IEEE 1547.1-2020 defines how to test that distributed energy resources conform to IEEE 1547-2018. It covers type, production, commissioning and periodic tests, plus design and installation evaluations. In the US, type tests are usually run by a recognized laboratory and appear as a UL 1741 listing. A listing does not prove the timing of the complete system on site.
Meeting a requirement and proving it are different jobs. IEEE 1547 says what a DER must do, and IEEE 1547.1 says how to show it. The background is in the IEEE 1547-2018 guide and the US electrical codes and grid interconnection guide.
This guide is based on IEEE 1547.1-2020, the edition in force. IEEE lists a revision as in preparation, with no publication date.
Short answer
IEEE 1547.1-2020 specifies the type, production, commissioning and periodic tests, and the evaluations, that show a DER conforms to IEEE 1547-2018. Type tests are normally run by a recognized laboratory, and in the US the result usually appears as a UL 1741 listing that includes Supplement SB. Production tests are run on every unit. Commissioning tests are run in the field. Periodic tests are repeated while the DER is in service.
The test types, in plain words
| Type | When | Where | What it proves |
|---|---|---|---|
| Design evaluation | Before installation | Desk | The proposed installation can meet the requirements |
| Type test | Once per design | Laboratory | The product design can meet them |
| Production test | Every unit | Factory | This unit matches the tested design |
| Commissioning test | After installation | Site | This installed system meets them |
| Periodic test | During service | Site | It still does |
Why type tests are not enough
A type test shows the inverter on its own. A real site adds an external relay, a plant controller, a transformer and cables. Those parts can add delay or change the measurement point. The standard recognizes this. Where the type test does not cover the whole chain, production or commissioning tests have to show the full system response, such as its timing.
UL 1741 SB in the picture
UL 1741 with Supplement SB is how inverters are certified in the US against the grid-support behavior of IEEE 1547-2018, using the procedures of IEEE 1547.1-2020. The certificate names UL 1741. A project test plan should therefore refer to the certificate and treat the IEEE standards as the requirements and procedures behind it. For the relation among the inverter standards, see PV inverter standards.
Worked example: timing budget of a complete system
This is illustrative, with our own data. The utility requires the plant to stop energizing within 2.0 s of an island forming (see anti-islanding). The inverter’s type test result is 1.20 s. The site adds an external interface relay with 0.25 s of delay and a contactor with 0.08 s of operating time.
- Total chain: 1.20 + 0.25 + 0.08 = 1.53 s.
- Margin to the limit: 2.00 − 1.53 = 0.47 s, or 23.5% of the limit.
- If the relay delay were 0.80 s, the chain would be 2.08 s and the plant would fail the requirement, even though the inverter passed its type test.
A commissioning test with the whole chain would show the 2.08 s. That is the reason to ask for system-level evidence and not only a listing.
Who runs what
Tests only count when the right party owns them and the evidence is kept.
The manufacturer arranges the type tests and the production tests. The installer or the commissioning engineer runs the commissioning tests, often witnessed by the utility. The owner is responsible for periodic tests when they are required. In a design review the question is not only whether a test exists but who owns it. A test without an owner is easily skipped.
Test equipment and records
Commissioning tests need measurement equipment that is calibrated and a source that can reproduce the condition, such as a controlled voltage or frequency step. In the field this often means a relay test set or the inverter’s own test mode, depending on what the utility accepts. Keep the raw record, the settings file and the instrument details together. An auditor, or the utility years later, will ask for them.
What to ask for in a design review
- The certificate and its scope: model, firmware version and the document it names.
- Which parts of the system sit outside the certified equipment.
- The commissioning test plan: what is measured, how and who witnesses.
- The settings in the file the inverter holds, matched to the utility’s list.
- A record of any later firmware change and a re-check if it affects grid functions.
Related field checks are in on-site PV inverter tests and solar plant commissioning tests.
Questions to put to the utility
- Which tests does it require and which does it accept from a certificate?
- Does it need to witness commissioning?
- What records does it keep, and in what format?
- How often are periodic tests required, if at all?
- What happens after a firmware change?
Checklist for the engineer
- Certificate for each inverter model, with firmware.
- Reference point of applicability agreed; see point of common coupling and reference point.
- Timing budget for every protective function that goes through external devices.
- Commissioning procedure approved by the utility before the visit.
- Records kept for the owner and the utility.
Who signs and seals
In the United States, drawings and studies are normally signed and sealed by a professional engineer licensed in the state of the project. Our work is delivered ready for your engineer of record to review and stamp. Tiza does not sign, seal or certify work in the United States.
Our independent review of a third-party design checks the test plan, the settings and the timing budget against the utility’s requirements. Your engineer of record then has a second look before commissioning. Contact us with the test plan and the utility’s requirements.
Frequently asked questions
What is the difference between a type test and a commissioning test?
A type test is run once on a representative unit, usually in a laboratory, and shows the design can meet the requirement. A commissioning test is run on the installed system on site and shows this installation does. Both can be needed for the same project.
Is IEEE 1547.1 the same as UL 1741 SB?
No. IEEE 1547.1-2020 defines the test procedures. UL 1741 with Supplement SB is the certification route that applies those procedures to inverters. The listing names UL 1741, so the test plan should refer to the document the certificate names.
Is a revision of IEEE 1547.1 coming?
IEEE lists a revision project as approved in 2026, with no publication date. Until it is published, 1547.1-2020 is the edition to cite.