Tiza Group

Home / Guides / Codes and grid connection: US, UK, CA, AU

NEC 110.24 Available Fault Current Marking Explained

NEC 110.24 available fault current marking: where the label goes, what it records, when it must be updated, and how it differs from an arc flash label.

By Shadai García, CEO and protection engineer at Tiza Group.

source750 kVA, 5.75 %1,000 kVA, 5.75 %480Y/277 V serviceMmotors 350 A+ 1,400 Aavailable current17.1 kA22.3 kAsource 15,689 Asource 20,918 Asource: 902.1 / 0.0575 = 15,689 A+ motors 4 x 350 = 1,400 A: 17.1 kA1,000 kVA: source 20,918 Atotal 22.3 kA: redo label, recheckavailable current (kA)20 kA panelboard17.1 kA750 kVA22.3 kA1,000 kVAtransformermotorsMarkingSourceMotor contributionCalculationMarkingRecheck© tizagrp.comsource750 kVA, 5.75 %1,000 kVA, 5.75 %480Y/277 V serviceMmotors 350 A+ 1,400 Aavailable current17.1 kA22.3 kAsource 15,689 Asource 20,918 Asource: 902.1 / 0.0575 = 15,689 A+ motors 4 x 350 = 1,400 A: 17.1 kA1,000 kVA: source 20,918 Atotal 22.3 kA: redo label, recheckavailable current (kA)20 kA panelboard17.1 kA750 kVA22.3 kA1,000 kVAtransformermotorsMarkingSourceMotor contributionCalculationMarkingRecheck© tizagrp.com
NEC 110.24 on a 480Y/277 V service: transformer and motor contributions to the available fault current, the field marking at the service, and the new value after a 750 kVA transformer is replaced by 1,000 kVA. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

NEC section 110.24 requires service equipment in other than dwelling units to be marked in the field with the maximum available fault current and the date the calculation was made. When a modification changes the available fault current, the calculation is redone and the marking updated. The label is an equipment-rating check, not an arc flash label, and it needs a documented short-circuit study behind it.

NEC 110.24 available fault current marking is one of the quiet requirements of the National Electrical Code (NEC, NFPA 70). It asks for a number and a date on the equipment, and it only works if someone has done the short-circuit study first.

The US code angle covers where the marking applies, what it must say and when it must change. The wider framework is in the US electrical codes and grid interconnection guide. The technical basis of the number is in the existing guide on the short-circuit study.

Section numbers here follow the 2023 edition of the NEC. Confirm the numbering and local amendments in the edition your authority having jurisdiction (AHJ) has adopted.

Short answer

Section 110.24(A) requires service equipment in other than dwelling units to be field marked with the maximum available fault current and the date the calculation was performed. Section 110.24(B) requires the calculation to be redone and the marking adjusted when modifications change the available fault current. The marking helps the inspector and the maintainer check that equipment ratings are enough for the fault current that can reach it.

What the marking is for

A circuit breaker, a switchboard or a motor controller has a rating that tells what fault current it can handle. If the source is stronger than that rating, the equipment can fail violently in a fault. The marking puts the available current on the equipment so anyone can compare the two numbers without looking through the drawings.

The same idea is behind the rating rules for assemblies. For switchboards and panelboards, the sister guide on NEC Article 408 explains how the short-circuit current rating is compared with this value. For control panels, see NEC Article 409.

What the label says and where it goes

The marking records two things: the maximum available fault current and the date the calculation was made. It goes on the service equipment, in a place where the inspector can see it. The date matters because the value is only as good as the system it was calculated for.

Three limits keep the marking in its place:

  • It does not apply to dwelling units.
  • It is not an arc flash label. Arc flash labeling is a separate requirement, explained in the guide on NEC 110.16 arc flash labeling.
  • It is not a substitute for the study. The calculation has to exist and has to be kept.

