Tiza Group

Home / Guides / Codes and grid connection: US, UK, CA, AU

NEC 690.12 Rapid Shutdown: 2023 and 2026 Clauses

NEC 690.12 rapid shutdown in the 2023 and 2026 editions: controlled limits, the array boundary, initiation devices and the checks a plan reviewer runs.

By Shadai García, CEO and protection engineer at Tiza Group.

roof planarray boundary 1 ft (305 mm)inside: 80 V, 30 s=~inverterinitiationdeviceto servicemodule-level device on each moduleoutside: 30 V, 30 spowerinitiation signalvoltage 30 s after initiationno devices: 24 x 49.5 = 1,188 V24 x 4 V = 96 V: above 80 V4 V devices: 20 modules max1 V device: 24 V, meets bothvoltage (V)80 V inside30 V96 V24 x 4 V80 V20 x 4 V24 V24 x 1 VSequenceInitiateDevices30 s80 V30 V© tizagrp.comroof planarray boundary 1 ft (305 mm)inside: 80 V, 30 s=~inverterinitiationdeviceto servicemodule-level device on each moduleoutside: 30 V, 30 spowerinitiation signalvoltage 30 s after initiationno devices: 24 x 49.5 = 1,188 V24 x 4 V = 96 V: above 80 V4 V devices: 20 modules max1 V device: 24 V, meets bothvoltage (V)80 V inside30 V96 V24 x 4 V80 V20 x 4 V24 V24 x 1 VSequenceInitiateDevices30 s80 V30 V© tizagrp.com
Rapid shutdown on a roof array: the 1 ft array boundary, the initiation device and the string voltage after initiation for 4 V and 1 V module-level devices. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

NEC 690.12 requires rapid shutdown for PV circuits on or in buildings. In the 2023 edition conductors inside the array boundary are controlled to 80 V within 30 seconds, or covered by a listed PV hazard control system, and conductors outside the boundary go to 30 V within 30 seconds. The 2026 edition reorganizes the initiation device text in 690.12(C). Confirm the edition your authority enforces.

NEC 690.12 rapid shutdown is the clause that lets firefighters work around a PV array without touching energized conductors. The 2023 and 2026 editions set the same limits, and a reviewer checks a design against both in the same way. It is part of the US electrical codes and grid interconnection guide series, and the article-level map is in NEC Article 690.

Short answer

NEC 690.12 applies to PV system circuits installed on or in buildings. After a person initiates rapid shutdown:

  • Conductors inside the array boundary must be controlled to no more than 80 V within 30 seconds. The alternative is a listed PV hazard control system installed as its listing requires.
  • Conductors outside the array boundary must be controlled to no more than 30 V within 30 seconds. So must conductors more than 1 m (3 ft) inside the building from the point of entry.
  • The array boundary extends 1 ft (305 mm) from the array in all directions.
  • The initiation device and the labels are covered in 690.12(C) and 690.12(D).

The history and the technology are in rapid shutdown in solar systems.

The structure of 690.12 in the 2023 edition

  • 690.12(A) names the controlled conductors.
  • 690.12(B) sets the controlled limits, with one set for conductors outside the array boundary and another for conductors inside it.
  • 690.12(C) covers the initiation device.
  • 690.12(D) covers the labels. In 2023 the marking moved here from 690.56(C).

Inside the array boundary, the 2023 edition offers two ways to comply. The first is a listed PV hazard control system (PVHCS) installed per its listing, which UL 3741 evaluates for shock hazard control for firefighters. The second is to limit conductors to 80 V within 30 seconds, with equipment such as limited-voltage equipment, rapid shutdown equipment or a combination.

The 2023 edition also added exceptions. Open structures such as carports and canopies are exempt, and detached arrays whose circuits end at the building exterior are treated differently. Read the exception wording in your edition before you rely on either.

What changed in 2026

Three points matter in 2026.

  1. The voltage and time targets did not change: 80 V and 30 V within 30 seconds.
  2. The language on initiation devices in 690.12(C) was reorganized.
  3. NFPA issued Tentative Interim Amendment (TIA) 26-2, which revises the initiation device text in 690.12(C). A TIA applies where the authority adopts it, so ask whether it has.

