A distributed generator that connects to a US distribution system follows a process set by the state and the utility: application, screening, possibly supplemental review or a study, an interconnection agreement, construction, a witnessed commissioning test and permission to operate. The screens compare the generator with the circuit's load and fault duty. The better the engineering package at the start, the fewer questions come back.
Every US distribution utility runs an interconnection process, and every one writes it a little differently. The steps are similar, though: from application to permission to operate, with screens in between and a package that keeps the review moving.
Where the process sits among the other US documents is in the US electrical codes and grid interconnection guide. California’s version is covered in Rule 21 distribution interconnection, and the transmission-level studies in interconnection studies explained.
Short answer
The US distribution interconnection process normally runs in this order: application, completeness check, screening, supplemental review or study if a screen fails, interconnection agreement, construction, commissioning and permission to operate. The rules come from the state commission and the utility’s interconnection procedures or tariff. The technical base is IEEE 1547-2018 (with amendment 1547a-2020), and equipment is usually expected to be listed to UL 1741. Read the utility’s own document first, because the screens, fees and timelines differ.
The usual steps
- Application. The form, a single-line diagram, equipment data sheets, a site plan and proof of site control. Utilities often ask for the inverter listing and the settings of the interface protection.
- Completeness check. The utility confirms the package is complete. Missing items pause the review.
- Screening. A set of tests applied to the generator and the circuit. A project that passes all of them usually proceeds without a study.
- Supplemental review or study. If a screen fails, the utility examines the specific concern. Some utilities offer a defined supplemental review. Larger or more complex projects go to an impact study and a facilities study.
- Interconnection agreement. The legal and technical terms, including who pays for utility-side upgrades.
- Construction and commissioning. The customer builds. The utility often witnesses the commissioning test of the protection and the anti-islanding function.
- Permission to operate. Issued after the utility accepts the test results and the as-built drawings.
What the screens test
Published procedures differ in number and thresholds, but the questions are consistent:
- Penetration. How large is the generator compared with the load of the line section, peak or minimum depending on the screen? A high ratio raises the risk of an island and of reverse power flow.
- Fault current. Does the contribution of the new generator push any device past its interrupting rating, or change protection coordination?
- Voltage. Does the generator raise or lower the voltage at the point of common coupling beyond what the utility accepts?
- Interconnection type. Is the connection to a shared transformer, a radial feeder, or a network? Networks have extra restrictions.
- Existing generation. What is already connected upstream, and does the total change the picture?
The point of common coupling and the unintentional islanding limit come up in most of these questions.
Worked example: a penetration screen (illustrative)
Assumptions, all illustrative: a 1.2 MW inverter plant on a 12.47 kV feeder. The feeder’s minimum daytime load is 2.4 MW. Existing generation on the feeder is 0.3 MW. The utility’s screen, in this example, sends a project to supplemental review when aggregate generation exceeds 50 % of minimum load.
- Aggregate generation = 1.2 + 0.3 = 1.5 MW.
- Ratio to minimum load = 1.5 / 2.4 = 0.625, or 62.5 %.
- 62.5 % is above 50 %, so the project goes to supplemental review.
The fault current check uses the rated current: I = 1.2 MW / (√3 × 12.47 kV) = 55.6 A. An inverter limits its output to a small multiple of rated current. At 1.1 per unit that is about 61 A, well under 1 % of an assumed 8 kA available at the point of connection. The fault screen passes easily. A synchronous generator of the same size with a subtransient reactance of 0.15 per unit would give about 370 A, which is why the utility asks for the machine type.
The outcome is not a rejection. The supplemental review would look at islanding risk and may ask for a transfer trip, which is covered in anti-islanding and transfer trip requirements.
The package that moves the process
- A single-line diagram with protective devices, instrument transformers and the point of common coupling marked.
- Inverter and transformer data, including the transformer winding connection and impedance.
- The proposed interface protection and its settings, as described in PCC relay settings for DER.
- A short protection description: functions, trip path, test points.
- The commissioning test plan.
The utility’s protection requirements for solar explain what these documents are usually measured against.
Checklist for the engineer
- Obtain the utility’s current interconnection procedures and the state rules, and note their dates.
- Confirm the circuit’s minimum load and the available fault current with the utility, in writing.
- Run the penetration and fault screens yourself before applying.
- Confirm whether the circuit is radial or networked.
- Prepare the single-line, equipment data and settings as separate documents.
- Confirm the commissioning test and who witnesses it.
- Keep the utility’s responses and the application dates in one record.
Who signs and seals
Interconnection drawings and protection studies for a US project are normally reviewed and stamped by a professional engineer licensed in the state of the project. Tiza delivers engineering and studies ready for your engineer of record to review and stamp. Tiza does not stamp, sign or certify work in the United States.
How Tiza can help
If the application needs a clean protection package, Tiza prepares the engineering design remotely, in English, ready for your engineer of record to review and stamp. Contact us with the utility’s procedures and the single-line, and we will scope it with you.
Related guides
- US electrical codes and grid interconnection guide
- California Rule 21 distribution interconnection
- Coordination with the utility’s protection
- Relay setting submittals to utilities
References
- IEEE 1547-2018 and amendment 1547a-2020, interconnection and interoperability of distributed energy resources.
- UL 1741, equipment listing for inverters and other grid-support equipment.
- The interconnection procedures or tariff of the utility that owns the circuit, and the rules of the state commission.
Figure: the interconnection process as a flow from application to permission to operate, with the screens and the supplemental review as a branch.
Frequently asked questions
What is the first step in a distribution interconnection?
A complete application to the utility that owns the circuit, with a single-line diagram, equipment data and site control. Many utilities publish the form and the fee schedule in their interconnection procedures or tariff. An incomplete application stops the clock until the missing items arrive.
What happens if the project fails a screen?
Failing a screen does not reject the project. It sends it to a supplemental review or a study, where the utility checks the specific concern, such as minimum load, fault current or voltage. The result can be a mitigation such as a transfer trip, a different transformer connection or an upgrade.
Who decides the technical requirements?
The utility applies its own interconnection procedures, set within the rules of the state commission. IEEE 1547 supplies the technical base. The utility's published handbook or tariff states which version applies and what it adds.