NEC Article 702 covers optional standby systems: backup power the owner chooses to have, such as a generator for a shop, a house or a data room. The system must be sized for the loads it is meant to run at the same time, and listed transfer equipment must stop the standby source and the utility from ever being connected together. Outside dwellings the short-circuit rating of the transfer equipment is marked on it, and portable generator inlets carry a warning sign about the neutral arrangement. Emergency and legally required standby are Articles 700 and 701.
NEC article 702 optional standby is the part of the National Electrical Code (NEC, NFPA 70) that governs backup power chosen by the owner: a generator for a shop that cannot stop, a house in a storm area, a communications room. No code asks for it, so the rules concentrate on one thing: that the backup source is installed safely and cannot backfeed the utility.
The wider framework is in the US electrical codes and grid interconnection guide. Its life-safety sister is NEC Article 700. The equipment side is in automatic source transfer and open versus closed transfer.
Section numbers here follow the 2023 edition of the NEC. The 2026 edition is current, but the authority having jurisdiction (AHJ) decides which one applies. Confirm numbering and local amendments in the adopted edition.
Short answer
Article 702 asks for two things. The standby source must have enough capacity for the loads it will run (section 702.4), and listed transfer equipment must keep the utility and the standby source from feeding the premises wiring at the same time (section 702.5). Outside dwelling units the short-circuit rating of the transfer equipment is marked on its exterior, and a portable generator inlet has a sign stating whether it accepts a generator with a bonded neutral (separately derived system) or not. Article 702 does not ask for the 10-second restart of emergency systems or for selective coordination.
Where optional standby sits
An optional standby system exists because the owner wants it. If a code or an authority requires the load to be backed up, it is legally required standby under Article 701, and if it protects life it is an emergency system under Article 700. The classification is made by the building code and the authority. A system can mix them: an emergency generator that also feeds optional loads must be arranged so that the optional loads cannot take capacity from the emergency ones. See the capacity discussion in NEC Article 700.
Capacity: section 702.4
The capacity rule depends on how the transfer happens:
- Manual transfer. The generator is sized for the loads the user intends to run at one time. The user decides which loads to connect, and the design must make that selection clear and practical.
- Automatic transfer. The generator carries the full load that transfers automatically, calculated under Article 220 or another approved method.
- Load management. If an energy management system keeps the connected load under a limit, the system is sized to the maximum load it permits. The system must be reliable, because the safety of the generator depends on it.
Capacity is more than running kilowatts. The starting of motors and the voltage dip matter, and so do harmonics from drives and the power factor. The sizing method is explained in sizing a generator set.
Transfer equipment: section 702.5
The transfer equipment connects the standby source to the premises wiring. The rules:
- The equipment is listed for the purpose.
- It is installed so that all sources are prevented from being connected at the same time.
- Outside dwelling units, the short-circuit current rating of the equipment is field-marked on the outside, based on the protecting device type and settings.
- If the system runs in parallel with the utility, the interconnection rules of Article 705 apply.
The reasons are simple. A generator connected to the building while the utility is also connected can be damaged by the first closing, and a generator connected to a dead utility line can energize it and injure a lineworker. Transfer equipment is the barrier, and a manual switch must be listed like an automatic one.
Signs and portable generators
For a portable generator connected through an inlet, a warning sign near the inlet states whether the wiring of the transfer equipment calls for a separately derived system (bonded neutral) or not (floating neutral). That way a generator with the wrong neutral arrangement is not plugged in. Section 702.7 covers the sign requirements. Grounding and the treatment of the neutral depend on whether the transfer equipment switches the neutral, which is a design decision for the engineer, and on the generator type. Section 702.12 adds rules for outdoor generator sets, such as the disconnect and power inlets of 100 A or more. The general generator rules are in Article 445.
Figure: single-line of an optional standby system with a utility supply, a manual or automatic transfer switch, a generator and the selected loads.
Worked example: a shop with manual transfer
The data are illustrative. A shop has a 240 V single-phase service. The owner wants to keep these loads running with a generator:
- HVAC unit: 4.8 kW running.
- Refrigeration: 1.2 kW.
- Lighting: 2.0 kW.
- Water pump: 1.5 kW.
- Controls and network: 0.5 kW.
- Loads intended to run together: 4.8 + 1.2 + 2.0 + 1.5 + 0.5 = 10.0 kW.
- Current at 240 V: 10,000 / 240 = 41.7 A.
- Choose a 14 kW generator: its rated current is 14,000 / 240 = 58.3 A. The running load is 10 / 14 = 71 percent.
- Starting: the HVAC compressor starts at an assumed three times its running current. The extra demand is 2 × 4.8 = 9.6 kW, so the peak is 10.0 + 9.6 = 19.6 kW. If the generator can carry a short overload of 1.5 times its rating (assumed, check with the supplier), it carries 21 kW for a short time, and the start is feasible. Starting the HVAC first, before the other loads, lowers the peak.
- Transfer equipment: a listed manual transfer switch rated above 58 A, with a short-circuit rating marked outside the equipment if this is not a dwelling.
- The generator inlet or the fixed connection has the sign and the grounding arrangement chosen by the designer.
If the same shop used automatic transfer, the generator would need to carry all the loads that transfer, not the ones the owner picks.
Common mistakes
- Sizing the generator for the running load only.
- Using a transfer device that is not listed.
- Forgetting the short-circuit rating marking outside dwellings.
- Assuming a portable generator needs no transfer switch.
- Mixing optional loads into an emergency system without a way to shed them.
- Ignoring the utility’s own requirements for backup generators.
Checklist for the engineer
- Confirm the NEC edition and amendments adopted by the AHJ.
- Classify the loads: optional, legally required or emergency.
- Choose manual or automatic transfer and size under 702.4.
- Check motor starting and voltage dip.
- Select listed transfer equipment and mark its short-circuit rating where required.
- Decide how the neutral and the grounding are handled at the transfer switch.
- Add the sign for any portable generator inlet.
- Check the generator installation rules and the fuel and location requirements.
Who signs and seals
In the United States a design normally has to be signed and sealed by a professional engineer licensed in the state of the project. For small residential systems local rules differ, and the AHJ and the utility have their say.
From the rules to a design your engineer can stamp
Tiza provides engineering design for standby power: load lists, generator and transfer equipment sizing, single-line diagrams and protection checks, ready for your engineer of record to review and stamp. Tiza does not sign, seal or certify work in the United States. Contact us with the load list and the service data.
Frequently asked questions
What does a transfer switch have to do under NEC Article 702?
Section 702.5 requires listed interconnection or transfer equipment, installed so that the utility and the standby source cannot be connected to the premises wiring at the same time. The rule covers permanent and portable generators. A transfer switch also protects utility workers from backfeed.
How is an optional standby generator sized under 702.4?
With manual transfer, the generator is sized for the loads the user intends to run at the same time, and the user chooses which loads to connect. With automatic transfer, it is sized for the full load that transfers automatically, calculated under Article 220 or another approved method. An energy management system can limit the load, and then the limit is the basis.
Does Article 702 require selective coordination or the 10-second rule?
No. Those belong to emergency systems under Article 700. Optional standby has no time limit for power to return and no mandatory coordination study, though good practice still checks protection and fault current.