ENA TS 41-24 is the Energy Networks Association technical specification for the design, installation, testing and maintenance of main earthing systems in substations. Issue 2, from November 2018, aligns the requirements with BS EN 50522. The designer works from fault current and soil data to a grid whose conductors, resistance and voltages meet the limits.
Short answer: what ENA TS 41-24 is for
ENA TS 41-24 is the technical specification that sets how main earthing systems in GB substations are designed, installed, tested and maintained. The full title is Guidelines for the design, installation, testing and maintenance of main earthing systems in substations. The current edition is Issue 2, published in November 2018 as a major revision. It aligns the requirements and terminology with BS EN 50522, including touch and step potentials. TS 41-24 is referenced in the Distribution Code, so a customer substation that connects to a network is designed with it in mind.
TS 41-24 belongs to the ENA layer in the UK electrical codes and grid connection guide. Its companion is ENA EREC S34, revised at the same time. The two split the work: TS 41-24 covers the earthing system itself (design, conductor ratings, installation, testing and maintenance), and S34 covers the assessment of earth potential rise and its effect on third parties. That assessment, with a worked rise calculation, is in the guide on ENA EREC S34.
The design sequence
An earthing design under TS 41-24 follows a chain. Each step feeds the next:
- Fault data. The highest earth fault current at the site and the time the protection takes to clear it, taken from the network operator for the present and the planned network.
- Current into the earth electrode. The fault current is shared between the grid and metallic return paths such as cable sheaths. Only the share that flows through the soil raises the grid potential.
- Soil model. Resistivity measured on site, from which a layered soil model is built. See soil resistivity: factors and treatment.
- Grid design. A layout of buried conductors and rods that meets conductor rating, resistance and potential goals. See earth grid resistance by IEEE 80 formulas for the resistance step.
- Conductor and joint ratings. Each conductor, joint and connection to equipment must carry its share of the fault current for the fault duration without damage.
- Earth potential rise, touch and step voltages. The rise and the voltages a person can be exposed to, compared with the tolerable limits for the fault clearing time. The S34 guide covers this assessment, including transfer to telecoms, pipes and low-voltage supplies. See also electric shock in a substation.
- Installation. Burial depth, jointing method, connections to fences and equipment, and protection against corrosion and theft.
- Testing and maintenance. Measurement after installation, records, inspection and a plan to retest.
The step that most often changes the design is the second one. A cable with a good metallic sheath carries part of the fault current away, and the designer who ignores that sizes the grid for a current that never enters the ground.
What the specification asks you to show
A reviewer, whether the network operator or your own engineer, wants to see:
- the fault current, its source and the clearing time used;
- how the share through the soil was determined;
- the soil measurements and the model built from them;
- the calculated grid resistance and the method;
- the earth potential rise and whether it is above or below the thresholds that need extra treatment;
- touch and step voltages against the tolerable values from the documents;
- the conductor and joint ratings for the fault duration;
- the measurement plan after installation.
The thresholds and tolerable values come from TS 41-24, BS EN 50522 and the network operator.
IEEE 80 and the GB approach
IEEE 80 and the GB approach address the same physics but differ in method and limits. A project that connects to a GB network follows the documents the network operator names. If an international design already uses IEEE 80, the engineer checks it against TS 41-24 and BS EN 50522 before submission. What carries over between the two is the design chain above: fault current, share into the soil, resistance, rise and tolerable voltages.
Worked example: sizing an earth conductor for the fault
All values are illustrative assumptions. The material constant k and the rating duration stand in for the figures that TS 41-24 and the network operator give.
The general adiabatic relation for a conductor that heats up during a short fault is A = I × √t ÷ k. Here A is the cross-section in mm², I the fault current in A, t the duration in s and k a constant for the material and its temperature limits.
- Earth fault current at the substation: 8 000 A.
- The connection from an equipment frame to the grid carries the full current.
- Assumed rating duration: 1 s.
- Assumed constant for bare copper: k = 200.
- Connection to the equipment: 8 000 × √1 ÷ 200 = 40 mm².
- If the operator asks for a 3 s rating: 8 000 × 1.732 ÷ 200 = 69.3 mm². The next copper tape size up is 25 × 3 mm, which is 75 mm².
- A grid conductor fed from both ends carries a share only. With an assumed 60 % share at 3 s: 0.6 × 69.3 = 41.6 mm², so 25 × 3 mm still covers it with margin.
The duration changes the answer by √3 = 1.73, more than any other input. That is why the rating duration and its source are stated in the design, along with the share each conductor carries.
Checklist for the engineer
- Obtain fault current, clearing time and earthing arrangement from the network operator in writing.
- Confirm which issue of TS 41-24 the network operator applies.
- Measure soil resistivity on site and keep the raw data.
- Determine the current return paths and the share into the soil.
- Calculate grid resistance, earth potential rise, touch and step voltages and show the method.
- Check conductor and joint ratings for the fault duration.
- Assess transfer to telecoms, pipes, fences and low-voltage networks.
- Plan the post-installation measurements and the retest interval.
- Send the design to your chartered engineer for review.
Related guides
The gravel layer that changes surface voltages is explained in gravel layer and the Cs factor. The earthing of a solar site is in grounding of a solar plant. Protection clearing times come from the design in DNO protection requirements for a substation, and the fault current from the fault level guide.
From the specification to an earthing study your chartered engineer can review
We run the earthing study for a substation: fault current share, grid resistance, earth potential rise, touch and step voltages and transfer, with the assumptions written down. The report is ready for your chartered engineer to review and sign off before it goes to the network operator. Tiza does not sign, seal or certify studies in the UK. Contact us with the fault data and the site layout.
Frequently asked questions
What is ENA TS 41-24?
It is the Energy Networks Association technical specification for the design, installation, testing and maintenance of main earthing systems in substations. It is referenced by the Distribution Code, so network operators apply it to their own substations and to connected customer substations.
Which issue of TS 41-24 is current?
Issue 2, published in 2018, which aligns requirements and terminology with BS EN 50522. Always confirm the issue with the network operator whose network you connect to, since it names the version it applies.
Does TS 41-24 replace the IEEE 80 method?
No. They are separate documents with their own methods and limits. A GB network connection follows the documents the network operator names, which are usually TS 41-24 and the standards it references, not IEEE 80.