PCC Relay Settings for DER: 27, 59, 81 and 67

PCC relay settings for DER: what the main breaker relay does, how 27, 59, 81 and 67 are chosen and a worked per unit to relay secondary conversion, simply.

By Shadai García, CEO and protection engineer at Tiza Group.

gridPCCVTCTmainbreakerVTPCC relay: 27 / 59 / 81 / 6725 sync-checkbattery-backedDC supplytransfer trip input=~inverter plantPowerMeasure / controlCommsVT 7200:120 V = 60:1, nominal 7200 V27: 0.88 × 7200 = 6336 V = 105.6 V59: 1.10 × 7200 = 7920 V = 132 Vfast stages: 60.0 V and 144 V92.6 × 1.25 = 115.7 A = 3.86 A on 5 Arelay secondary voltage, V120 V nominal27 fast 60.027 105.659 13259 fast 144pick-up current: 3.86 A of a 5 A input012345 Aillustrative values; time delays come from the utilityPCC relayVT / CT27 / 59 / 816725Trip© tizagrp.comgridPCCVTCTmainbreakerVTPCC relay: 27 / 59 / 81 / 6725 sync-checkbattery-backedDC supplytransfer trip input=~inverter plantPowerMeasure / controlCommsVT 7200:120 V = 60:1, nominal 7200 V27: 0.88 × 7200 = 6336 V = 105.6 V59: 1.10 × 7200 = 7920 V = 132 Vfast stages: 60.0 V and 144 V92.6 × 1.25 = 115.7 A = 3.86 A on 5 Arelay secondary voltage, V120 V nominal27 fast 60.027 105.659 13259 fast 144pick-up current: 3.86 A of a 5 A input012345 Aillustrative values; time delays come from the utilityPCC relayVT / CT27 / 59 / 816725Trip© tizagrp.com
Point of common coupling relay of a distributed generator: a voltage transformer, a current transformer, the main breaker and a second voltage transformer feeding a relay with undervoltage 27, overvoltage 59, frequency 81, directional 67 and synchronism check 25 that trips the breaker, a battery backed supply, a yellow dashed transfer trip input, with the worked conversion of per unit values on 7200 to 120 volts to 105.6, 132, 60 and 144 volts and 3.86 amperes on a 150 to 5 current transformer. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

The relay that trips the main breaker at the point of common coupling is where a distributed generator meets the utility's rules. It combines voltage and frequency functions, a directional or overcurrent function and a trip path that must work without the grid. The values come from the utility's requirements and the study, and the engineer's work is to convert them correctly to the relay's secondary side.

The main breaker of a distributed generation site is the device the utility trusts to separate the plant. The relay that controls it, usually at the point of common coupling, has to meet the utility’s requirements and the plant’s own protection needs. Its settings must also be converted to the relay’s secondary side without error.

The point itself is explained in PCC vs RPA in IEEE 1547, and the wider context is in the US electrical codes and grid interconnection guide.

Short answer

A PCC relay for distributed energy resources normally combines undervoltage 27, overvoltage 59, frequency 81 and an overcurrent or directional function, and it trips the main breaker. The utility sets or limits the values, referring to IEEE 1547-2018 and its own studies. The engineer’s task is to take per-unit values, convert them with the correct voltage and current transformer ratios, check that they coordinate with the plant and the utility, and record them for review. The relay is a generator-side interface to the grid, not a copy of the utility’s own protection.

What each function does

  • 27 and 59. They separate the plant when voltage leaves an allowed band for a stated time. Time delays let the plant ride through short events, as explained in voltage ride-through categories.
  • 81U and 81O. Same idea for frequency. See frequency ride-through and trip settings.
  • 67 or 32. A directional function that reacts to current flowing towards or away from the utility. Used to detect faults on the feeder or, with a threshold, reverse or export power.
  • 50/51 and 50N/51N. Overcurrent protection of the connection and the transformer.
  • 59N on a broken-delta VT winding. Detects ground faults in some configurations, as in neutral overvoltage protection 59N.
  • 25. Synchronism check for closing the main breaker.
  • Transfer trip input. Trips the breaker when the utility sends the signal. See transfer trip requirements.

