NEC Article 700 covers emergency systems: the circuits that keep life-safety loads such as egress lighting running when normal power fails. Power must be available within 10 seconds, the circuits are kept apart from other wiring and serve only emergency loads, transfer equipment is automatic, the system is tested and maintained on a schedule, and the overcurrent devices are selectively coordinated. Legally required standby is Article 701 and optional standby is Article 702.
NEC article 700 emergency systems is the part of the National Electrical Code (NEC, NFPA 70) that governs the circuits meant to keep people safe when normal power fails: egress lighting, exit signs, fire alarm and similar life-safety loads. Its rules are stricter than those for ordinary standby power, because the system has to work at the moment people need it.
The wider framework is in the US electrical codes and grid interconnection guide. The sources of power are covered in diesel emergency plants, and the switching in automatic source transfer.
Section numbers here follow the 2023 edition of the NEC. The 2026 edition is current, but the authority having jurisdiction (AHJ) decides which one applies. Confirm numbering and local amendments in the adopted edition.
Short answer
Article 700 asks for an emergency system that supplies power within 10 seconds of a failure of the normal supply (section 700.12) and serves only emergency loads (700.15). It must have enough capacity for the loads connected (700.4), be tested and maintained with records (700.3), and have selectively coordinated overcurrent devices (700.32). Transfer is automatic and the equipment is identified for emergency use. Two sister articles handle lesser needs: legally required standby (Article 701, 60 seconds) and optional standby (Article 702, no time limit).
Three kinds of standby power
| Article | Purpose | Time to power |
|---|---|---|
| 700, emergency | Life safety: egress, exit signs, alarms | 10 seconds |
| 701, legally required standby | Loads a code or authority requires to be backed up | 60 seconds |
| 702, optional standby | Owner’s choice: comfort, process, data | Set by the owner |
The classification comes from the authority or the building code, not from the designer’s taste. A load placed in the wrong category will be rejected at inspection, or a system built to emergency rules will be expensive for loads that do not need it. The optional category is in the sister guide on NEC Article 702.
What the article asks for
- Capacity (700.4). The source must carry the connected emergency loads, calculated under Article 220 or another approved method.
- Sources (700.12). The article lists the accepted sources, such as storage batteries, generator sets with an automatic start, uninterruptible supplies and unit equipment for lighting, each with its own conditions. Storage batteries, for example, must carry the load for at least 1.5 hours.
- Emergency loads only (700.15). The emergency circuits do not carry other loads.
- Wiring. Emergency wiring is kept separate from other wiring and protected from damage and fire for a set time, with rules on routing and location.
- Illumination (700.16). The failure of one source must not leave a space in total darkness, and some locations, such as an indoor service disconnect, need emergency lighting.
- Signals (700.6). Indication of the state of the emergency source.
- Signs. A sign at the service identifies each power source.
- Commissioning and maintenance (700.3). Acceptance testing, periodic testing and records.
- Selective coordination (700.32). Described below.
Transfer equipment
The transfer equipment is automatic, identified for emergency use, approved by the AHJ and supplies only the emergency loads. A bypass-isolation arrangement is allowed for maintenance, but it has to avoid unintended paralleling of the sources. The short-circuit current rating of the equipment is marked on its exterior. If the system is meant to run in parallel with the utility, the interconnection rules of Article 705 also apply. The difference between open and closed transition is covered in open versus closed transfer.
Selective coordination
When a fault happens in one branch of an emergency system, the goal is that only the nearest device opens. Otherwise a fault in one light fixture could take out a whole floor of egress lighting. Section 700.32 asks that the overcurrent devices of the emergency system be selectively coordinated with all the devices on the supply side. A qualified person selects them, the study is documented, and it is checked again when devices are replaced or the system changes.
In practice this means a coordination study: the time-current curves of each device, the available fault current at each point and the choice of breakers or fuses that do not overlap. The method is the one explained for protection studies in general, and the same data feed the available fault current marking of the switchgear. Coordination also constrains the product: not every breaker family can be coordinated with the one upstream at high fault levels, and the result can decide the choice of equipment.
