PJM replaced its first-come, first-served queue with a cycle process where projects must show readiness to enter. Existing queue projects moved through transition cycles. Cycle 1 of the Reformed Interconnection Process closed its application window on 27 April 2026, and PJM reported 715 projects accepted into the study. Projects pass through three phases with decision points where they may continue or withdraw.
Short answer
The PJM interconnection process is now cycle-based. PJM, the regional transmission organization (RTO) for much of the Mid-Atlantic and Midwest, replaced its first-come, first-served queue with a first-ready, first-served process. Projects enter a cycle only after showing readiness. Older queue projects moved in through transition cycles. PJM calls the new process the Reformed Interconnection Process. Its Cycle 1 closed its application window on 27 April 2026, and PJM announced the accepted projects on 3 August 2026. The federal background, set by the Federal Energy Regulatory Commission (FERC), is in FERC Order 2023 cluster studies. For the US framework, see the US electrical codes and grid interconnection guide.
How the process is organized
The reform moved PJM from a serial queue to cycles. Tariff Parts VII and IX took effect on 3 January 2023, and the transition date was 10 July 2023. The groups are:
- Transition Cycle 1. Projects from the older AE1 to AG1 queues. At the first decision point, projects could reduce their maximum facility output or capacity interconnection rights, with limits on fuel changes and on moving the point of interconnection.
- Transition Cycle 2. Projects from the AG2 to AH1 queues, which had to resubmit under the new requirements. Maximum output and capacity rights could not increase, and fuel type could not change except to remove one.
- Cycle 1. Projects from the AH2 and later queues resubmit. Fuel type may change at reapplication but not at a decision point.
The tariff also sets conditions for site control and equipment data in each group.
Cycle 1 in numbers
PJM announced on 3 August 2026 that the Cycle 1 window drew 811 proposals and 715 projects were accepted for study, with about 201.5 GW of nameplate capacity. By count, storage was the largest group, and by capacity, natural gas was. PJM notes that these are maximum potential outputs and that only part of the projects will reach operation. PJM describes Cycle 1 as a study of one to two years, depending on a project’s impact, and published the study models in the weeks after the announcement. PJM expects completion of Transition Cycle 2 in early 2027 and of Cycle 1 in 2028.
PJM publishes the current Phase I schedule on its service request status pages. Use that schedule for planning, because dates move.
Phases and decision points
Projects accepted into a cycle are batched with peers and pass through three phases, with a decision point after each. PJM publishes the study models so that developers can understand the impact and decide whether to continue or withdraw. Financial deposits fund the studies, and as phases advance more of the deposits become non-refundable. A developer therefore weighs, at each decision point, the study result against what leaving would cost.
What a project must show to enter is similar to other operators: site control, a signed application and studies agreement, study deposits and readiness payments. The same cluster logic exists in the other regions, as the guides on CAISO and MISO show. Texas works differently, as the ERCOT guide explains. For the study stages in general, see interconnection study stages explained.
Worked example (illustrative)
The first part uses PJM’s reported numbers. The second uses assumptions to show attrition.
Part 1. From PJM’s figures.
- Acceptance rate: 715 ÷ 811 = 0.882, so about 88 percent of proposals were accepted.
- Average size of an accepted project: 201.5 GW ÷ 715 = 0.282 GW, about 282 MW.
Part 2. Assumed attrition. Suppose a cycle of 100 projects loses 20 percent at the first decision point, 15 percent at the second and 10 percent at the third. These withdrawal rates are assumptions, not PJM data.
- After decision point 1: 100 × 0.80 = 80 projects.
- After decision point 2: 80 × 0.85 = 68 projects.
- After decision point 3: 68 × 0.90 = 61.2, so about 61 projects.
Reading the result. Roughly four in ten projects leave in this assumed case. Each exit can change the cost shares of the others, so a developer should check how sensitive the project is to a lower share of the cluster before the decision point.
Checklist for the engineer
- Confirm which group the project is in: transition cycle or Cycle 1.
- Read PJM’s current manuals and tariff for the cycle and its deadlines.
- Prepare site control, equipment data and models before the window opens.
- Understand what each deposit buys and when it becomes non-refundable.
- Test the project’s sensitivity to withdrawals of others in the cluster.
- Review the point of interconnection and the options allowed at each decision point.
- Have the engineer of record review the study results before each decision.
Legal frame
The process above is general orientation. PJM’s tariff, manuals and notices decide each case, and they change often. Tiza does not sign, seal or certify work in the United States. We deliver studies and engineering ready for your engineer of record to review and stamp.
How Tiza can help
A screening before each decision point shows how a result could change if other projects withdraw. Tiza provides power-system studies, ready for your engineer of record to review and stamp. Contact us with your single-line diagram and the PJM study results you have.
Figure: timeline of a PJM cycle with the application window, the three phases and the decision point after each.
Related guides
- Which interconnection study each market requires
- Electrical codes and grid connection compared by country
- NERC MOD-032 and MOD-033 steady-state and dynamic data
- IEEE 2800 model and simulation requirements
References
- PJM, Interconnection Process Reform page (transition cycles and Cycle 1 rules).
- PJM Inside Lines, announcement of the projects accepted into Cycle 1 (3 August 2026).
- PJM Open Access Transmission Tariff, Parts VII and IX.
Frequently asked questions
What is PJM's Reformed Interconnection Process?
It is the cycle-based process that replaced the serial queue. Projects apply in a window, prove readiness with site control and deposits, and are studied together in phases. PJM describes it as first-ready, first-served.
What are the transition cycles?
They moved projects that were already in the old queue into the new process in groups. Transition Cycle 1 and Transition Cycle 2 each had decision points where projects could reduce size or withdraw. Projects in later queues resubmit in Cycle 1.
What does a decision point mean for a developer?
It is a step where the developer sees study results and chooses to continue, adjust within the allowed limits or withdraw. Deposits become non-refundable as the phases advance, so the choice has a cost.