IEEE 1547 Point of Applicability: PCC vs RPA

IEEE 1547 point of applicability explained simply: PCC, point of DER connection and reference point of applicability, with a worked voltage offset example.

By Shadai García, CEO and protection engineer at Tiza Group.

=~=~=~480 V inverters, 500 kWcable 0.6%1,000 kVA5.75%, X/R 5MV breakerWmeterutilityPoCRPA candidateor RPA candidatePCCMVrelayPowerControltransformer R: 5.75 / sqrt(1 + 5²) = 1.13%P = 0.5 per unit on 1,000 kVAtransformer: 1.13% x 0.5 = 0.56%cable: 0.6% x 0.5 = 0.30%total 0.56 + 0.30 = 0.86%, about 0.9%voltage rise PCC to inverter (%)0.56%transformer0.30%cable0.86%totalOffsetResistancePowerTransformerCableTotal© tizagrp.com=~=~=~480 V inverters, 500 kWcable 0.6%1,000 kVA5.75%, X/R 5MV breakerWmeterutilityPoCRPA candidateor RPA candidatePCCMVrelayPowerControltransformer R: 5.75 / sqrt(1 + 5²) = 1.13%P = 0.5 per unit on 1,000 kVAtransformer: 1.13% x 0.5 = 0.56%cable: 0.6% x 0.5 = 0.30%total 0.56 + 0.30 = 0.86%, about 0.9%voltage rise PCC to inverter (%)0.56%transformer0.30%cable0.86%totalOffsetResistancePowerTransformerCableTotal© tizagrp.com
IEEE 1547 points of applicability: 480 V inverters, a cable, a 1,000 kVA step-up transformer, an MV breaker and meter to the utility, with the PoC, two RPA candidates and the PCC marked, and the 0.56 plus 0.30, 0.86 percent voltage offset at 500 kW. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

IEEE 1547-2018 applies its requirements at a reference point of applicability: the point of common coupling or the point of DER connection, chosen by conditions set in the standard. Choosing it changes where voltage is measured and how a plant is tested. The voltage between the two points can differ by about 1 percent at full output.

Every requirement in IEEE 1547 has to be checked somewhere. That place is the point of applicability, and getting it wrong shifts measurements, settings and tests. The background is in the IEEE 1547-2018 guide and the US electrical codes and grid interconnection guide.

This guide is based on IEEE 1547-2018 (active, amended by 1547a-2020). IEEE has a revision in development.

Short answer

IEEE 1547-2018 uses three terms:

  • Point of common coupling (PCC): the point where the local electric power system (the customer side) connects to the area electric power system (the utility).
  • Point of DER connection (PoC): the point where an individual DER unit connects to the local system.
  • Reference point of applicability (RPA): the point where the performance requirements apply and compliance is assessed.

Clause 4.2 of the standard decides whether the RPA is the PCC or the PoC. The decision looks at whether zero-sequence continuity is kept in the local system, at the annual average load compared with 10% of the DER rating, and at whether the aggregate DER rating exceeds 500 kVA. A point between the two is also allowed under specified conditions. The utility confirms the result.

Why it matters

The voltage and frequency at the PCC are not the same as at the inverter terminals. Between them are cables, a transformer and sometimes other loads. If the rule says “measure at the PCC” and the inverter measures at its own terminals, its voltage-dependent functions react to a slightly different voltage.

It also decides how the plant is tested. If the RPA is the PoC, a certified unit can be accepted as a unit. If it is the PCC, the whole plant, including equipment between the two points, has to be shown to meet the requirements, usually through design evaluation and commissioning tests.

Where the points sit in a typical plant

Take a plant with several inverters, a step-up transformer and a meter. The layout runs from the inverters at 480 V to a transformer, a medium-voltage breaker, the utility meter and the line. The PoC is at each inverter output. The PCC is at the utility side of the plant. The point between them could be the low-voltage bus or the high-voltage side of the transformer. Which one is the RPA is a documented agreement.

Worked example: voltage difference between PoC and PCC

This is illustrative, with our own data. A 500 kW inverter output at unity power factor feeds a 1,000 kVA step-up transformer with 5.75% impedance and an X/R ratio of 5. A cable between the inverter and the transformer has 0.6% resistance on the 1,000 kVA base. We estimate the voltage rise from the PCC to the inverter terminals with a simple per-unit approximation, ΔV ≈ R × P. Reactance has little effect at unity power factor.

  1. Transformer resistance: 5.75 / sqrt(1 + 5²) = 1.13%.
  2. Active power in per unit on 1,000 kVA: 0.5.
  3. Transformer rise: 1.13% × 0.5 = 0.56%.
  4. Cable rise: 0.6% × 0.5 = 0.30%.
  5. Total: 0.56 + 0.30 = 0.86%.

So the inverter terminals sit about 0.9% above the PCC voltage at that output. Suppose the utility asks for a voltage function referenced to the PCC. If the curve has a narrow dead band, a 0.9% offset can change the reactive power the inverter produces. The offset grows with power and with reactive flow, so compute it at several operating points.

Several units and shared equipment

When a plant has more than one DER, the standard looks at the whole group at the point where the requirements apply. Two 250 kVA units are not judged one by one if the RPA is the PCC. The sum of their behavior is. This matters for reactive power, where the units add up, and for islanding, where the units can influence each other.

Storage and solar behind the same transformer are also treated together. If a load sits between the DER and the PCC, it nets against the output. A 400 kW load next to a 500 kW inverter means the PCC sees only 100 kW of export. The standard’s requirements are written for the DER, so the documentation must say clearly how the netting is handled and what is measured where.

How to handle it in a design

Questions to put to the utility

  • Where does the utility place the PCC for this project?
  • Does it accept the point of DER connection as the reference point?
  • Is the metering point the same as the PCC?
  • How does it want equipment between the points to be evaluated?
  • Does the answer change if more units are added later?

Checklist for the engineer

  • PCC, PoC and RPA marked on the single-line diagram.
  • Utility confirmation of the RPA, with the date and the reference.
  • Impedance data between the points, to compute the offset.
  • Measurement and settings reference points consistent across inverter, plant controller and relays.
  • List of equipment between the RPA and the PCC and how its effect was evaluated.

Who signs and seals

In the United States, drawings and studies are normally signed and sealed by a professional engineer licensed in the state of the project. Our work is delivered ready for your engineer of record to review and stamp. Tiza does not sign, seal or certify work in the United States.

Our engineering design service prepares the single-line diagram with the three points marked and the offset calculation, ready for your engineer of record to review and stamp. Contact us with the single-line diagram and the impedance data.

Frequently asked questions

What is the reference point of applicability in IEEE 1547?

It is the physical point where the standard's performance requirements apply and compliance is assessed. It is the point of common coupling or the point of DER connection, depending on conditions set in clause 4.2 of the standard. A point in between is also allowed under specified conditions.

What is the difference between PCC and point of DER connection?

The point of common coupling is where the local electric power system meets the utility system. The point of DER connection is where an individual DER unit connects inside the local system. With several units or a transformer in between, they are different places.

Who decides the reference point?

The characteristics of the local system and the DER determine it under the standard, and the utility confirms it in the interconnection process. Agree it in writing early, because relay and test planning depend on it.