BS 7671 Section 551: Low Voltage Generating Sets

BS 7671 Section 551 explained: standby and parallel generating sets, changeover and neutral switching, earthing and a fault current check for a 40 kVA set.

By Shadai García, CEO and protection engineer at Tiza Group.

Public supplyTN-C-SGenerating set40 kVAelectrodeMET4-poleL + Ninterlockedno parallelingDistributionboardpublic supply: one N–PE linkon the set: neutral to METdisconnection does not depend on thedistributor's earthing conductorown electrode at the METLineN, PE40,000 / (√3 × 400) = 57.7 A3 × 57.7 = 173 A; 230 / 173 = 1.33 Ωloop: 1.33 + 0.35 = 1.68 Ω0.95 × 230 / 1.68 = 130 A5 × 32 = 160 A needed: 130 A falls shortthermal curve: slower than 0.4 soptions: RCD, 20 A breaker (100 A)rated 57.7 Asustained short circuit 173 Aearth fault current 130 A160 A needed20 A breaker: 5 × 20 = 100 AA050100150200illustrative valuesStandby setPublic supplyChangeoverSetMETFault current© tizagrp.comPublic supplyTN-C-SGenerating set40 kVAelectrodeMET4-poleL + Ninterlockedno parallelingDistributionboardpublic supply: one N–PE linkon the set: neutral to METdisconnection does not depend on thedistributor's earthing conductorown electrode at the METLineN, PE40,000 / (√3 × 400) = 57.7 A3 × 57.7 = 173 A; 230 / 173 = 1.33 Ωloop: 1.33 + 0.35 = 1.68 Ω0.95 × 230 / 1.68 = 130 A5 × 32 = 160 A needed: 130 A falls shortthermal curve: slower than 0.4 soptions: RCD, 20 A breaker (100 A)rated 57.7 Asustained short circuit 173 Aearth fault current 130 A160 A needed20 A breaker: 5 × 20 = 100 AA050100150200illustrative valuesStandby setPublic supplyChangeoverSetMETFault current© tizagrp.com
BS 7671 Section 551: a 40 kVA standby set and the public supply on a TN-C-S network, with the PEN conductor split into N and PE, joined to the distribution board through a four-pole changeover switch that switches line and neutral and never connects both sources, the neutral of the set taken to the main earthing terminal with its own electrode so that disconnection does not depend on the distributor's earth, and the fault check: 57.7 A rated, 173 A sustained, 1.68 ohm loop and 130 A against the 160 A a 32 A type B breaker needs. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

Section 551 of BS 7671 covers low-voltage generating sets that supply an installation, either as a standby source that replaces the public supply or as a source that runs in parallel with it. The main design questions are how the set is earthed when it works alone, how the changeover stops the set and the network from being connected by accident, and whether the set can deliver enough fault current for the protective devices to disconnect in time. An illustrative 40 kVA example works through the third question.

A generator in an installation changes three things at once: where fault current comes from, where the neutral and earth meet, and whether the network and the set can ever be connected together. Section 551 of BS 7671 deals with all three for low-voltage sets. The standard is the one described in BS 7671 18th edition explained, and the wider framework is in the UK electrical codes and grid connection guide. The current edition is BS 7671:2018+A4:2026.

Short answer: what does BS 7671 Section 551 cover?

Section 551 of BS 7671 sets the rules for low-voltage generating sets in an installation. It treats three cases. A standby set that is a switched alternative to the public supply. A set that runs in parallel with the public supply. And a set that can do both. For all of them it deals with protection against overcurrent and shock when the source is the set, with the switching that keeps the sources apart or synchronised, and with the earthing of the set. The connection of a set that runs in parallel with the network also falls under the network operator’s rules.

Standby sets: the switched alternative

In a standby installation, the public supply is disconnected before the set connects. Three consequences follow.

Earthing. The earthing conductor to the distributor’s terminal usually stays connected, but while the set runs it is no longer a fault return path to the source. Disconnection of supply therefore must not rely on it. The star point of the set is connected to the main earthing terminal, and the set needs its own means of earthing, often an earth electrode, and the installation works as a TN-S or a TT system while on generator, depending on the design. The earthing arrangements are explained in low-voltage system earthing and the conductor sizes in Chapter 54.

Changeover. The switch that selects the source must make it impossible for the set and the network to be connected together, by mechanical interlock or an equivalent method. IET guidance on this point is that the changeover should switch all live conductors including the neutral, so that the neutral-to-earth link of the set is not in circuit when the network supplies the installation. This avoids a second neutral-earth connection that would split the return current on a PME supply.

