NEC 690.41 to 690.47 cover PV grounding and bonding. 690.41 sets how the PV system is grounded, 690.42 where the grounded conductor is connected, 690.43 equipment grounding and bonding, 690.45 and 690.46 the size and use of equipment grounding conductors, and 690.47 the grounding electrode system for the array structure. Article 250 supplies the sizing tables.
NEC 690.41 to 690.47 is the grounding and bonding part of Article 690 for solar PV. It is short on its own, because it relies on Article 250 for sizing and electrode rules. The sections below show how the pieces connect and how the equipment grounding conductor is sized from the overcurrent device. The wider US framework is in the US electrical codes and grid interconnection guide.
Short answer
Part V of Article 690 splits grounding into a few jobs:
| Section | Subject |
|---|---|
| 690.41 | System grounding: grounded or ungrounded arrays, and the configuration chosen |
| 690.42 | Point of connection of the grounded conductor |
| 690.43 | Equipment grounding and bonding of frames, equipment and enclosures |
| 690.45 | Size of equipment grounding conductors, through Article 250 |
| 690.46 | Array equipment grounding conductors, including small conductors |
| 690.47 | Grounding electrode system for a building or structure supporting a PV array |
The table is our own index of the section subjects. The wording and values belong to NFPA 70 and are different in each edition. The 2023 edition made minor rewording changes in 690.41(A), and the 2026 edition keeps the section numbers. See the changes between 2023 and 2026.
System grounding, 690.41 and 690.42
A PV array can be grounded or ungrounded. Many modern inverters use ungrounded arrays with ground-fault detection and interruption inside the inverter. Others use a grounded conductor with a single bond. The configuration decides where the system-grounding connection sits, and 690.42 fixes the point at which a grounded conductor is bonded.
The choice affects the rest of the design: the type of fault detection, the inverter’s listing and the rapid shutdown approach. The grounding design is part of the inverter and array package, so read the manufacturer instructions before drawing the single-line. See PV array faults for how ground faults develop.
Equipment grounding and bonding, 690.43
Metal parts that can become energized in a fault must be bonded to an equipment grounding conductor (EGC). That covers module frames, racking, combiner enclosures, inverters and metallic raceways. The key points for a designer:
- Bond modules with the method in the module installation instructions and the equipment listing, such as listed bonding clips or lugs.
- Treat the racking as a bonding path only if it is listed or identified for that use.
- Keep the EGC continuous from the array to the inverter and to the main grounding point.
The earlier guide on grounding of a solar plant covers the utility-scale side with earthing grids. Surge protection in the array is its own topic: see surge protective devices in PV systems.
Sizing the EGC, 690.45 and 690.46
Section 690.45 points to 250.122. There the size of the EGC follows the rating of the overcurrent device protecting the circuit, which is the device sized under 690.9. See NEC 690.9.
Section 690.45 also covers circuits with no overcurrent device, and it has its own provision on upsizing for voltage drop. That provision differs from the general rule in 250.122(B), so do not carry a feeder habit into the PV circuits without reading it. Section 690.46 adds a rule for array EGCs smaller than 6 AWG. Where the EGC runs unprotected on a roof, read the mechanical protection requirements of 250.120 in your edition.
Grounding electrodes, 690.47
When a building or structure supports the array, 690.47 ties the array grounding to the building’s grounding electrode system under Article 250. The rules for an additional electrode at the array have been reworded between editions, so do not copy a detail from an older project. Confirm what your edition requires and what the authority expects. See grounding of distribution substations for the earthing basics behind electrode design.
Worked example: EGC from the overcurrent device
This example is illustrative. A combiner takes six strings, each with a 20 A fuse sized under 690.9. The combiner output circuit is protected by a 100 A device.
- String circuits: the device is 20 A. Table 250.122 gives 12 AWG copper for that rating.
- Combiner output circuit: the device is 100 A. Table 250.122 gives 8 AWG copper.
- The EGC does not follow the size of the string or output conductors. It follows the device ahead of each circuit.
- If the output conductors are later enlarged for voltage drop, apply the upsizing provision of 690.45 for that circuit, not the 250.122(B) rule by habit.
The schedule shows each EGC next to its device, so the reviewer can follow the table lookup.
Figure: array grounding schematic with module frames bonded by the EGC, the combiner enclosure, the inverter, the main grounding point and the building electrode system.
What reviewers ask for
A plan reviewer looks for three things on grounding. The first is the system grounding configuration, with the inverter manufacturer’s instruction that supports it. The second is an EGC schedule that ties each conductor size to the overcurrent device and to any upsizing. The third is a drawing that shows where the array grounding meets the building electrode system. A notes-only submittal that says “grounding per NEC” gives the reviewer none of them.
Checklist for the engineer
- Confirm the NEC edition and amendments adopted by the AHJ.
- State the system grounding configuration and confirm it with the inverter manufacturer.
- Show module bonding with the method in the installation instructions.
- Size each EGC from 250.122 and the 690.45 provisions, including any upsizing for voltage drop.
- Show the connection of the array grounding to the building electrode system.
- Mark the bonding of racking, combiners and raceways on the drawing.
- Cross-check overcurrent devices with the PV overcurrent guide.
- Ask the authority about local additions to the grounding requirements.
Who signs and seals
A US design normally has to be signed and sealed by a professional engineer licensed in the state of the project. Tiza delivers engineering ready for your engineer of record to review and stamp. Tiza does not sign, seal or certify work in the United States.
How Tiza can help
If your solar project needs a grounding and bonding design that matches the inverter and array package, Tiza prepares the engineering design remotely and in English, with the EGC schedule and the single-line notes. It is ready for your engineer of record to review and stamp. Send the equipment data sheets, the layout and the adopted NEC edition, and we will scope the package with you. For the wider context see NEC Article 690. Contact us to start.
Frequently asked questions
Do PV module frames need to be grounded?
Yes. Section 690.43 requires exposed non-current-carrying metal parts, such as module frames, equipment and conductor enclosures, to be connected to an equipment grounding conductor, regardless of voltage. The modules and their mounting hardware must be listed or identified for the bonding method used.
How is the equipment grounding conductor sized?
Section 690.45 sends the designer to 250.122, where the size follows the rating of the overcurrent device protecting the circuit. Section 690.45 also covers circuits with no overcurrent device and has its own provision on upsizing for voltage drop, which differs from the general rule in 250.122(B).
Is a separate grounding electrode required at the array?
Section 690.47 covers the grounding electrode system for a PV array supported by a building or structure and ties it to Article 250. The detailed rules on additional electrodes have been reworded between editions, so read 690.47 in the edition your authority enforces.