Testing and records
The system is tested when it is commissioned, and the AHJ may witness the test. Later it is tested on a schedule and maintained, and the records are kept. The scope of the tests depends on the sources. A generator set needs an operational test with load, a battery needs a capacity check, and transfer equipment needs a functional test. The guide on generator set sizing and the standards for the engine side (for example NFPA 110 for emergency power supply systems) complement the NEC.
Figure: single-line of an emergency system with a utility supply, a generator, an automatic transfer switch and the emergency distribution panel with the life-safety branches.
Worked example: capacity and timing of a small emergency system
The data are illustrative. A building has these emergency loads at 208 V, three-phase:
- Egress and exit lighting: 12 kW.
- Fire alarm and communications: 3 kW.
- Smoke control fan: 22 kW.
- Elevator recall and controls: 8 kW.
- Connected load: 12 + 3 + 22 + 8 = 45 kW. Emergency loads are normally taken at full value, without a diversity factor, unless the code allows another method.
- Current at an assumed power factor of 0.9: 45,000 / (1.732 × 208 × 0.9) = 138.8 A.
- Margin: 45 × 1.25 = 56.3 kW for a generator that must also start the fan. A generator rated 60 kW or larger covers the running load. The start of the fan motor and the voltage dip are checked separately: see motor starting with a generator set.
- Transfer equipment: an automatic transfer switch rated above 139 A, for example 200 A. Its short-circuit rating, with its protective device, must be at least the available fault current at its terminals (assumed 22 kA).
- Timing: engine start and voltage build-up of 4 s plus transfer of 2 s gives 6 s (assumed), inside the 10 s limit with margin.
- Coordination: the devices from the generator to each branch are checked on time-current curves so that a fault on one lighting branch opens only that branch device.
The numbers show the structure of the check. Real equipment data replace the assumptions.
Common mistakes
- Putting non-emergency loads on emergency circuits.
- Measuring the 10 seconds from the generator start only, not from the loss of power to the loads.
- Ignoring coordination until the equipment is bought.
- Sharing raceways between emergency and normal wiring.
- Skipping the test records.
- Using a transfer switch not identified for emergency use.
Checklist for the engineer
- Confirm the NEC edition and amendments adopted by the AHJ.
- Classify each load: emergency, legally required standby or optional.
- Calculate capacity, with the starting of the largest motor.
- Select the source and verify the 10-second timing.
- Select transfer equipment and mark its short-circuit rating.
- Keep emergency wiring and circuits separate.
- Perform the coordination study and keep it with the project.
- Plan commissioning tests and the maintenance schedule.
Who signs and seals
In the United States a design normally has to be signed and sealed by a professional engineer licensed in the state of the project. The fire authority and the AHJ approve emergency systems, and they often witness the acceptance test.
From the rules to a design your engineer can stamp
Tiza provides engineering design and studies for emergency power: load classification, capacity and timing checks, single-line diagrams and the selective coordination study, ready for your engineer of record to review and stamp, remotely and in English. Tiza does not sign, seal or certify work in the United States. Contact us with the drawings, the load list and the equipment data.
Frequently asked questions
How fast must emergency power be available under NEC Article 700?
Section 700.12 requires emergency power to be available within 10 seconds of the loss of the normal supply. Legally required standby systems under Article 701 are given 60 seconds. The time is measured at the loads, so the start of the generator and the operation of the transfer equipment both count.
What is selective coordination in an emergency system?
It means that when a fault occurs, only the overcurrent device closest to the fault opens, and the rest of the emergency system stays energized. Section 700.32 asks for it, requires a qualified person to select the devices and asks for a new check when devices are replaced or the system changes.
Can an emergency system supply loads other than emergency loads?
No. Section 700.15 restricts the emergency circuits to emergency loads. Other loads that need backup belong to legally required standby under Article 701 or optional standby under Article 702, with their own transfer arrangement.