Fault current. A generator is a weak source. During a short circuit, the excitation system limits the fault current, and the level and its duration depend on the machine. Protective devices that would clear a fault in milliseconds on the network may not operate in time on the set.

Sets that run in parallel with the network

When a set can run in parallel with the supply, extra measures are needed so that the set does not feed a fault on the network, and so that a loss of the network is detected. For small sets, the connection is covered by G98 for up to 16 A per phase. For larger ones, see the G99 types A to D and the G99 protection requirements. A battery inverter that can export behaves in the same way; see the battery storage connection guide.

Worked example: can a 40 kVA set clear a fault?

The numbers are illustrative and the data are assumed. A 40 kVA, 400 V three-phase standby set supplies a final circuit protected by a 32 A type B breaker with a 0.4 s disconnection time. Type B devices are assumed to operate magnetically at five times their rating.

  1. Rated current of the set: 40,000 / (√3 × 400) = 57.7 A.
  2. The manufacturer’s data give a sustained short-circuit current of three times the rated current: 3 × 57.7 = 173 A.
  3. Equivalent impedance of the set for a line-to-earth fault: 230 / 173 = 1.33 Ω.
  4. The circuit cable, line plus protective conductor, is assumed to add 0.35 Ω.
  5. Total loop impedance: 1.33 + 0.35 = 1.68 Ω.
  6. Fault current with a minimum voltage factor of 0.95: 0.95 × 230 / 1.68 = 130 A.
  7. The breaker needs 5 × 32 = 160 A to operate magnetically. At 130 A it falls short, so the breaker would operate on its thermal curve and take longer than 0.4 s.

On the public supply, the same circuit would see hundreds of amperes and pass easily, which is why this check is easy to miss. The options are a 30 mA residual current device (RCD), which operates on the residual current and not on the fault level; a lower-rated breaker, such as 20 A, which needs only 100 A; a set with a higher fault capability; or a larger cable. The answer must be checked on the generator and on the network, because the circuit has two sources.

Figure: a single-line diagram of a standby set and the public supply connected through a four-pole changeover switch to a distribution board, with the neutral-earth link of the set shown.

Common problems in practice

  • Checking disconnection times only against the network fault level.
  • A changeover that leaves the neutral of the set connected to the network neutral.
  • No earth electrode for the set, so the installation has no earth reference on generator.
  • An automatic transfer switch bypassed for maintenance with no interlock.
  • Forgetting motor starting: a large motor start can pull the set voltage down.
  • Sizing the set for the running load and ignoring the largest step load.
  • Missing the notification or application to the network operator when the set can parallel with the grid.

Checklist for the engineer

  • Define the mode: standby, parallel or both.
  • Choose the earthing arrangement on generator and size the electrode.
  • Specify the changeover with its interlock and neutral switching.
  • Obtain the sustained short-circuit data from the manufacturer.
  • Check every protective device against the lower fault level of the set; see the overcurrent protection guide.
  • Check the shock protection while on generator; see Chapter 41.
  • For parallel sets, start the network operator’s process early.
  • Test both modes at commissioning; see the inspection and testing guide.

In the UK there is no statutory stamp for electrical designs. A chartered engineer or other competent person reviews the design and signs it under their own responsibility. The duty to prevent danger is in the Electricity at Work Regulations 1989, and a set that parallels the grid also falls under the ESQCR 2002.

How Tiza can help

If your project needs a generating set integrated, Tiza prepares the engineering remotely and in English: fault level and protection checks for both sources, earthing and changeover design, and the documents for the network operator. Tiza does not stamp, sign or certify designs in the UK; we deliver engineering ready for your chartered engineer to review and sign. Contact us with the set data and the single-line diagram.

Frequently asked questions

Does a standby generator need its own earth?

When the set is a switched alternative to the public supply, automatic disconnection of supply cannot rely on the distributor's earth, because the path back to the network source is switched out while the set runs. Section 551 therefore requires a suitable means of earthing for the set, commonly an earth electrode, and the arrangement while on generator is usually TN-S or TT as the design chooses.

Should the changeover switch break the neutral?

For a standby set that is a switched alternative, the practice described in IET guidance is to switch all live conductors including the neutral, so two poles for a single-phase installation and four for a three-phase one. This keeps the neutral-to-earth link of the set out of the circuit when the public supply is connected. Confirm the rule in the current text of Section 551.

Is a generator that runs in parallel with the grid under BS 7671 or under G99?

Both. Section 551 covers the installation side, including protection and switching. The distribution network operator's technical rules for parallel generation, ENA Engineering Recommendations G98 and G99, cover the connection to the network, including interface protection. A standby set that never parallels the grid is mainly a Section 551 matter.