ENA Engineering Recommendation G98 covers small-scale generation of up to 16 A per phase on the low-voltage network. Type-tested equipment is installed first and the network operator is told afterwards, so the check that matters is arithmetic: current per phase against 16 A. A battery or a second inverter on the same phase can push a home or small business over the limit and into G99.
Short answer: what ENA G98 covers
ENA G98 covers small-scale generation of up to 16 A per phase connected to the low-voltage network. The route is the lightest in the UK: the installer uses type-tested equipment, installs it, and notifies the distribution network operator (DNO) within 28 days of commissioning. Larger systems go to G99. G98 is the successor of the older G83, and Issue 2 is the current issue of the document. Rules for the whole site are in the UK electrical codes and grid connection guide.
The question for a designer is therefore short: what is the current per phase of everything that can export at the connection? If it is 16 A or less, and the equipment is type tested, G98 applies. If it is more, G99 applies.
What type tested means
G98 relies on the manufacturer. The generating unit, usually an inverter, has been tested against the requirements of G98 and the results are recorded in a type test certificate that the DNO can check. The protection that separates the unit from the network when the supply fails is built in. So are the response to voltage and frequency and the behaviour when the network returns. The manufacturer fixes all of them. An installer cannot change the settings to suit a site.
Type testing is why a G98 connection can go ahead without a prior application: the network operator already knows what the equipment will do. A unit with no valid type test evidence is outside the G98 route, whatever its size.
Counting the current per phase
The 16 A limit is per phase, so the arithmetic depends on how the units are connected:
- Single-phase unit. Current = power ÷ 230 V. At 3.68 kW the current is exactly 16 A.
- Balanced three-phase unit. Current per phase = power ÷ (3 × 230 V). A 11 kW unit gives 15.9 A per phase.
- Several units. Add the currents of all units that connect to the same phase before comparing with 16 A.
Check the power the unit can export, not the panel rating: an inverter rated at 3.6 kW with 5 kW of panels exports 3.6 kW at most, and an inverter that can export from a battery counts like any other unit. If the DNO asks about the capacity of the connection, state both the AC rating and the DC side.
Worked example: four homes, one limit
All values are illustrative. Supply is 230 V single phase unless stated.
- Home A: 3.6 kW PV inverter. Current = 3,600 ÷ 230 = 15.7 A. Below 16 A, so G98 can apply.
- Home B: 4 kW PV inverter. Current = 4,000 ÷ 230 = 17.4 A. Above 16 A, so G99 applies, even though the difference is only 0.4 kW.
- Home C: 3.6 kW PV inverter and a 3 kW battery inverter, both on the same phase. Total = 6,600 W ÷ 230 = 28.7 A. This is above the limit. A single-phase supply has no second phase to share the load, so G99 applies. On a three-phase supply, units on different phases are counted phase by phase.
- Home D: a three-phase 12 kW inverter. Current per phase = 12,000 ÷ (3 × 230) = 17.4 A. Above 16 A, so G99 applies. A 11 kW unit would give 15.9 A and stay inside.
The decision that looks small on paper changes the process: a notification after installation becomes an application before the work.
What the DNO sees after notification
The notification carries the site address, the equipment and its type test reference, and the installer’s details. The DNO records the connection so that it knows how much generation sits on each feeder. If the DNO finds a problem, for example a unit that is not type tested, it can ask for the installation to be corrected or disconnected. Keep the notification and the commissioning record together for later checks.
Why G98 is not just a form
Notifying after installation does not mean the installation is free of rules. The wiring still follows BS 7671 (see the BS 7671 overview for the layers), the protection devices and cable sizes must suit the extra current, and the installer holds the commissioning record. The DNO can still ask for the evidence, and can refuse a unit that is not type tested.
Local network limits also exist: if many small systems are on the same low-voltage feeder, voltage rise can become a problem, and the DNO decides what to do about it. Harmonic and flicker issues are assessed by G5 and P28 in larger installations.
Checklist for the engineer
- Add the exportable power of all units on each phase, batteries included.
- Convert each total to current at 230 V and compare with 16 A per phase.
- Confirm that every unit has valid G98 type test evidence.
- Keep the type test certificates with the commissioning record.
- Check cables, protection devices and BS 7671 requirements for the extra current.
- Notify the DNO after installation, with the data the form asks for.
- If the total is above 16 A on any phase, stop and use the G99 process.
- Re-check the arithmetic whenever a battery or a second inverter is added later.
Related guides
For the equipment standards behind type testing, see PV inverter standards. The interface protection guide explains the protection that G98 equipment carries inside, and the G100 guide covers export limits. For the way export is held to a set value, see zero export control in solar plants.
From the limit check to a design your chartered engineer can review
For projects close to the 16 A line, the decision between a G98 route and a G99 application depends on the design of the whole site. We prepare the engineering design and the connection documents, ready for your chartered engineer to review and sign. Tiza does not stamp, sign or certify designs in the UK. Contact us with the site data.
Frequently asked questions
What is ENA G98?
G98 is the ENA Engineering Recommendation for connecting small-scale generation, up to 16 A per phase, to the low-voltage network. It sets a simple route: type-tested equipment is installed and the network operator is notified after installation, with no application before the work.
How do I check if a system is inside the G98 limit?
Divide the rated output power by the voltage and, for three-phase units, by three. For a 230 V supply, 16 A per phase is 3.68 kW per phase. Add every generating unit connected to the same phase, including inverters for batteries.
What happens if the system is above 16 A per phase?
It falls under ENA G99. That means an application to the network operator before the work starts, more design information and commissioning evidence. The G98 and G99 comparison guide sets out the steps in that decision.