NEC 690.8 Conductor Sizing and the 125% Factor

How NEC 690.8 sizes PV conductors: the 125% circuit current, the two ampacity tests and a worked example in which the larger result governs the design.

By Shadai García, CEO and protection engineer at Tiza Group.

Isc 11.5 Astring conductorcombinerTest 1: 17.97 A1.25 x 14.375, no deratingTest 2: 14.375 / f15.97 A (A), 20.54 A (B)largergoverns1.25 x 11.5 = 14.375 A maximum circuit currentpowercalculationtwo tests, the larger governscase A, factor 0.90: 17.97 A, Test 1case B, factor 0.70: 20.54 A, Test 2the same wire can pass A and fail Bampacity required (A)17.9715.97Test 1Test 2case A17.9720.54Test 1Test 2case BCalculationIsc125 %Test 1Test 2Larger© tizagrp.comIsc 11.5 Astring conductorcombinerTest 1: 17.97 A1.25 x 14.375, no deratingTest 2: 14.375 / f15.97 A (A), 20.54 A (B)largergoverns1.25 x 11.5 = 14.375 A maximum circuit currentpowercalculationtwo tests, the larger governscase A, factor 0.90: 17.97 A, Test 1case B, factor 0.70: 20.54 A, Test 2the same wire can pass A and fail Bampacity required (A)17.9715.97Test 1Test 2case A17.9720.54Test 1Test 2case BCalculationIsc125 %Test 1Test 2Larger© tizagrp.com
One PV string conductor sized by two ampacity tests in parallel: Test 1 at 17.97 A against Test 2 at 15.97 A in case A and 20.54 A in case B, the larger governing. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

NEC 690.8 sizes PV conductors in two steps. 690.8(A) sets the maximum circuit current, starting from the module short-circuit current with a 125% factor. 690.8(B) then requires conductor ampacity to meet the larger of two tests: 125% of that current with no adjustment, or that current after temperature and conduit fill factors. The larger result governs.

NEC 690.8 conductor sizing is where the 125% factor appears twice. The clause is a two-step method, and the numeric example below shows how to check a calculation sheet quickly. The wider framework is in the US electrical codes and grid interconnection guide, and the article map is in NEC Article 690.

Short answer

NEC 690.8 sizes PV conductors in two steps:

  1. 690.8(A), maximum circuit current. For a PV source circuit this is the sum of the module short-circuit currents in parallel, multiplied by 125%.
  2. 690.8(B), conductor ampacity. The conductor must satisfy the larger of two tests. The first test is 125% of the 690.8(A) current, with no correction or adjustment applied. The second test is the 690.8(A) current after temperature correction and conduit fill adjustment have been applied to the conductor ampacity.

The larger of the two results governs. The two 125% factors are not a single compounding factor, although multiplying them gives about 156% of the short-circuit current, a figure designers use as a shortcut.

Systems of 100 kW or more have an engineered route in 690.8(A)(1). The 2026 edition removes the size threshold from that route, and it adds a method based on the module instructions in 690.8(A)(1)(a)(2). See the changes between 2023 and 2026.

Step 1: maximum circuit current, 690.8(A)

The 125% factor allows for irradiance above the standard test condition of 1,000 W/m². Cloud-edge effects and cold, clear days can push module current above the data-sheet short-circuit current. Section 690.8(A) uses the factor so that the designer does not have to estimate it.

For several strings in parallel, the current of the circuit is the sum of the module short-circuit currents in parallel, times the factor. Section 690.8(D) addresses overcurrent protection for parallel string circuits, and the 690.9 guide covers it.

Step 2: conductor ampacity, 690.8(B)

Two tests are run side by side.

  • Test 1: the conductor ampacity, taken without temperature or fill adjustment, must be at least 125% of the 690.8(A) current. This test covers the termination and the continuous nature of the current.
  • Test 2: the conductor ampacity after correction for ambient temperature and adjustment for the number of current-carrying conductors must be at least the 690.8(A) current.

Test 1 tends to govern in mild conditions. Test 2 tends to govern in hot conduit on a roof, with many conductors in the same raceway. Which one wins depends on the installation, so the designer runs both.

