Volt-var, watt-var and volt-watt are the voltage-support functions of a smart inverter under IEEE 1547-2018. Each one changes the inverter's output according to a curve, either from the local voltage or from its own power. The utility chooses the functions and curves, and the inverter's apparent power limits the reactive power available.
A high-voltage problem on a solar feeder has a solution inside the inverter. The background is in the IEEE 1547-2018 guide and the US electrical codes and grid interconnection guide.
This guide is based on IEEE 1547-2018 (active, amended by 1547a-2020). IEEE has a revision in development.
Short answer
IEEE 1547-2018 requires a DER to be capable of several voltage-support functions. Three matter most:
- Volt-var: reactive power as a function of the local voltage. High voltage makes the inverter absorb reactive power, which lowers the voltage.
- Watt-var: reactive power as a function of the inverter’s active power. More output means more reactive absorption.
- Volt-watt: active power reduced as the voltage rises above a set level.
The standard sets the capabilities and the allowed range of each curve. The utility decides which functions to enable. The reactive power capability itself depends on the voltage regulation performance category (A or B) assigned to the project.
How a curve works
A volt-var curve is a polyline with a few points. In the middle is a dead band where reactive power is zero. Above the upper point the inverter absorbs reactive power, increasing with voltage until it reaches a maximum. Below the lower point it injects. The slope sets how aggressively it responds.
Too steep and the inverter hunts, with voltage and reactive power oscillating. Too flat and it does little. Volt-watt is the last resort: it only acts when the voltage rises so far that reactive absorption is not enough, because it reduces energy.
The reactive range depends on the inverter’s apparent power. An inverter whose kVA rating equals its kW rating has no reactive headroom at full output. IEEE 1547-2018 asks for the reactive capability at rated active power, so a compliant DER has a kVA rating above its kW rating. The guide on solar panels and power factor shows the customer-side view of the same effect, and capacitive reactive power covers the opposite problem.
Worked example: one point on a curve
This is illustrative, with our own curve and not a utility setting. A 100 kVA inverter delivers 90 kW. The hypothetical volt-var curve is flat at zero up to 1.02 per unit, then absorbs linearly up to 0.44 per unit of the rating at 1.06 per unit. The feeder voltage is 1.04 per unit.
- Position on the slope: (1.04 − 1.02) / (1.06 − 1.02) = 0.50.
- Reactive power: 0.50 × 0.44 × 100 kVA = 22.0 kvar absorbed.
- Headroom check: sqrt(100² − 90²) = 43.6 kvar available at 90 kW, so 22.0 kvar fits.
- Apparent power: sqrt(90² + 22²) = 92.6 kVA, below the 100 kVA rating.
The curve asks for 22.0 kvar and the inverter can supply 43.6 kvar, so it does not hit its limit. At 1.06 per unit the curve would ask for 44.0 kvar, just above 43.6 kvar. The inverter would then cap reactive power or reduce active power, depending on its priority setting. That is the check an engineer should run.
Why not just use a fixed power factor
A fixed power factor is simple, and some utilities still accept it. It does not react to the feeder. At noon with high generation and low load, a fixed value may absorb too little. At night, with no generation, it does nothing. A volt-var curve works only when the voltage needs it, so it uses less of the inverter capacity and gives the utility a response that follows the grid. Watt-var is a middle path, because the reaction follows the inverter’s own output and needs no voltage measurement.
Interaction with other functions
The functions share the same inverter capacity. Reactive power takes room that active power could use, and volt-watt takes active power back when the voltage is still high. A design should list the order of priority. It should also confirm that the curves do not push against each other. One example is a volt-var curve that absorbs at a voltage where a plant-level power factor control asks the inverter to inject.
Checks in a design
- Confirm which functions the utility enables and which curve each uses.
- Confirm the priority mode: active power first or reactive power first.
- Confirm the voltage reference point; see point of common coupling and reference point.
- Confirm that the plant power factor requirement, if any, does not conflict with the curve.
- Confirm firmware: some functions arrive with updates, as noted in inverter firmware: secure updates.
- Verify on site; see on-site PV inverter tests.
Questions to put to the utility
- Which functions are enabled by default and which only on request?
- Is the volt-var curve fixed, or can the utility update it remotely?
- Is the reference voltage measured at the inverter or at the point of applicability?
- Is there a limit on how much active power may be curtailed by volt-watt?
- How is compliance shown at commissioning: a screenshot, a test or a measured response?
Checklist for the engineer
- The utility’s curve points and priority mode, in writing.
- Reactive headroom at the plant’s maximum output.
- The setting file or screenshot saved at commissioning.
- A voltage profile along the feeder with and without the functions, if the utility provides it.
- Who can change these settings later, and how that is recorded.
Who signs and seals
In the United States, drawings and studies are normally signed and sealed by a professional engineer licensed in the state of the project. We deliver studies ready for your engineer of record to review and stamp. Tiza does not sign, seal or certify work in the United States.
Our power-system studies can check voltage and reactive power along the feeder for the curves your utility proposes, so your engineer of record can review the results. Contact us with the feeder data and the proposed curves.
Frequently asked questions
What is the difference between volt-var and watt-var?
Volt-var sets reactive power from the local voltage. Watt-var sets reactive power from the inverter's own active power. Volt-var reacts to the grid, while watt-var follows the inverter's output.
What does volt-watt do?
Volt-watt reduces active power when the voltage rises above a set level, which relieves overvoltage on weak feeders. It costs energy production, so the curve is chosen with the utility.
Who chooses the curve values?
The utility or the interconnection rules choose which functions are enabled and with which curve. The standard says what the inverter must be able to do. The values are a settings decision and are checked at commissioning.