Ground Fault Overvoltage and Grounding Transformers

Ground fault overvoltage from DER: effective grounding, the X0/X1 ratio, when a grounding transformer is required and a worked example of its impedance.

By Shadai García, CEO and protection engineer at Tiza Group.

substationfeeder breakerground faultdelta,utility side=~inverter plantzig-zagbankNeutral relayCTPowerMeasure / controlhealthy-phase voltage against X0/X1X0/X1 = 3 gives 1.25 puno zero-sequence path: about 1.73 puX1 = 0.06 × 77.7 = 4.67 ohm; limit 14.0 ohm8 / 4.67 = 1.71; I = 1246 A, 415 A per phase11.0021.1531.2551.38101.52ungrounded1.7301.01.5 puillustrative values; sequence reactances as in the guideGroundingGround faultIslandDelta windingGrounding bankNeutral relay© tizagrp.comsubstationfeeder breakerground faultdelta,utility side=~inverter plantzig-zagbankNeutral relayCTPowerMeasure / controlhealthy-phase voltage against X0/X1X0/X1 = 3 gives 1.25 puno zero-sequence path: about 1.73 puX1 = 0.06 × 77.7 = 4.67 ohm; limit 14.0 ohm8 / 4.67 = 1.71; I = 1246 A, 415 A per phase11.0021.1531.2551.38101.52ungrounded1.7301.01.5 puillustrative values; sequence reactances as in the guideGroundingGround faultIslandDelta windingGrounding bankNeutral relay© tizagrp.com
Ground fault overvoltage of a distributed generator: a feeder with a ground fault cleared by the substation breaker, an interconnection transformer whose delta winding faces the utility so it gives no zero sequence path, and a zig-zag grounding transformer on the utility side with a current transformer in its neutral feeding a relay, with the healthy phase voltage of 1.00 to 1.73 per unit against the ratio X0 over X1 and the worked example of an 8 ohm bank giving a ratio of 1.71. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

When a ground fault on a utility feeder is cleared at the substation, a distributed generator that stays connected can leave the island without a grounded source. The unfaulted phases then rise towards line-to-line voltage and can damage arresters and customer equipment. Utilities therefore ask for an effectively grounded source, judged by the ratio of zero-sequence to positive-sequence reactance, and sometimes require a grounding transformer.

Imagine a ground fault on a 12.47 kV feeder. The substation breaker opens and clears it. A solar plant behind the fault stays connected for a moment. What the plant’s transformer does with the neutral decides whether the healthy phases stay near normal or rise towards the line-to-line voltage. That is ground fault overvoltage, and it is a reason for many utility requirements on transformer connections.

The broader context is in the US electrical codes and grid interconnection guide and in grounding practice by country.

Short answer

Ground fault overvoltage appears when an island stays energized from a source that has no path for zero-sequence current. In that case the healthy phases can reach about 1.73 per unit. Utilities limit it by requiring an effectively grounded source, usually judged with the ratio of zero-sequence to positive-sequence reactance, X0/X1, together with the resistance ratio. A generator connection that does not meet this on its own can add a grounding transformer. The reference documents are the IEEE C62.92 guide series, in particular C62.92.1-2016, C62.92.4-2014 for distribution systems and C62.92.6-2017 for current-regulated sources such as inverters, and the requirements of the utility.

Why the island matters

The risk is not the fault itself, which the utility clears. The risk is the moment after: the utility source opens and the plant, if it has not tripped, feeds the feeder section with the fault still present. If the plant’s connection offers no zero-sequence path, the neutral floats and the voltage on the healthy phases rises. Arresters rated for the normal level can fail, and so can other customers’ equipment. Fast anti-islanding and transfer trip reduce the time, and a grounded source reduces the level. See unintentional islanding in IEEE 1547.

What the ratio tells you

For a phase-to-ground fault with no fault resistance, the voltage on a healthy phase depends on X0/X1. The table uses equal positive and negative sequence reactance and a purely reactive zero sequence. The results are calculated with symmetrical components, in per unit of the normal line-to-neutral voltage.

X0/X1Healthy phase voltage (pu)
11.00
21.15
31.25
51.38
101.52
very large (ungrounded)1.73

At X0/X1 = 3 the voltage is 1.25 pu, which is 0.72 of the line-to-line value of 1.73 pu. This is why the 80 % coefficient and the limit of 3 are used together as an approximation. For inverter sources, the ratios used for rotating machines do not apply directly, and many utilities state their own criteria. Confirm them with your utility.

