IEEE 1547-2018 sorts abnormal-voltage behavior into performance categories I, II and III, while categories A and B belong to voltage regulation. The category sets how long an inverter must keep operating through a voltage sag or swell before it may stop. The inverter's current limit caps the power it can deliver during a sag, and the utility sets the category.
IEEE 1547 category I, II, III voltage ride-through is often confused with category A and B. They answer different questions. The background is in the IEEE 1547-2018 guide and the wider US electrical codes and grid interconnection guide.
This guide is based on IEEE 1547-2018 (active, amended by 1547a-2020). IEEE has a revision in development.
Short answer
IEEE 1547-2018 defines three abnormal operating performance categories, I, II and III. They set how a DER behaves during abnormal voltage and frequency. Category III asks for the most ride-through. It suits grids with a lot of DER, because a sag that trips many inverters at once can turn a local event into a system problem. Categories A and B are a separate pair that set reactive power and voltage regulation capability.
Ride-through means the inverter stays connected and keeps operating, or at least resumes, through a defined disturbance instead of tripping. The standard describes ranges of voltage and time. In each range the DER must either operate continuously, operate while in a mandatory region, or may stop under defined conditions.
Why categories exist
An older rule was simple: trip fast if the voltage left a narrow band. That protected one site but removed generation exactly when the grid needed it. The categories let the utility match the requirement to the penetration of DER on its system. A feeder with little DER can accept a lower category. A region with high penetration needs the highest one.
Voltage bands of the highest category
In category III, continuous operation applies between 0.88 and 1.10 per unit voltage. Mandatory operation applies for sags down to 0.50 per unit, for a time that is longer at higher voltage. Below 0.50 per unit the DER enters momentary cessation. Above 1.20 per unit it ceases to energize. The time for each band is in the standard, and the trip settings that apply are in your utility’s settings document.
What the inverter does during a sag
During a sag the inverter sees a lower terminal voltage, but its current limit stays the same. The available power falls with voltage. Many inverters also give priority to reactive current to support voltage, or reduce active current. On recovery they ramp back, and the rate is part of the setting.
Below the lowest voltage range the standard allows the inverter to stop injecting current momentarily, called momentary cessation, and then resume. That behavior matters because a stopped inverter feeds no fault current, and a fast restart changes what the protection sees.
Worked example: power available during a sag
This is illustrative, with our own hypotheses. A 250 kVA inverter at 480 V line-to-line has a current limit of 1.10 times its rated current, and it prioritizes active current.
- Rated current: 250,000 / (1.732 × 480) = 300.7 A.
- Current limit: 1.10 × 300.7 = 330.8 A.
- A sag to 0.50 per unit puts the terminal voltage at 240 V.
- Apparent power at the limit: 1.732 × 240 × 330.8 = 137.5 kVA.
- That is 137.5 / 250 = 0.55 of the rated power.
With these hypotheses, the inverter cannot deliver more than 55% of its rating during the sag, even if it stays online. A design that counts on full output through a deep sag overstates the support. The real current limit comes from the manufacturer’s data sheet.
Swells and the other side of the band
Ride-through applies to high voltage as well. A swell can follow a fault clearing, a capacitor switching or the loss of a large load. The inverter must tolerate a defined overvoltage for a short time, and beyond the top of the range it ceases to energize. Overvoltage ride-through is less visible than the sag case. It matters on weak feeders with a lot of generation, where the trip of one plant lifts the voltage seen by its neighbors.
Why the category is a system decision
The inverter owner usually wants the lowest-cost option. The utility wants the highest category where DER is dense. Ask for the category early, because a higher one can need different equipment or firmware. It can also change the project economics when an older inverter model is only certified to a lower category. The choice is documented in the interconnection agreement, and the settings record at commissioning should state it.
How to check it in a design
- Ask the utility which abnormal performance category applies and which voltage categories apply, and in writing.
- Confirm the inverter is capable of that category, according to its certified documentation.
- Confirm the settings are loaded as the utility requires and are not left at factory values.
- Check the plant controller and the protective relays at the point of connection. A relay setting that trips faster than the inverter ride-through defeats it. See the guide on inverter disconnections from the grid.
- Check the voltage measurement point. See the guide on the point of common coupling and reference point.
- Consider the industrial load side too. A sag that the inverter rides through can still stop the plant’s drives; see voltage sags in industry.
Checklist for the engineer
- Record the edition, the category and the source document for each value.
- Compare relay and inverter settings in one table.
- Document the current limit and the priority mode used in the studies.
- Keep the evidence of the settings applied at commissioning.
- Note the sister guide on frequency ride-through and trip settings.
Who signs and seals
For work in the United States, drawings and studies are normally signed and sealed by a professional engineer licensed in the state of the project. We deliver engineering ready for your engineer of record to review and stamp. Tiza does not sign, seal or certify work in the United States.
Our remote relay and inverter configuration service prepares the settings plan for the ride-through values your utility requires. Your engineer of record can review it before the inverter is commissioned. Contact us with the inverter model and the utility’s settings document.
Frequently asked questions
Are category A and B the same as category I, II and III?
No. Categories A and B describe voltage regulation capability, such as reactive power. Categories I, II and III describe abnormal operating performance, which includes voltage and frequency ride-through. A project is assigned one of each, and the two choices are independent.
Which ride-through category does the utility choose?
The utility, the state commission or the interconnection rules choose it, based on how much DER is on the system. The inverter must be capable of the category, and the site must be configured for it. The highest category is meant for areas with a lot of DER.
Does ride-through mean the inverter keeps injecting power during a sag?
Not always at full power. Depending on the settings, the inverter may keep injecting current, reduce it or briefly stop and then resume. The inverter's current limit also caps how much power it can deliver while voltage is low.