Tiza Group

Home / Guides / Codes and grid connection: US, UK, CA, AU

NEC Article 690: Solar PV Systems Explained

NEC Article 690 for solar PV systems: how the article is organized, which sections drive a design, and how to check voltage, current and protection sizing.

By Shadai García, CEO and protection engineer at Tiza Group.

...array boundary20 modules in seriescombiner+ fusesdisconnect=~inverterPOCArticle 690: PV source and output circuitsArticle 705: connection to the supplymaximum voltage must not exceed any component ratingpowermaximum voltage of the string20 x 49.5 = 990 V at STCx 1.0945 at -10 C = 1,083.6 Vfits 1,500 V, not 1,000 Vvoltage (V)1,500 V equipment1,000 V equipment990 VSTC1,083.6 Vat -10 CPower pathStringCombinerDisconnectInverterConnection© tizagrp.com...array boundary20 modules in seriescombiner+ fusesdisconnect=~inverterPOCArticle 690: PV source and output circuitsArticle 705: connection to the supplymaximum voltage must not exceed any component ratingpowermaximum voltage of the string20 x 49.5 = 990 V at STCx 1.0945 at -10 C = 1,083.6 Vfits 1,500 V, not 1,000 Vvoltage (V)1,500 V equipment1,000 V equipment990 VSTC1,083.6 Vat -10 CPower pathStringCombinerDisconnectInverterConnection© tizagrp.com
PV string single line with the array boundary, combiner, dc disconnect, inverter and the reach of Articles 690 and 705, and the maximum string voltage against 1,000 V and 1,500 V ratings. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

NEC Article 690 is the part of NFPA 70 that governs solar photovoltaic systems. It sets how to calculate maximum voltage and current, protect and disconnect the circuits, shut them down quickly, and ground and bond the array. Article 705 covers the connection to other sources and Article 706 covers storage. The edition adopted by the authority having jurisdiction decides the clause text.

NEC Article 690 is the part of the National Electrical Code (NFPA 70, NEC) that governs solar photovoltaic (PV) systems. Its structure and the sections that drive a design let you read a PV single-line diagram the way a plan reviewer does. For the full US framework, with the NEC, IEEE 1547 and the utility process, see the US electrical codes and grid interconnection guide.

Short answer

Article 690 answers five design questions for a PV system:

  1. How high can voltage and current go? Sections 690.7 and 690.8.
  2. How is each circuit protected? Section 690.9, with Article 240.
  3. How is the array shut down quickly for firefighters? Section 690.12.
  4. How is the system disconnected? Section 690.13 in the 2023 edition, with the rules moved to 705.20 in the 2026 edition.
  5. How is it grounded and bonded? Sections 690.41 to 690.47, with Article 250.

Article 705 covers connection to other sources such as the utility, and Article 706 covers energy storage. The edition your authority having jurisdiction (AHJ) has adopted fixes the text. NFPA issued the 2026 edition in 2025, and many places still enforce 2020 or 2023. The 2026 vs 2023 comparison lists what moved.

How a PV design reads against the article

A solar array is a current-limited source. Its current barely rises in a fault, and its voltage rises in cold weather. Most of Article 690 follows from those two facts.

Voltage first. Section 690.7 sets how to find the maximum PV system voltage. In practice it is the string open-circuit voltage corrected for the lowest expected temperature. Every conductor, fuse, switch and inverter input in the string must be rated for that value. The guide on PV string sizing walks through the temperature correction.

Current next. Section 690.8(A) sets the maximum circuit current, which starts from the module short-circuit current with a factor for irradiance above standard test conditions. Section 690.8(B) then sets the conductor ampacity from that current. The 125% guide shows both tests.

Protection and disconnects. Section 690.9 covers overcurrent protection, including the rule that devices in PV source circuits are listed for PV use. The 690.9 guide explains when a string needs a fuse and when it does not. For the devices themselves, see gPV fuses and DC disconnects.

Rapid shutdown. Section 690.12 applies to PV circuits on or in buildings. It sets voltage limits inside and outside the array boundary after initiation. The sibling 690.12 guide covers the limits, and the earlier guide on rapid shutdown covers the technology.

