between editions. Cite 705.12(B) in your documents and let the calculation sheet show the numbers.
The source breaker usually goes at the end of the busbar opposite the main, and the panel label or the listing may require it. Panels fed from the middle of the bus have separate provisions in the edition you apply.
Disconnects, overcurrent protection and power control
- 705.20 is the section for the source disconnecting means. In the 2026 edition, 690.13 and 706.15 refer to it, so PV and storage follow the same rules.
- 705.30 carries much of the overcurrent protection for the source circuits in the 2023 edition, with references to Article 230.
- 705.13 covers power control systems. A listed power control system limits export or load so that the busbar or conductor is not overloaded. The informational notes refer to UL 3141 and UL 1741. See zero export in solar.
Relay-based interconnection protection on larger plants is a utility matter outside the NEC: see interconnection relays and the US codes and interconnection guide.
Worked example: a 200 A panel
This example is illustrative. The panel, the inverter and the loads are assumed.
Assumptions: a 200 A busbar, a 200 A main breaker at one end, a backfed source breaker at the opposite end, and a 240 V single-phase inverter.
- Room for 125% of the source output current under the 120% method: 1.20 × 200 - 200 = 40 A.
- Inverter A, 7.6 kW: output current 7,600 / 240 = 31.7 A. Multiplied by 125%: 39.6 A, which is within the 40 A limit. A 40 A breaker works.
- Inverter B, 9.6 kW: 9,600 / 240 = 40 A. Multiplied by 125%: 50 A, which exceeds 40 A. The connection fails the 120% method.
- Options for B: connect on the supply side under 705.11. Reduce the main to 175 A if the load calculation allows it; the limit becomes 1.20 × 200 - 175 = 65 A, and 50 A fits. Replace the panel with one of a higher rating. Or use a listed power control system to limit the current.
- Compare the options by cost and by the effect on the load calculation, not only by which one passes.
The 120% method is a limit on the connection, not a design target. A supply-side connection avoids it, with its own requirements.
Figure: single-line of a 200 A panel with the main at the top of the bus, the backfed breaker at the opposite end and the 120% check written beside it.
Checklist for the engineer
- Confirm the NEC edition and amendments adopted by the AHJ.
- Decide supply side or load side and justify the choice.
- For load side, show the busbar rating, the main rating, the source output current and the check with the numbers.
- Check the position of the source breaker against the panel listing and labels.
- Show the disconnecting means under 705.20 and the overcurrent protection of the source circuits.
- Measure supply-side conductor length along the route if the edition has a limit.
- State whether a power control system limits export and which listing covers it.
- Confirm the utility’s application and its technical requirements separately.
Who signs and seals
A US design normally has to be signed and sealed by a professional engineer licensed in the state of the project. Tiza delivers engineering and studies ready for your engineer of record to review and stamp. Tiza does not sign, seal or certify work in the United States.
How Tiza can help
If the busbar check fails, or a larger plant needs more than a panel calculation, Tiza prepares the interconnection engineering design, remotely and in English. It is ready for your engineer of record to review and stamp. Send the single-line, the equipment data and the utility’s requirements and we will scope the work with you. For the wider article map see NEC Article 690. Contact us to start.
Frequently asked questions
What is the 120% rule?
A load-side connection method in 705.12. When the source breaker and the main breaker sit at opposite ends of a busbar, the sum of 125% of the source output current and the main breaker rating may not exceed 120% of the busbar rating. The subsection number differs between editions, so cite 705.12(B) and check the one in force.
What is a supply-side connection?
A connection made ahead of the service disconnect, to the service conductors, under 705.11. It avoids the busbar limits of the load side. The 2026 edition restores a limit on the length of conductor between the connection and the first overcurrent device inside a building.
Is utility approval separate from the NEC?
Yes. The NEC governs the installation and the AHJ inspects it. The utility approves the connection under its own interconnection rules and IEEE 1547 requirements. A project needs both approvals before it can operate in parallel with the grid.