IEEE 1547 Interconnection Standard: 2018 Guide

What the IEEE 1547 interconnection standard requires of solar and storage inverters in the US: ride-through, voltage control, islanding and communications.

By Shadai García, CEO and protection engineer at Tiza Group.

=~=~=~=~4 x 250 kVAinverters480 V bus1,000 kVAstep-upbreakerWmeterutility feederPoCRPA candidatePCCplantcontrollerDER to utility interfacePowerControlCommunications250,000 / (1.732 x 480) = 300.7 A4 x 300.7 = 1,202.8 A at 480 V1,000,000 / (1.732 x 12,470) = 46.3 Ascreened at 1,000 kVA, not at the loadsrated current (A)300.7 Aone inverter480 V1,202.8 Afour inverters480 V bus46.3 A12.47 kV sideutility viewCurrentsOne inverterFour inverters12.47 kV sideScreeningClosing© tizagrp.com=~=~=~=~4 x 250 kVAinverters480 V bus1,000 kVAstep-upbreakerWmeterutility feederPoCRPA candidatePCCplantcontrollerDER to utility interfacePowerControlCommunications250,000 / (1.732 x 480) = 300.7 A4 x 300.7 = 1,202.8 A at 480 V1,000,000 / (1.732 x 12,470) = 46.3 Ascreened at 1,000 kVA, not at the loadsrated current (A)300.7 Aone inverter480 V1,202.8 Afour inverters480 V bus46.3 A12.47 kV sideutility viewCurrentsOne inverterFour inverters12.47 kV sideScreeningClosing© tizagrp.com
IEEE 1547 interconnection: four 250 kVA inverters on a 480 V bus, a 1,000 kVA step-up transformer, breaker and meter to a 12.47 kV feeder, with the PoC, RPA candidate and PCC marked and the 300.7 A, 1,202.8 A and 46.3 A currents. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

IEEE 1547-2018 is the technical standard that tells a distributed energy resource how to behave when it is connected to a US distribution system. It covers ride-through, voltage regulation, response to abnormal grid conditions, unintentional islanding and communications. The utility or state commission applies it, and a listed inverter proves it.

The IEEE 1547 interconnection standard is the document a utility cites when it asks how a solar array, battery or generator must behave on the distribution grid. It is the technical core of layer 2 in the US electrical codes and grid interconnection guide.

This guide is based on IEEE 1547-2018 and its amendment 1547a-2020, both active. IEEE has a revision in development.

Short answer

IEEE 1547-2018 is titled “Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces”. It applies to distributed energy resources (DER) connected to a distribution system, from a rooftop inverter to a multi-megawatt plant. It defines what the DER must do at its reference point of applicability. That covers how it rides through disturbances and how it supports voltage. It also covers when it must stop, how it reacts to an island and how it talks to the utility.

It does not cover wiring or protection of the installation. That is the National Electrical Code (NEC), checked by the local inspector. The two documents are enforced by different offices, as the guide on NEC 705.13 power control systems also explains for the installation side.

What the standard covers

The main requirement blocks are:

How the standard reaches your project

  1. IEEE publishes the standard. It does not enforce it.
  2. A state commission or utility adopts it in its interconnection rules, sometimes with its own settings.
  3. The equipment manufacturer gets the inverter certified. In the US this is usually done by listing to UL 1741, as the guide on PV inverter standards describes.
  4. The designer configures the settings the utility asks for.
  5. The utility reviews the design, witnesses or accepts commissioning, and grants permission to operate.

Steps 2 and 4 are where projects go wrong. The standard sets what a DER must be capable of; the utility chooses which functions to enable and with which values.

Performance categories in one paragraph

IEEE 1547-2018 groups requirements into categories. Abnormal operating performance has three categories (I, II and III), which differ in how long the DER must ride through disturbances. The highest category is designed for areas with a lot of DER, where losing many units together would hurt the grid. Voltage regulation performance has two categories (A and B), which differ in reactive power capability. The category that applies is chosen by the utility or the interconnection rules, and the manufacturer must be able to meet it.

Worked example: nameplate to interconnection current

This is illustrative, with our own data. A site has four 250 kVA inverters at 480 V, three-phase, connected through one 1,000 kVA step-up transformer to a 12.47 kV feeder.

  1. Rated current of one inverter: 250,000 / (1.732 × 480) = 300.7 A.
  2. Four inverters on the 480 V bus: 4 × 300.7 = 1,202.8 A.
  3. Rated current on the 12.47 kV side: 1,000,000 / (1.732 × 12,470) = 46.3 A.

The utility screens the project by the total DER nameplate at the connection point, here 1,000 kVA, not by the sum of loads. The 46.3 A on the 12.47 kV side is the figure for the utility protection discussion. The 1,202.8 A on the low-voltage side is what the busbar, breakers and conductors must carry, using the NEC rules.

Common mistakes

  • Treating a listing as the whole approval. The inverter certificate says what the equipment can do. The utility still needs to see the settings it asked for and, often, a commissioning record.
  • Assuming one edition everywhere. One utility may still apply an earlier interconnection standard, while a neighbor has moved to the 2018 edition. The tariff or interconnection agreement is the reference, not the date of publication.
  • Mixing the installation code with the interconnection standard. A correct NEC design can still fail the utility review over a wrong ride-through setting. The reverse also happens.
  • Leaving factory settings. Inverters ship with generic values. If nobody loads the utility’s values, the site passes the paper review and fails the field check.
  • Ignoring communications until the end. The interface and the protocol have to be agreed early, because they affect equipment selection and network design.

Where the standard sits in the project timeline

At the application stage the utility wants the single-line diagram, the equipment data and the nameplate. During the design review it wants the settings plan and the reference point of applicability. Before energizing it wants the commissioning plan, and after energizing it keeps the records for the life of the interconnection. A change of inverter model or firmware later can reopen the review, so keep the file complete from the first day.

Checklist for the engineer

  • Confirm the edition of IEEE 1547 your utility has adopted, and any amendment.
  • Identify the performance categories the utility requires.
  • Collect the utility’s required settings for ride-through, voltage functions and trip.
  • Confirm the inverter listing and that its firmware version matches the certified one.
  • Define the reference point of applicability with the utility.
  • Confirm the communication interface and the protocol the utility will use.
  • Plan commissioning checks and who will witness them.
  • For cyber security of the DER interface, see IEEE 1547.3 instead of repeating it here.

Who signs and seals

In the United States, electrical drawings and studies for an interconnection are normally signed and sealed by a professional engineer licensed in the state of the project. Our engineering is delivered ready for your engineer of record to review and stamp. Tiza does not sign, seal or certify work in the United States.

Our engineering design service prepares the single-line diagram, the settings package and the data the utility asks for, so that your engineer of record can review and stamp it. Contact us with the single-line diagram and the utility’s requirements.

Frequently asked questions

Is the IEEE 1547 interconnection standard a law?

No. It is a voluntary technical standard. It becomes mandatory when a utility, a state commission or an interconnection tariff requires it. Your interconnection agreement states which edition applies.

Which edition of IEEE 1547 is current?

IEEE 1547-2018, amended by 1547a-2020, is the active edition. IEEE lists a revision as in development, with no publication date. Check which edition your utility has adopted, because adoption often lags publication.

Does an inverter listed to UL 1741 automatically meet IEEE 1547?

A listing covers the equipment tested in the lab. The site must still use the settings the utility requires and pass any commissioning checks. Listing is necessary for most utilities, but it is only one part of the approval.