Ampacity values come from the Article 310 tables of your edition. The temperature rating of the terminations at both ends also limits the usable ampacity, so check the equipment instructions. The guide on PV conductor sizing and raceways covers the routing side, and solar cable and MC4 connectors covers the product side.

Worked example: one string, two installations

This example is illustrative. The module data and the correction factors are assumed to show how the tests compete.

Assumptions: module short-circuit current of 11.5 A, one string per circuit, and two installation cases.

  1. Maximum circuit current: 1.25 × 11.5 = 14.375 A.
  2. Test 1, the same in both cases: 1.25 × 14.375 = 17.97 A of ampacity without adjustment.
  3. Case A, mild conditions, combined temperature and fill factor of 0.90. Test 2 requires ampacity of 14.375 / 0.90 = 15.97 A. The larger result is 17.97 A, so Test 1 governs.
  4. Case B, hot conduit with many conductors, combined factor of 0.70. Test 2 requires 14.375 / 0.70 = 20.54 A. The larger result is 20.54 A, so Test 2 governs.
  5. Select the conductor whose table ampacity in your edition is at least 17.97 A in Case A and 20.54 A in Case B. Then confirm that the terminal ratings at both ends allow that ampacity.

The same wire can pass in Case A and fail in Case B. A calculation sheet that shows only one test does not prove the sizing.

Figure: single string circuit from the module to the combiner, with the two ampacity tests drawn as parallel checks and the larger one selected.

Common mistakes

  • Applying the 125% factor to the wrong current. The factor belongs to the short-circuit current, not to the operating current on the data sheet.
  • Using the wrong ampacity column. The termination temperature limits the column you can use.
  • Forgetting adjustment for roof conduit. Conduit near the roof surface runs hotter than the air temperature on the site data sheet.
  • Rounding too early. The 2026 edition adds 690.4(G), which allows rounding only on the final result, after correction factors.

What the newer editions add

The 2023 edition keeps the two-step method and renamed some subsections, including 690.8(D) for multiple PV string circuits. The 2026 edition adds options inside 690.8(A)(1). One lets a licensed engineer use a documented calculation method for any system size, where 2023 limited it to systems of 100 kW or more. Another lets the maximum current follow the module manufacturer’s instructions. A rounding rule in 690.4(G) applies to the final result. None of them removes the two ampacity tests, so a sizing sheet still shows both.

Checklist for the engineer

  • Confirm the NEC edition and amendments adopted by the AHJ.
  • List module short-circuit current from the data sheet and the number of strings in parallel.
  • Calculate 690.8(A) current, then both 690.8(B) tests, and show the larger.
  • Document the correction and adjustment factors with their source.
  • Check termination temperature ratings at the modules, combiner and inverter.
  • Check voltage drop separately. See DC and AC voltage drop in cables.
  • Confirm the overcurrent device rating matches the conductor under 690.9.

Who signs and seals

A US design normally has to be signed and sealed by a professional engineer licensed in the state of the project. Tiza delivers engineering ready for your engineer of record to review and stamp. Tiza does not sign, seal or certify work in the United States.

How Tiza can help

If your PV project needs conductor schedules, voltage drop and protection calculations that show each step, Tiza prepares the engineering design remotely and in English. The package is ready for your engineer of record to review and stamp. Send the module data sheets, the layout and the adopted NEC edition, and we will scope the calculations with you. Contact us to start.

Frequently asked questions

Is the 156% rule in the NEC?

No. The figure of about 156% is shorthand for 125% times 125% applied to the module short-circuit current. The code states two separate tests and the larger one governs, so the shorthand is only a quick estimate. The sizing sheet shows both tests with their correction factors.

Where does the first 125% come from?

From 690.8(A), which sets the maximum PV circuit current. It starts from the sum of the module short-circuit currents in parallel and applies a 125% factor for irradiance above standard test conditions. The 2026 edition also permits maximum circuit current to follow the module instructions, which can help with bifacial modules.

Do I apply the 125% factor to inverter output too?

The output side of an inverter follows a different calculation. The inverter's maximum continuous output current is the basis, and the overcurrent device and conductors are sized with the continuous-load factor in your edition. See the guide on Article 705 and the feeder example in the US codes guide.