The system disconnect rules moved from 690.13 to 705.20 in 2026. That is a separate section from rapid shutdown, but the same switch is often the initiation device, so the drawing notes should point to the correct clause. See the 2026 vs 2023 comparison.

How rapid shutdown is achieved

There are three common equipment strategies:

  • Module-level devices under each module, which drop the voltage at the module when initiation occurs. Microinverters and power optimizers work this way. See string inverter, microinverter or power optimizer.
  • String-level devices at the end of each string, with the module wiring still live inside the boundary unless the module conductors are covered by an alternative.
  • Listed hazard control systems that cover the array and are installed as their listing states.

The choice follows the equipment listing. A rapid shutdown device from one manufacturer can be used with modules or inverters from another only when the listings cover that combination.

Worked example: how many modules per string

This example is illustrative. A real design uses the off-state voltage in the device listing.

Assumptions: a module-level device whose output goes to 4 V per module in the shutdown state, modules with an open-circuit voltage of 49.5 V, and 24 modules per string.

  1. Without devices, a string reads 24 × 49.5 = 1,188 V, far above any limit.
  2. With devices, the string reads 24 × 4 = 96 V inside the array boundary. That is above 80 V, so the design fails.
  3. The largest string that meets 80 V inside the boundary is floor(80 / 4) = 20 modules, which reads 80 V exactly, with no margin.
  4. The string conductors that leave the boundary carry the same 96 V, and the limit there is 30 V. With this device only floor(30 / 4) = 7 modules would pass, so the 4 V device does not suit a 24-module string.
  5. With a device that goes to 1 V per module, the 24-module string reads 24 V, which meets both limits.

The method is the same for any device: modules per string times off-state voltage must not exceed the limit that applies. Use the listing values, not the nameplate output.

Figure: roof array with the array boundary drawn 1 ft around it, the initiation device at the service, and the 80 V and 30 V zones marked.

Checklist for the engineer

  • Confirm the adopted NEC edition, and whether the TIA on 690.12(C) is adopted.
  • Mark the array boundary on the roof plan and state which conductors are inside and which are outside.
  • State the compliance route inside the boundary: PVHCS or 80 V within 30 seconds.
  • Compute modules per string against the off-state voltage in the listing.
  • Show the initiation device, its location and the labels per 690.12(D).
  • Check that modules, inverters and shutdown devices are listed together.
  • Ask the authority and the local fire service whether they require anything beyond the NEC.
  • Check the string-level wiring and the combiner arrangement in string combiner boxes and PV array faults.
  • Cross-check protection under NEC 690.9.

Who signs and seals

A US design normally has to be signed and sealed by a professional engineer licensed in the state of the project. Tiza delivers engineering ready for your engineer of record to review and stamp. Tiza does not sign, seal or certify work in the United States.

How Tiza can help

A rapid shutdown submittal is rejected when the roof plan, the equipment listing and the single-line do not agree. Tiza can perform an independent review of a third-party design, checking the array boundary, the string layout and the labels against the edition your authority enforces. We return a list of comments tied to clauses, ready for your engineer of record to review and stamp. Send the permit set and the equipment data sheets to start. Contact us to start.

Frequently asked questions

What does NEC 690.12 require?

Rapid shutdown of PV system circuits installed on or in buildings. After initiation, conductors inside the array boundary must reach 80 V within 30 seconds, unless a listed PV hazard control system is used. Conductors outside the boundary must reach 30 V within 30 seconds. Initiation devices and labels are covered in the same section.

Does rapid shutdown apply to ground-mounted arrays?

Section 690.12 is aimed at PV circuits on or in buildings. Ground-mounted arrays are generally outside it, and the 2023 edition added exceptions for detached arrays and for non-enclosed structures such as carports. Where an array's circuits enter a building, the rule applies to them. Confirm the application with your authority.

Where is the rapid shutdown label now?

In the 2023 edition the rapid shutdown marking sits in 690.12(D), moved from 690.56(C). The 2026 edition keeps the label requirements in 690.12(D). Use the label wording and placement your authority enforces.

WhatsApp