ERCOT NOGRR 245: Ride-Through Rules for IBR Plants

ERCOT NOGRR 245 sets ride-through for inverter-based resources, aligned with IEEE 2800-2022. See who it covers, what to check and a plant settings example.

By Shadai García, CEO and protection engineer at Tiza Group.

345 kV gridpoint of interconnectionX = 0.12 puon 160 MVAcollector bus=~invertersplantcontroller27undervoltagesetpoints0.70 pu0.796 puPowerMeasure / tripCommspuinverter trip 0.80 putrip regionPOI 0.70+0.096 puterminal 0.7960.8 x 0.12 = 0.096 pu of voltage rise0.70 + 0.096 = 0.796 pu at the terminals0.796 < 0.80: the inverter tripsaction: lower the setting or add delayPowerChecksPlantPOI 0.70RiseTerminationSetting© tizagrp.com345 kV gridpoint of interconnectionX = 0.12 puon 160 MVAcollector bus=~invertersplantcontroller27undervoltagesetpoints0.70 pu0.796 puPowerMeasure / tripCommspuinverter trip 0.80 putrip regionPOI 0.70+0.096 puterminal 0.7960.8 x 0.12 = 0.096 pu of voltage rise0.70 + 0.096 = 0.796 pu at the terminals0.796 < 0.80: the inverter tripsaction: lower the setting or add delayPowerChecksPlantPOI 0.70RiseTerminationSetting© tizagrp.com
ERCOT ride-through for inverter-based resources: a 160 MVA plant at 345 kV with its point-of-interconnection voltage transformer, plant controller, inverter breaker and the undervoltage protection that trips it, and the voltage scale where 0.70 per unit at the point of interconnection plus a 0.096 rise reads 0.796 at the terminals, below the 0.80 trip setting. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

ERCOT revision request NOGRR 245 sets voltage and frequency ride-through requirements for inverter-based resources, aligned with IEEE 2800-2022. Which requirements apply depends on the date of the plant's original interconnection agreement. Settings at inverter and plant level must keep the plant online inside the required regions.

Short answer

NOGRR 245 is a Nodal Operating Guide Revision Request that sets voltage and frequency ride-through requirements for inverter-based resources (IBR) in the Electric Reliability Council of Texas (ERCOT). ERCOT submitted it because some IBR plants did not ride through system disturbances and tripped when they should have stayed online. The requirements are aligned with IEEE 2800-2022, which is described in IEEE 2800 ride-through and reactive capability. The wider US context is in the US electrical codes and grid interconnection guide. A separate reliability standard of the North American Electric Reliability Corporation (NERC), NERC PRC-029, addresses the same subject for the bulk power system. A Texas plant should check both documents, because ERCOT writes its own operating rules.

What the requirement does

Ride-through means a plant must stay connected and keep supporting the grid through defined voltage and frequency excursions. For an IBR the behavior comes from control software and settings, so the rule covers the inverter, the plant controller and any protection that can trip the plant. The Public Utility Commission of Texas (PUCT) approved NOGRR 245 on 26 September 2024. Some parts took effect on 1 October 2024. Other performance requirements apply once the changes that maximize ride-through capability are in place.

Three points matter for planning:

  • Agreement date decides. The original interconnection agreement date determines which ride-through requirements apply to a plant, even if the agreement is later amended.
  • Exemptions under a PUCT rule. The approved version separated the exemption process. The PUCT then adopted 16 TAC §25.517, which sets the exemption process for ERCOT reliability requirements and is open only to existing resources. ERCOT can reject a request if the plant has not made the commercially reasonable changes that maximize its ride-through capability.
  • Related items continue. ERCOT has published implementation material on further IBR items, such as negative-sequence current injection. Check the current documents before design.

Where plants usually go wrong

Settings measured at the wrong point. Plant requirements are stated at the point of interconnection. Inverter protection reads its own terminals, so the same event looks different to each. Settings must be converted between the two, as the example below shows.

Defaults left in place. Inverters often ship with protection set for other rules. Compare each trip setting with the required region and with the plant model.

Controller behavior after the event. The inverters may ride through while the plant controller ramps or holds power, so plant output at the point of interconnection falls anyway.

Model not updated. If settings change, the model ERCOT uses must change too. See NERC MOD-026 and MOD-027 for model verification practice and IEEE 2800 model and simulation requirements.

For distribution-connected inverters, the relevant standard is IEEE 1547; see category A and B voltage ride-through. A cross-country comparison is in ride-through requirements compared.

Worked example (illustrative)

The plant and the settings are assumptions to show the conversion.

Assumptions. A 160 MVA plant is connected at 345 kV. The plant base is 160 MVA. The main transformer and collector system total 0.12 per unit (pu) reactance on that base. During a fault the plant injects reactive current of 0.8 pu on the plant base. An inverter’s undervoltage trip is set at 0.80 pu at its own terminals. The voltage at the point of interconnection falls to 0.70 pu.

Step 1. Voltage rise caused by reactive current. 0.8 × 0.12 = 0.096 pu.

Step 2. Voltage at the inverter terminals. 0.70 + 0.096 = 0.796 pu.

Step 3. Compare with the setting. 0.796 is below 0.80, so the inverter protection would trip even though the plant should ride through.

Step 4. Action. Lower the terminal setting or add delay, so the inverter trip sits outside the required ride-through region. Then record the change in the plant documentation and the model. The check must use the ride-through region of the Nodal Operating Guide for the plant’s category.

Use real data in a real study. The simplified voltage addition ignores resistance and the voltage angle.

Checklist for the engineer

  • Identify the original interconnection agreement date and the requirements that apply.
  • Read the current Nodal Operating Guide text and ERCOT’s implementation notes.
  • List every protective function in the inverter and plant controller that can trip.
  • Convert plant-level regions to inverter terminal values with the actual impedances.
  • Test or simulate each model with the settings that will be installed.
  • Keep the ERCOT model in line with the as-built settings.
  • Have the engineer of record review the settings basis.

The points above are general orientation. ERCOT and the PUCT publish the rules that decide each case. Tiza does not sign, seal or certify work in the United States. We deliver settings reviews and studies ready for your engineer of record to review and stamp.

How Tiza can help

If your inverter plant needs its protection and ride-through settings checked against ERCOT’s requirements, Tiza provides remote relay configuration in English: a settings table ready for your engineer of record to review and stamp, then applied and recorded remotely. Contact us with the inverter and plant controller settings.

Figure: block diagram of an inverter plant showing the point of interconnection, the plant controller, the inverters and the protection functions that can trip them.

References

  • ERCOT Nodal Operating Guide revision request NOGRR 245 and the ERCOT implementation presentations to the Reliability and Operations stakeholders.
  • PUCT rule 16 TAC §25.517, Exemption Process for ERCOT Reliability Requirements.
  • IEEE Std 2800-2022, Interconnection and interoperability of inverter-based resources.

Frequently asked questions

Which plants does NOGRR 245 apply to?

It applies to inverter-based resources in ERCOT. The original interconnection agreement date determines which ride-through requirements apply to a plant, even if the agreement is later amended. Read the current Nodal Operating Guide text for the plant's category.

Is NOGRR 245 the same as IEEE 2800?

No. NOGRR 245 is an ERCOT rule that is aligned with IEEE 2800-2022 but is its own text. The Nodal Operating Guide, not the IEEE standard, is the document ERCOT enforces.

Can a plant that cannot meet the requirement get an exemption?

The approved version of NOGRR 245 left the exemption process to a later step. The Public Utility Commission of Texas then adopted 16 TAC §25.517, the exemption process for ERCOT reliability requirements, which is open only to existing resources.