Tiza Group

Home / Guides / Codes and grid connection: US, UK, CA, AU

IEEE 2800 Ride-Through Requirements and Reactive Capability

IEEE 2800 ride-through requirements: voltage and frequency ride-through and reactive capability of IBR power plants, with a worked example and a checklist.

By Shadai García, CEO and protection engineer at Tiza Group.

voltage (pu)time1.0trip may be allowedride through0.70 puenvelope drawn qualitativelydip: 1.00 - 0.70 = 0.30 puIq = 2 x 0.30 = 0.60 puIp max = sqrt(1.0² - 0.60²) = 0.80P = 0.70 x 0.80 = 0.56 pugain 3: Iq 0.90, Ip 0.44, P 0.31limit 1.0 pu0.60Iq0.80Ipgain 2, P 0.56 pu0.90Iq0.44Ipgain 3, P 0.31 puRide-throughDipReactiveLimitActivePower© tizagrp.comvoltage (pu)time1.0trip may be allowedride through0.70 puenvelope drawn qualitativelydip: 1.00 - 0.70 = 0.30 puIq = 2 x 0.30 = 0.60 puIp max = sqrt(1.0² - 0.60²) = 0.80P = 0.70 x 0.80 = 0.56 pugain 3: Iq 0.90, Ip 0.44, P 0.31limit 1.0 pu0.60Iq0.80Ipgain 2, P 0.56 pu0.90Iq0.44Ipgain 3, P 0.31 puRide-throughDipReactiveLimitActivePower© tizagrp.com
IEEE 2800 ride-through: voltage against time with a qualitative ride-through envelope and a dip to 0.70 per unit, and the split of the 1.0 per unit current limit between reactive and active current at gains of 2 and 3. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

IEEE 2800 ride-through requirements ask an inverter-based plant to stay connected and keep supporting the grid through voltage and frequency disturbances, and to deliver reactive power at the point of interconnection. In a fault the plant must also manage its current limit between active and reactive current.

IEEE 2800 ride-through requirements decide whether a large solar or storage plant helps the grid through a fault or becomes part of the problem. Two ideas sit together: staying connected, and supplying the right current while connected.

This guide is based on IEEE 2800-2022, with reactive capability in its clause 5 and ride-through in its clauses 7.2 for voltage and 7.3 for frequency. IEEE 2800.2-2026, the test and verification practice, was published on 30 June 2026.

Short answer

IEEE 2800 ride-through requirements ask an inverter-based resource (IBR) plant to remain connected and to keep supporting the grid through defined voltage and frequency disturbances, and to have reactive power capability at the point of interconnection. The standard sets the envelopes and the performance. A designer checks the inverter, the plant controller and the protection settings against them, together with the operator’s own requirements.

Figure: voltage against time with a ride-through envelope, the region where the plant may trip and a trace of a fault and recovery.

The wider framework is in the US electrical codes and grid interconnection guide. The scope of the standard is in the IEEE 2800 overview. A comparison with Great Britain and Australia is in ride-through requirements compared.

Voltage and frequency ride-through

Voltage ride-through describes how long the plant must stay connected at each voltage level, from deep dips to over-voltage. Frequency ride-through does the same for system frequency. Each has a region where the plant must continue, a region where tripping is allowed, and in-between behavior that the standard describes.

Three consequences for the design.

  • Protection must sit outside the envelope. An overvoltage or underfrequency element that trips inside the ride-through region defeats the requirement. The guide on 59 overvoltage trips in solar plants shows how real plants trip for reasons the designer did not expect.
  • Controls must not stall. The plant controller and the inverters must resume normal output in a defined way after the disturbance.
  • Equipment limits count. Where hardware cannot meet the envelope, the operator needs to know before the study, not after.

Reactive capability

Reactive capability is the steady-state range of reactive power the plant can provide at the point of interconnection. It depends on the inverters, the transformers and the collector system. The plant must also regulate voltage by a control mode that the operator selects. See the reactive check in the IEEE 2800 overview.