Transformer connections and grounding transformers

The connection of the interconnection transformer sets the zero-sequence path:

  • Grounded wye on the utility side, with a delta winding on the generator side. The transformer itself is a zero-sequence source for the feeder, so it holds down the healthy phases. It also adds ground fault current that can desensitize the utility’s ground relays, and the utility may ask for a neutral impedance.
  • Grounded wye on both sides. Often the preferred connection on four-wire multi-grounded circuits, but it can pass utility ground faults into the plant, so the plant protection must be designed for it.
  • Delta on the utility side. The plant looks ungrounded to the utility, which tends to need a grounding transformer or an equivalent.

A grounding transformer, usually a zig-zag or a wye-delta bank, provides a low zero-sequence impedance at a chosen point. It must be connected correctly: its neutral is solidly or impedance grounded, its windings are rated for the fault current for the clearing time, and the relay that watches the neutral current is fed from a current transformer in the neutral. The device is described in grounding transformer.

Worked example: how large a Z0 can the bank have? (illustrative)

Assumptions, all illustrative: a 2 MVA plant at 12.47 kV with a 6 % interconnection transformer, so the island’s positive-sequence reactance is dominated by the transformer. The utility asks for X0/X1 of 3 or less.

  1. Base impedance = 12.47² / 2 = 77.7 Ω. X1 = 0.06 × 77.7 = 4.67 Ω.
  2. Maximum allowed zero-sequence reactance = 3 × 4.67 = 14.0 Ω.
  3. A zig-zag bank with a zero-sequence impedance of 8 Ω per phase gives X0/X1 = 8 / 4.67 = 1.71, which meets the limit.
  4. Ground fault current in the island, with X2 equal to X1: I = 3 × 7200 / (8 + 2 × 4.67) = 1246 A. Each phase of the bank carries one third, about 415 A, for the time until the plant trips.

The bank’s short-time rating and the neutral relay setting are then chosen to match that current and the clearing time. The numbers only illustrate the steps. With an inverter source the utility may set the criterion another way, as noted above.

Checklist for the engineer

  • Get from the utility the circuit grounding (three-wire or four-wire) and its rule for effective grounding.
  • Confirm the transformer winding connection and its zero-sequence behaviour.
  • Calculate X0/X1 and R0/X1 for the island case, and document the assumptions.
  • Check arrester and equipment ratings against the overvoltage you calculated.
  • If a bank is needed, define its rating, its connection and its protection.
  • Coordinate the neutral relay with the plant and with the transfer trip, if any.
  • Record the result for the utility’s review.

Who signs and seals

Grounding studies and transformer specifications for a US project are normally reviewed and stamped by a professional engineer licensed in the state of the project. Tiza delivers power-system studies ready for your engineer of record to review and stamp. Tiza does not stamp, sign or certify work in the United States.

How Tiza can help

If your interconnection transformer needs a grounding check, Tiza delivers power-system studies remotely, in English, ready for your engineer of record to review and stamp. Contact us with the single-line and the transformer data.

References

  • IEEE C62.92.1-2016, guide for neutral grounding in utility systems, part I, introduction.
  • IEEE C62.92.4-2014, same series, part IV, distribution.
  • IEEE 1547-2018, for the response of distributed energy resources to abnormal conditions.
  • The grounding rules in the interconnection handbook of the utility that owns the circuit.

Figure: single-line of a feeder with a plant transformer whose delta winding faces the utility, a zig-zag grounding transformer on the utility side, with the current transformer in its neutral feeding a relay.

Frequently asked questions

What does effectively grounded mean?

A system is effectively grounded when the coefficient of grounding stays below 80 %. A commonly used approximation is that the zero-sequence reactance is no more than three times the positive-sequence reactance and the zero-sequence resistance is no more than the positive-sequence reactance, for all conditions. IEEE C62.92.1-2016 is the guide behind the definition. For inverter sources, IEEE C62.92.6-2017 applies, and the utility may use other criteria.

Why does a delta winding cause trouble?

A delta winding on the utility side of the interconnection transformer gives no zero-sequence path into the island. After the utility source opens, a ground fault on the feeder can keep the island energized with an ungrounded source, so the healthy phases can reach about 1.73 per unit.

Is a grounding transformer always required?

No. Where the interconnection transformer already gives an effectively grounded source, none is needed. Utilities decide it from the circuit grounding, the transformer connection and the study.