Tiza Group

Home / Guides / Codes and grid connection: US, UK, CA, AU

IEEE C57.13 CT Accuracy Class: C, T and Metering

IEEE C57.13 CT accuracy class explained: how C100 to C800, T and metering 0.3 classes are read, how burden decides them and how to check a CT for relaying.

By Shadai García, CEO and protection engineer at Tiza Group.

source busbreaker600:5ratio 120test switch 0.05 ohmleads 0.50 ohm (500 ft)relay0.20 ohm80 A secondary16 x 5 Afault 9,600 Aburden 0.20 + 0.50 + 0.05 = 0.75 ohmPowerMeasure / trip80 A = 9,600 / 120, then 80 x 0.75 = 60 V660 V = 60 x (1 + 10), X/R = 10C800 holds: margin 140 V, about 21%300:5 tap: 160 A, 1,320 V requiredcapability 800 / 2 = 400 V: it failsV02004008001,200600:5 tap660 V requiredC800: 800 V300:5 tap (half the winding)1,320 V requiredcapability 400 Vclasses: C100, C200, C400, C800(1 + X/R) is a rough check, not from C57.13ChecksSecondary currentBurdenRequired voltageClass voltageMargin© tizagrp.comsource busbreaker600:5ratio 120test switch 0.05 ohmleads 0.50 ohm (500 ft)relay0.20 ohm80 A secondary16 x 5 Afault 9,600 Aburden 0.20 + 0.50 + 0.05 = 0.75 ohmPowerMeasure / trip80 A = 9,600 / 120, then 80 x 0.75 = 60 V660 V = 60 x (1 + 10), X/R = 10C800 holds: margin 140 V, about 21%300:5 tap: 160 A, 1,320 V requiredcapability 800 / 2 = 400 V: it failsV02004008001,200600:5 tap660 V requiredC800: 800 V300:5 tap (half the winding)1,320 V requiredcapability 400 Vclasses: C100, C200, C400, C800(1 + X/R) is a rough check, not from C57.13ChecksSecondary currentBurdenRequired voltageClass voltageMargin© tizagrp.com
CT accuracy class: a 600:5 CT with its secondary loop of test switch, leads and relay totalling 0.75 ohm, a 9,600 A fault and the trip to the breaker, with the 660 V required against the C800 class and the 1,320 V required against 400 V on the 300:5 tap. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

In the US, current transformers for protection are rated by letter and voltage, such as C400 or C800, and those for metering by an accuracy percentage, such as 0.3. The C rating is the secondary voltage the CT can deliver at twenty times rated current into its standard burden without the ratio error passing 10 percent. It only holds when the real burden is at or below that standard burden and the CT is used on its full winding. Checking a CT means comparing the voltage it needs with the voltage it can give.

In US projects, the question about a current transformer is rarely “5P20 or 10P10”. It is “C400 or C800”, or “0.3 or 0.6 at which burden”. Those designations come from the IEEE C57.13 family. Below are how to read an IEEE C57.13 CT accuracy class, how the burden decides whether the class holds and how to check a CT for a relay or a meter without relying on the label alone.

Classes and burdens here follow IEEE C57.13-2016. IEEE C57.13.1-2017 is the companion guide for field testing relaying current transformers.

The wider framework is in the US electrical codes and grid interconnection guide. What a utility expects from the instrument transformers at the service entrance is described in utility relay requirements for industrial customers.

Short answer

An IEEE C57.13 CT accuracy class is a promise made for a stated burden. For protection, the class is a letter and a voltage. C is for a CT whose leakage flux is negligible and T is for one where it is not. A number follows, such as 100, 200, 400 or 800 volts. The voltage is what the CT can deliver at twenty times rated secondary current into its standard burden with no more than 10 percent ratio error. For metering, the class is an accuracy percentage, such as 0.3, 0.6 or 1.2, tied to a burden and to the current range. Check the real burden and the real fault current against the label.

What the standard covers

IEEE C57.13 sets requirements for instrument transformers: current transformers and voltage transformers, for metering and for relaying. It defines the accuracy classes, the standard burdens, the ratings, the markings and the tests. IEEE C57.13.1 covers how to check relaying CTs in the field: ratio, polarity, excitation and condition. The IEC equivalent is IEC 61869, whose classes such as 5P20 are covered in 5P and 10P protection CT classes and equivalences between protection CT classes. The two systems use different labels and different test conditions, so a conversion is a design decision, not a lookup.

Reading a relaying class

A label such as C400 has three parts:

  • C means the leakage flux is low enough to calculate the ratio performance from the excitation curve. T means it cannot, and the manufacturer tests it.
  • 400 is the terminal voltage in volts that the secondary can deliver at twenty times rated current, into the standard burden, with ratio error not over 10 percent.
  • The standard burden that goes with it is an impedance at 0.5 power factor. For a 5 A secondary, a C800 pairs with burden B-8, 8 ohms: 100 A × 8 Ω = 800 V. The other burdens are listed in the standard.

Two consequences follow:

  1. The class is a statement about a voltage, not about current. A C400 CT on a 600:5 winding can drive a lot of secondary current into a low burden before it saturates, and very little into a high one.
  2. The class belongs to the full winding. On a multi-ratio CT, a lower tap uses fewer turns and delivers proportionally less voltage. Our guide on CT primary current and multiple ratios shows the reason.