The trip path must work without the grid. Many designs use a battery-backed supply for the relay and the breaker coil, and the utility often asks for it.

The main breaker as a separation device

The breaker is also the device that the utility will operate or ask to be operated. It needs an interrupting rating above the available fault current at the point of common coupling, including the plant’s own contribution. The utility’s lockable disconnect, where required, is a separate device. The relay, the breaker and the disconnect should be shown on the single-line with the current and voltage transformers that feed them.

Worked example: converting to the secondary side (illustrative)

Assumptions, all illustrative: a 2 MW plant at 12.47 kV. The voltage transformers are 7200:120 V, wye connected, so the ratio is 60:1 on line-to-neutral values. The current transformers are 150:5, ratio 30:1. The utility’s requirement, in this example, gives the values in per unit of nominal.

Voltage functions (nominal line-to-neutral = 7200 V, secondary 120 V):

FunctionPer unitPrimarySecondary
27 pickup0.886336 V105.6 V
27 fast stage0.503600 V60.0 V
59 pickup1.107920 V132 V
59 fast stage1.208640 V144 V

The time delays come from the utility’s requirement and are entered as given.

Overcurrent. Plant rated current = 2 MW / (√3 × 12.47 kV) = 92.6 A. With a 1.25 factor for the pickup: 115.7 A primary, which is 115.7 / 30 = 3.86 A secondary. The relay input is 5 A nominal, so 3.86 A is within range. The utility will compare this with its own device to confirm coordination.

Frequency. Values are in hertz and need no conversion, for example an 81O pickup of 60.5 Hz, as an assumed figure.

If the relay measured line-to-line values from the same wye VTs, the same per-unit values would apply to 12.47 kV primary and 208 V secondary. The base is the point where mistakes are made, so write the base next to every value.

Common mistakes

The errors that reach review are values entered on the wrong base and a voltage function fed from a transformer that is not at the point of common coupling. Others are time delays that do not allow the ride-through the standard describes, and a trip source that depends on the grid. A second calculation by another person, using a different route to the same secondary value, catches them before the utility does.

Checklist for the engineer

  • Get the utility’s functions and values in writing, with the edition of the standard they refer to.
  • Confirm the voltage base and the VT and CT ratios and connections.
  • Convert every value to the secondary side and recalculate with a second method.
  • Check the CT saturation margin at the maximum fault current.
  • Confirm the trip source and its behaviour without the grid.
  • Confirm the transfer trip input, if any, and its supervision.
  • Record the settings in a sheet the utility can review, as in relay setting submittals.

Who signs and seals

Protection settings for a US interconnection are normally reviewed and stamped by a professional engineer licensed in the state of the project. Tiza delivers engineering and studies ready for your engineer of record to review and stamp. Tiza does not stamp, sign or certify work in the United States.

How Tiza can help

If the PCC relay needs its settings calculated and its configuration prepared, Tiza delivers remote relay and inverter configuration, in English, with the settings sheet ready for your engineer of record to review and stamp. Contact us with the utility’s requirements and the relay model.

References

  • IEEE 1547-2018 and amendment 1547a-2020, for the abnormal voltage and frequency response of distributed energy resources.
  • The utility’s interconnection handbook or technical manual, which gives the values it requires.

Figure: single-line of the point of common coupling with the main breaker, the relay fed from current and voltage transformers, the trip path and the transfer trip input as a dashed line.

Frequently asked questions

Which functions does a PCC relay for DER usually have?

Undervoltage 27, overvoltage 59, under and over frequency 81U and 81O, and an overcurrent or directional function such as 50/51 or 67. Many utilities add synchronism check 25 for closing and a transfer trip input. The utility's document lists what it requires.

Who sets the values?

The utility states the required values or the allowed range, based on IEEE 1547-2018 and its own study. The customer's engineer converts them to the relay and documents them. The utility reviews the result.

Can the inverter's built-in protection replace the PCC relay?

For small systems many utilities accept the listed inverter's functions. For larger plants or where the main breaker must separate the plant, a separate relay is common. Ask the utility which applies to your size.