Where the two meet: current during a fault

An inverter has a current limit. During a fault the voltage is low, the plant is asked for reactive current to help the voltage, and the active current shrinks to fit the same limit. How the plant splits the limit between the two is a control choice that the operator and the study must agree on. A plant that gives priority to reactive current supports the voltage better, while a plant that keeps active current recovers its output faster.

Evidence

The operator will ask how each claim is supported. A good evidence file ties every requirement to a source: a type-test report, a simulation case, a commissioning record or a manufacturer statement. Each gap in that file becomes a question from the operator.

Evidence comes from several places: type tests of the inverters, plant-level simulation, and field commissioning. A simulation alone can overstate what the plant does, so type-test evidence for the equipment matters. The model side is covered in IEEE 2800 model and simulation requirements.

Worked example (illustrative)

A fault drops the voltage at the inverter terminals to 0.70 per unit. The inverter current limit is 1.0 per unit. In this example the control injects reactive current in proportion to the voltage dip, with an illustrative gain of 2 per unit of reactive current per per unit of voltage dip, and gives priority to reactive current.

Step 1. Voltage dip. 1.00 − 0.70 = 0.30 per unit.

Step 2. Reactive current. 2 × 0.30 = 0.60 per unit.

Step 3. Room left for active current. The limit is 1.0 per unit, so the active current can be at most √(1.0² − 0.60²) = √0.64 = 0.80 per unit.

Step 4. Active power during the fault. P = V × Ip = 0.70 × 0.80 = 0.56 per unit.

Step 5. Reading the result. The plant keeps 56 percent of its pre-fault power while supplying 0.60 per unit of reactive current. A gain of 3 would give 0.90 per unit of reactive current and leave √(1 − 0.81) = 0.44 per unit of active current, which cuts the power to 0.31 per unit. The study shows which compromise suits the grid.

The gain and the priority are chosen for the illustration. The real values come from the operator’s requirement and the plant control design.

Checklist for the engineer

  • Obtain the voltage and frequency envelopes the operator expects and the edition they refer to.
  • Compare every protection element in the plant with the envelope.
  • Check the plant controller behavior after the disturbance, including recovery ramps.
  • Confirm reactive capability at the point of interconnection, with losses.
  • Define the current priority during faults and agree it with the operator.
  • Identify equipment that cannot meet the envelope and report it early.
  • Collect type-test evidence for each inverter model and firmware.
  • Reconcile IEEE 2800 with NERC PRC-029-1 and the operator’s text.

Who signs and seals

In the United States a design is normally signed and sealed by a professional engineer licensed in the state of the project. Our reviews and studies are delivered ready for your engineer of record to review and stamp. Tiza does not sign, seal or certify work in the United States.

How Tiza can help

If a ride-through design has been prepared by someone else, an independent check of the protection settings, the controller behavior and the evidence against the operator’s requirements can prevent a late redesign. Tiza provides independent review of a third-party design, remotely and in English. Contact us with the design package and the operator’s requirements.

Frequently asked questions

What does ride-through mean for an IBR plant?

It means the plant stays connected and keeps operating, within defined envelopes, during voltage and frequency disturbances rather than tripping. A plant that trips on a fault takes its output away at the moment the grid needs it.

Is reactive capability the same as ride-through?

No. Reactive capability is how much reactive power the plant can supply or absorb at its point of interconnection in steady state. Ride-through covers behavior during disturbances. During a fault the two meet, because reactive current competes with active current for the same inverter limit.

Do IEEE 2800 and NERC PRC-029 ask the same thing?

No. IEEE 2800 is a technical standard. PRC-029-1 is a NERC reliability standard approved by FERC. PRC-029-1 uses terms from IEEE 2800 without adopting it in full, so the project needs to check both.

WhatsApp