Grounding and bonding. Sections 690.41 to 690.47 cover system grounding, equipment grounding and the grounding electrode system. They lean on Article 250. See the grounding guide.

Where Article 690 stops

Three neighbors complete the picture.

  • Article 705 covers sources that connect to other sources: how a PV system ties into the service, the busbar rules and the power control systems. See Article 705.
  • Article 706 covers energy storage systems, which matter for hybrid designs. See hybrid solar with batteries.
  • Chapters 1 to 4 supply the general rules: working space, overcurrent protection, grounding and conductor ampacity. Article 690 changes some of them for PV and leaves the rest as they are.

Inverter behavior at the utility is outside the NEC. IEEE 1547 and UL 1741 handle it, as the US codes and interconnection guide explains.

Worked example: maximum voltage of a string

This example is illustrative, with assumed module data.

Assumptions: 20 modules in series and an open-circuit voltage of 49.5 V per module at standard test conditions. The data-sheet temperature coefficient of open-circuit voltage is -0.27%/°C. The record low site temperature is -10°C, and cell temperature at the low is taken equal to the air temperature.

  1. Temperature difference from 25°C down to -10°C: 35°C.
  2. Correction factor: 1 + 0.0027 × 35 = 1.0945.
  3. String open-circuit voltage at STC: 20 × 49.5 = 990 V.
  4. Maximum voltage: 990 × 1.0945 = 1083.6 V.

The result is below 1,500 V, so the string fits equipment rated for 1,500 V. It would not fit equipment rated for 1,000 V. A reviewer checks the voltage rating of every component against 1083.6 V, not against the 990 V on the data sheet.

Figure: PV string single-line view with the array boundary, the combiner, the dc disconnect, the inverter and the points where Articles 690 and 705 apply.

How a plan reviewer reads the set

A reviewer does not need to read Article 690 front to back. A practical order follows the single-line from the array to the service:

  1. The maximum voltage on the drawing against the voltage rating of each component.
  2. The conductor schedule against the circuit current calculation.
  3. The fuses and breakers against both the conductors and the module limit.
  4. The rapid shutdown notes against the roof plan.
  5. The grounding notes against the inverter instructions.
  6. The point of connection against Article 705.

Each item corresponds to a section of the article, so a calculation sheet organized in the same order is easier to review.

Checklist for the engineer

  • Confirm the NEC edition and amendments adopted by the AHJ.
  • Calculate maximum voltage with the lowest site temperature and the module’s coefficient.
  • Calculate maximum circuit current and conductor ampacity from 690.8, then check overcurrent protection under 690.9.
  • State where rapid shutdown applies and what equipment achieves it.
  • Show the disconnects, grounding electrode connections and equipment grounding on the drawing.
  • Mark which article covers each part of the single-line: 690, 705 or 706.
  • Confirm utility requirements outside the NEC.

Who signs and seals

A US design normally has to be signed and sealed by a professional engineer licensed in the state of the project. Tiza delivers engineering ready for your engineer of record to review and stamp, and does not sign, seal or certify work in the United States.

How Tiza can help

If your permit set came back with comments, or the project is changing designers, Tiza can run an independent review of a third-party design against the NEC edition your authority enforces. We list each comment with the clause it comes from, so your engineer of record can resolve them quickly. Send the drawings and the adopted edition and we will scope the review with you. Contact us to start.

Frequently asked questions

What does NEC Article 690 cover?

Solar photovoltaic systems: the array, its circuits, the inverter and the equipment up to the point where the system connects to other sources. It sets rules for maximum voltage and current, overcurrent protection, disconnects, rapid shutdown, grounding and bonding and marking. The connection to the utility side is in Article 705.

Is Article 690 enough to design a PV system?

No. Article 690 works with Chapters 1 to 4 of the NEC, mainly Article 110 for general requirements, Article 240 for overcurrent protection, Article 250 for grounding and Article 310 for conductors. The utility and the AHJ add their own requirements.

Did the Article 690 numbers change in the 2026 edition?

The article keeps its number and the section numbers used in this guide. The 2026 edition changed content inside it, including a new 690.4(G), and moved the system disconnect rules to 705.20. Check the edition your authority has adopted.

WhatsApp