NEC Article 625 covers electric vehicle power transfer systems. The branch circuit and the overcurrent device for an EVSE are sized at 125 percent of its maximum continuous load. An energy management system can limit the combined load of several chargers so the feeder is sized to the managed limit rather than the sum of the nameplates. Grounding, disconnects, ground-fault protection and ventilation sit in the same article.
NEC article 625 EV charging is the part of the National Electrical Code (NEC, NFPA 70) that governs the equipment which charges an electric vehicle: the electric vehicle supply equipment (EVSE), its circuit, its disconnect and its protection. It applies to a single charger in a garage and to a charging hub with dozens of points.
The wider framework for US codes is in the US electrical codes and grid interconnection guide. For the sizing of a whole station, see how to size an EV charging station. For a home or building installation, see the home EV charger installation checklist.
Section numbers here follow the 2023 edition of the NEC. The 2026 edition is current, but your authority having jurisdiction (AHJ) decides which one applies. In 2026, Article 625 covers on-road vehicles, and the new Article 624 covers charging equipment for other vehicles. Confirm the numbering and local amendments in the adopted edition.
Short answer
Article 625 treats an EVSE as a continuous load. The branch circuit and its overcurrent protection are sized at 125 percent of the maximum load of the equipment (section 625.41). An EVSE above 16 A or above 120 V normally has its own individual branch circuit (section 625.40). The same section lets one circuit serve several chargers when an energy management system, or the adjustable settings of the equipment, limit the load under the conditions of section 625.42. The same article also covers the disconnecting means, ground-fault protection for personnel and the rules for chargers that send power back to a building.
What the article covers
Article 625 is a set of installation rules around one piece of equipment:
- Branch circuit. An individual circuit for the charger, with no other outlets on it, in the usual case.
- Rating. Conductors and overcurrent device above the continuous load, as in the example below.
- Several chargers. The rules that allow a shared circuit with load management.
- Disconnecting means. A way to isolate the charger for service. The exact trigger depends on the equipment rating and the edition.
- Protection of people. Ground-fault protection and the grounding of the equipment.
- Ventilation and location. Some charging equipment and some battery technologies need ventilation or a specific location.
- Power export. Equipment that can send energy from the vehicle to a building or the grid. In the 2023 edition this is recognized as an optional standby source in island mode; interconnection with the utility falls under Article 705.
Load calculations for services and feeders sit in Article 220, which in the 2023 edition includes a rule for EVSE loads. A common reading takes the larger of a fixed minimum and the nameplate rating.
Why 125 percent
A vehicle can draw its full charging current for hours. Heat builds up in breakers, terminals and conductors under that kind of load. The 125 percent factor leaves margin so the circuit is not running at its limit for the whole charge. The same logic appears in other continuous-load rules of the code.
Three consequences follow:
- The breaker is larger than the charger’s current. A 48 A charger needs at least 60 A.
- The conductor needs an ampacity of at least that figure, after terminal temperature limits and correction factors. The ampacity step is the subject of the guide on conductor ampacity under Article 310.
- Setting the charger to a lower current can reduce the circuit rating, but only if the equipment is built for adjustable settings and the setting is protected from casual change. Check this with the manufacturer and the AHJ.
Several chargers on one service
The simple sum is expensive. Six chargers at 48 A each ask for 288 A before the 125 percent factor. Most sites will never charge all vehicles at full power at the same time.
An energy management system measures the load and limits the combined charging current. Section 625.42 in the 2023 edition recognizes this: the service and feeder can be sized to the limit the system enforces, instead of the sum of the nameplates. The practical conditions are:
- The system meets the energy management rules of the code (Article 750 in the 2023 edition).
- The limit is set where only qualified people can change it.
- The behavior on loss of communication is known: the chargers fall back to a safe current, not to full power.
- The feeder and service protection are labelled with the managed limit.
The other branch of the same section covers chargers with adjustable settings. The relationship with service load management and with the other loads of a building is the subject of the guide on protections of a charging station and of the charging modes 1 to 4.
Grounding, disconnects and ground-fault protection
The article calls for the equipment to be grounded and for ground-fault protection of personnel in the charger or upstream. The equipment grounding conductor is sized with Article 250, and the earthing system of a public station deserves its own attention: see grounding and safety at EV charging stations. For heavier chargers, a disconnect within reach of the equipment is part of a serviceable design.
Figure: single-line of a charging site, with the service, feeder, energy management system and six charger circuits.
Worked example: six chargers on a managed feeder
The data are illustrative. Six chargers, each rated 48 A at 240 V single-phase (11.52 kW).
- Individual circuit per charger: 48 × 1.25 = 60 A. Each branch has a 60 A breaker and a conductor with at least that ampacity at the terminal rating.
- Sum of nameplates: 6 × 48 = 288 A. With the 125 percent factor, an unmanaged feeder would need 288 × 1.25 = 360 A.
- An energy management system limits the combined current to 150 A.
- Managed feeder: 150 × 1.25 = 187.5 A, which leads to a 200 A feeder device.
- At the limit, the six vehicles share 150 A, or 25 A each: 6.0 kW per vehicle instead of 11.52 kW. A vehicle that needs 40 kWh at that rate charges in about 6.7 hours.
- The service must carry 187.5 A at the limit plus the other loads of the building. Check the transformer, the service and the available fault current.
The management system gives up charging speed at peak hours. In exchange the feeder drops from 360 A to about 200 A. That decision belongs in the design file, with the load limit written next to the protection.
Common mistakes
- Sizing the breaker at 100 percent of the charger current.
- Putting other outlets on a charger circuit.
- Relying on a load management setting that anyone can change.
- Forgetting that the transformer and service see the managed limit plus the building load.
- Using a section number from one edition on a project that follows another.
Checklist for the engineer
- Confirm the NEC edition and amendments adopted by the AHJ.
- Take the maximum load of each EVSE from its nameplate.
- Size each branch circuit and conductor at 125 percent, with the terminal temperature limit.
- If you manage load, document the system, the limit, the fallback behavior and who can change the setting.
- Size the feeder to the managed limit and label it.
- Check grounding, ground-fault protection and the disconnect.
- Check the transformer, the service and the available fault current.
- If vehicles can export power, separate that scope and follow the interconnection rules.
Who signs and seals
In the United States a design normally has to be signed and sealed by a professional engineer licensed in the state of the project. Charging sites are also reviewed by the AHJ and, in many cases, by the utility.
From the rules to a design your engineer can stamp
Tiza provides engineering design for charging sites: load calculation, single-line diagrams, load management logic and protection ratings, ready for your engineer of record to review and stamp. Tiza does not sign, seal or certify work in the United States. Contact us with the site plan, the charger data and the service details.
Frequently asked questions
How is the branch circuit for an EV charger sized under NEC Article 625?
An EV charger is treated as a continuous load. The overcurrent device and the conductors are sized for 125 percent of the maximum load of the EVSE, as section 625.41 sets out. A 48 A charger therefore needs a circuit rated for at least 60 A. Then the usual conductor corrections and terminal temperature limits apply.
Can several EV chargers share one circuit?
In the 2023 edition, section 625.40 allows one branch circuit to supply more than one EVSE when an energy management system limits the load or the chargers have adjustable settings, under the conditions of 625.42(A) or (B). The circuit is then sized to the limit that the system enforces.
Do I need a new design for the 2026 NEC?
Only if your jurisdiction has adopted the 2026 edition. Many still enforce 2020 or 2023. The section numbers in this guide follow 2023. Check the adopted edition and the local amendments before you finish a design.