Reading a metering class

A metering class, such as 0.3, 0.6 or 1.2, is an accuracy percentage. It is guaranteed at stated burdens, at the rated frequency and between a stated fraction of the rated current and the rated current multiplied by the rating factor. Outside those conditions the CT is not rated, and a meter fed at a very light load may read poorly. A CT is often marked with both a metering and a relaying class. A dual rating means two windings or two accuracy statements, so read each one against its own burden. Metering CTs are not meant to feed relays. They saturate at low multiples of the rated current, which is what protects the meter and what ruins a relay.

Voltage transformers

ANSI voltage transformers carry accuracy classes such as 0.3, 0.6 and 1.2, each one tied to a letter that names a standard burden (W, X, M, Y, Z and ZZ). The class holds when the real burden does not exceed the one the letter names, and when the voltage is within the rated range. The guides on measuring voltage transformer accuracy classes and on 3P and 6P protection VT classes cover the IEC side of the same question.

Why the burden decides everything

The burden is what the secondary circuit presents to the CT: relay input, lead wire, test switches, terminal blocks and any auxiliary device. Longer leads and smaller wire raise it. The CT’s class stays valid only while the real burden is at or below the standard one. When the CT drives more burden, or more current, than its voltage allows, it saturates, and a relay sees a distorted signal. See CT saturation for what that does to protection.

Worked example: does a C800 hold?

This example uses illustrative data, not from any project. A feeder has a 600:5 CT, a ratio of 120. The maximum fault current is 9,600 A primary. The secondary circuit is:

  • Relay burden: 0.20 Ω.
  • Leads: 250 ft one way in #10 copper, so 500 ft round trip. At about 1 Ω per 1,000 ft, that is 0.50 Ω.
  • Connections and test switch: 0.05 Ω.

The total burden is 0.20 + 0.50 + 0.05 = 0.75 Ω.

  1. Secondary fault current: 9,600 / 120 = 80 A, or 16 times the rated 5 A.
  2. Voltage for a symmetrical fault: 80 × 0.75 = 60 V.
  3. A conservative allowance for the DC offset in a network with X/R = 10 multiplies it by (1 + 10) = 11, giving 60 × 11 = 660 V.
  4. The CT must be able to deliver at least 660 V without saturating. C100, C200 and C400 cannot. C800 can, with a margin of 800 − 660 = 140 V, about 21 percent above the 660 V required.

Now suppose the relay is moved to the 300:5 tap, a ratio of 60.

  1. The secondary fault current doubles to 9,600 / 60 = 160 A.
  2. The required voltage is 160 × 0.75 × 11 = 1,320 V.
  3. The CT’s capability on that tap is half the full-winding value, so 800 / 2 = 400 V.

The tap fails by a wide margin. The (1 + X/R) allowance is a rough conservative check, not a method from IEEE C57.13. The final selection uses the transient tools described in CT for overcurrent protection. An excitation test, described in CT excitation and knee point, confirms the real curve in the field.

Checklist for the engineer

  • Read the full nameplate: ratio, taps, metering class, relaying class, rating factor.
  • Compute the real burden: relay, leads, switches and terminals.
  • Compute the secondary fault current at the tap in use.
  • Compare the voltage required, including the DC offset allowance, with the class voltage of the tap, not of the full winding.
  • Check that metering and protection use separate windings, with the class suited to each.
  • Check the VT burden letter against the real burden.
  • Request an excitation curve from the factory or measure it.
  • Plan the field test with ratio, polarity and excitation, following the field-testing guide.

Who signs and seals

Instrument transformer selection is part of the protection design, which in the United States is normally reviewed and stamped by a professional engineer licensed in the state of the project. Tiza delivers the specification and checks ready for your engineer of record to review and stamp. Tiza does not sign, seal or certify work in the United States.

How Tiza can help

If you have to specify or check the CTs and VTs for a service entrance, Tiza delivers engineering design remotely, in English, ready for your engineer of record to review and stamp. Contact us with the single-line diagram, the fault study and the relay model, and we will scope the work with you.

References

  • IEEE C57.13-2016, IEEE Standard Requirements for Instrument Transformers.
  • IEEE C57.13.1, Guide for Field Testing of Relaying Current Transformers, 2017 edition.
  • IEC 61869-2, for the comparison with the IEC classes.

Figure: CT secondary circuit with the CT winding and its burden: relay, leads and test switch, with the class voltage compared against the voltage required at the fault current.

Frequently asked questions

What does C800 mean on a current transformer?

C800 is a relaying class. It says the CT can deliver 800 V at its secondary terminals at twenty times rated secondary current, into its standard burden, with a ratio error of no more than 10 percent. For a 5 A secondary, that is 100 A into 8 ohms. The C means the leakage flux is small enough for the ratio to be calculated.

What is the difference between class C and class T?

In class C the leakage flux in the core is negligible, so the ratio error can be calculated from excitation data. In class T the leakage flux is significant, so the ratio error is found by test. Bushing and toroidal CTs are usually C. Wound-primary CTs are the usual source of T.

Does a tapped C800 CT keep its class on every tap?

No. The class applies to the full winding. On a lower ratio tap, the voltage the CT can give falls in proportion to the turns used. A C800 on its 600:5 winding is a C400 on the 300:5 tap. Always check the burden and the fault current against the tap in use.

WhatsApp