NEC 690.9 requires overcurrent protection for PV circuits unless the conductors and modules can carry the available current. A device is rated at no less than 125% of the 690.8(A) current, must be listed for PV use in source circuits, and must not exceed the module's maximum series fuse rating. Backfeed from parallel strings decides whether a string needs its own fuse.
NEC 690.9 overcurrent protection answers a question that every string combiner design starts with: does this string need a fuse, and if so, what size? The answer depends on what current can flow in a fault, which is different in a PV array than in an ordinary circuit. The wider US framework is in the US electrical codes and grid interconnection guide.
Short answer
Under NEC 690.9:
- A PV circuit needs overcurrent protection unless the conductors and the modules can carry the current that all connected sources can deliver.
- The device rating is at least 125% of the current calculated in 690.8(A).
- Devices in PV source circuits must be listed for PV use (690.9(B) in the 2023 edition).
- The rating must not exceed the maximum series fuse rating printed on the module data sheet, and it must protect the conductor.
An array is current-limited, so a single string cannot overload its own conductors. The danger is backfeed: in a faulted string, the other parallel strings push current into the fault. The more strings in parallel, the more backfeed.
Why backfeed matters
Take a string with a fault, for example a pinched cable with a ground path. Its own current stays near the module short-circuit current. The other strings connected to the same combiner bus also feed the fault. The current in the faulted string is the sum of the others, and it flows in the reverse direction through the modules.
Modules tolerate a limited reverse current, stated as the maximum series fuse rating. Above it, the modules can overheat. A fuse in each string opens before that happens. Section 690.8(D) lists the currents of the parallel strings that the protection has to consider. See PV array faults for how these faults appear in the field.
When protection is not required
Section 690.9(A) allows the omission when two conditions hold:
- the conductor ampacity meets 690.8(B), and
- the currents from all sources stay within the maximum overcurrent device rating the module manufacturer specifies.
Two strings in parallel are the usual case where this works. The faulted string sees only one other string’s current. With three or more strings, the sum often exceeds the module rating, and the string needs its own device.
Choosing the device
- Listing. Devices in source circuits are listed for PV use. Examples are fuses listed to UL 2579 and circuit breakers listed to UL 489B, with a dc voltage rating at or above the maximum system voltage. See gPV fuses and DC disconnects.
- Placement. A single device on one conductor can protect a circuit if it sits on the same polarity throughout the system. 690.9(C) gives this permission for PV system dc circuits. Some combiners fuse both poles. The string combiner box guide shows the arrangement.
- Marking. Devices in dc circuits carry the PV marking your edition requires.
Worked example: three strings in a combiner
This example is illustrative. The module data are assumed.
Assumptions: module short-circuit current of 11.5 A and a maximum series fuse rating of 20 A on the data sheet. The backfeed is estimated as the 690.8(A) current of each other string.
- Maximum circuit current per string: 1.25 × 11.5 = 14.375 A.
- Minimum device rating: 1.25 × 14.375 = 17.97 A.
- The next standard rating at or above 17.97 A is 20 A.
- The module limit is 20 A, so 20 A is allowed. Had the module limit been 15 A, no standard device would fit between 17.97 A and 15 A, and the design would have to change.
- Two strings in parallel: the backfeed into a faulted string is 1 × 14.375 = 14.375 A. That is below the module rating of 20 A, so the modules do not require a device. The conductor check under 690.8(B) still applies.
- Three strings in parallel: the backfeed is 2 × 14.375 = 28.75 A, above 20 A. Each string needs a device.
The decision depends on the module rating as much as on the string count. A module with a 30 A series fuse rating would allow the third string without a fuse.
Figure: three strings at a combiner bus, with the backfeed path into a faulted string drawn as a current arrow and the 20 A fuse in each string.
Documentation a reviewer expects
A protection schedule is easier to approve when it shows its inputs. For each combiner, list the number of strings, the module short-circuit current, the 690.8(A) current, the minimum and selected device rating, the module series fuse rating and the backfeed. Add the device listing and its dc voltage rating. If the design omits fuses, state the two conditions from 690.9(A) and the numbers that meet them. A sheet that only states “20 A fuse” forces the reviewer to rebuild the reasoning.
Checklist for the engineer
- Confirm the NEC edition and amendments adopted by the AHJ.
- Read the maximum series fuse rating on the module data sheet. See how to read a module data sheet.
- Calculate the 690.8(A) current and the minimum device rating at 125%.
- Calculate the backfeed for each combiner size and compare it with the module rating.
- Select a listed device, check its dc voltage rating against the maximum system voltage and its interrupting rating against the available current.
- Check that the device protects the conductor under 690.8(B).
- Mark devices as the edition requires.
- Cross-check the conductor sizing in the 690.8 guide.
Who signs and seals
A US design normally has to be signed and sealed by a professional engineer licensed in the state of the project. Tiza delivers engineering ready for your engineer of record to review and stamp. Tiza does not sign, seal or certify work in the United States.
How Tiza can help
If your project has combiner boxes to size and protection to document, Tiza prepares the engineering design, including backfeed calculations and device schedules, remotely and in English. It is ready for your engineer of record to review and stamp. Send the module data sheets, the string layout and the adopted NEC edition, and we will scope the package with you. The overview in NEC Article 690 shows where this section fits. Contact us to start.
Frequently asked questions
Does every PV string need a fuse?
No. Section 690.9 allows circuits without overcurrent protection when the conductors can carry the available current and the current from all sources stays within the maximum series fuse rating of the modules. With two strings in parallel that is often the case. With three or more, backfeed from the healthy strings into a faulted one usually requires protection.
What fuse rating does 690.9 require?
A device rated at no less than 125% of the current calculated in 690.8(A). That minimum then has to fit under the module's maximum series fuse rating and protect the conductor. Select the next standard rating at or above the minimum, then check both limits.
Can I use any DC fuse on a PV string?
No. Overcurrent devices in PV source circuits must be listed for use in PV systems, such as fuses listed to UL 2579 or circuit breakers listed to UL 489B. A general-purpose AC fuse or breaker is not the right product for a dc string at the system voltage.