What the number depends on

The available fault current at a point is not a property of the equipment. It comes from the system:

  1. The utility source. The utility provides the available fault current or the equivalent impedance at the service point. Ask for it in writing and note the date.
  2. The transformer. Its size and impedance set the largest part of the current at low voltage.
  3. Conductors between the source and the point. Length and size reduce the current as distance grows.
  4. Motors and other local sources. Running motors feed current into a fault for the first cycles. Inverter-based sources add a smaller contribution.

The usual practice is to calculate the maximum value, because the marking is a safety limit and not a typical-condition figure. For the technical method, see the guides on low-voltage short-circuit calculation and on X/R ratio and the peak of the fault current.

When the marking must change

Section 110.24(B) ties the update to a change in the available fault current. Examples are a larger transformer, a new utility feed, extra generation on site or a change in the cable path. The new calculation produces a new value and a new date.

A change that does not affect the available current, such as adding a feeder breaker, does not require a new number. But the new equipment still has to have a rating at least equal to the marked value.

Figure: service equipment fed by a transformer and a motor load, with the fault current marking and its calculation date shown on the equipment.

Worked example: a transformer replacement

The data are illustrative, not from a project. A 750 kVA transformer, 5.75% impedance, feeds a 480Y/277 V service. Running motors total 350 A. A rule of thumb for the contribution of induction motors in the first cycle is four times their full-load current. Treat it as an assumption, and replace it with data from the study.

  1. Full-load current of the transformer: I = 750,000 / (1.732 × 480) = 902.1 A.
  2. Available current from the source, infinite bus: 902.1 / 0.0575 = 15,689 A.
  3. Motor contribution: 4 × 350 = 1,400 A.
  4. Total at the service: 15,689 + 1,400 = 17,089 A, which rounds to 17.1 kA. The label would read 17.1 kA and carry the calculation date.
  5. The owner replaces the transformer with a 1,000 kVA unit of the same impedance. New full-load current: 1,000,000 / (1.732 × 480) = 1,202.8 A.
  6. Available current from the source: 1,202.8 / 0.0575 = 20,918 A. Adding 1,400 A gives 22,318 A, or 22.3 kA.
  7. The label must be redone, from 17.1 kA to 22.3 kA, with a new date. Every device and every assembly downstream must be rechecked against 22.3 kA. A 20 kA panelboard that was fine before is now short.

The point is the sequence: calculate, mark, and recheck whenever the source changes.

Checklist for the engineer

  • Confirm the NEC edition and amendments adopted by the AHJ.
  • Request the utility’s available fault current data in writing and keep the date.
  • Calculate the maximum available fault current at the service equipment and record the assumptions.
  • Include contribution from motors and from any on-site generation.
  • Compare the result with the rating of every device and assembly on the system.
  • Mark the equipment with the value and the date of the calculation.
  • Plan the update: every modification that touches the source or the impedance triggers a new calculation.
  • Keep the calculation where the people who inspect or maintain the equipment can find it.

Who signs and seals

In the United States a design normally has to be signed and sealed by a professional engineer licensed in the state of the project. The fault current calculation belongs with the engineer of record or the engineer who performs the study.

From the label to a study your engineer of record can stamp

A label is only as reliable as the study behind it. Tiza prepares power-system studies, including short-circuit calculations, ready for your engineer of record to review and stamp, remotely and in English. Tiza does not sign, seal or certify work in the United States. Contact us with the single-line diagram, the utility data and the equipment list.

Frequently asked questions

What is the difference between the 110.24 label and an arc flash label?

The 110.24 label records the maximum available fault current and the date it was calculated, so equipment ratings can be checked against it. An arc flash label records the incident energy or protective equipment level for a worker. They use related data, but they answer different questions and the fault current label is not meant to be used for the arc flash analysis.

Does the label have to be updated when the utility or the plant changes?

Yes, when a change affects the available fault current. A new transformer, a changed utility source or added generation can all raise it. The calculation is redone and the marking is adjusted, so the date on the label stays meaningful.

Who calculates the available fault current?

The code does not name who performs it, but the calculation should be documented and done by someone competent in short-circuit studies. On most projects the engineer of record or the study engineer provides the value, using the utility's available fault current data and the plant's equipment data.

WhatsApp