ENA EREC S34: Ground Potential Rise at Substations

ENA EREC S34 guides the assessment of earth potential rise at UK substations: touch, step and transferred voltage, with a worked rise calculation example.

By Shadai García, CEO and protection engineer at Tiza Group.

11 kV sourcesubstationbusbarfeeder 8,000 Asheath return 5,200 A (65 %)earth grid, Rg 0.8 Ωearth grid, Rg 0.4 Ω2,800 A intothe soilremote earthtelecom cableremotetransferredPowerEarth / sheathTelecomIg = 8,000 x (1 − 0.65) = 2,800 AEPR = 2,800 x 0.8 = 2,240 Vtouch 20 % = 448 V, above 300 V: failsRg 0.4 Ω: EPR 1,120 V, touch 224 V: passestransferred voltage still to assessVdistance01,1202,240gridEPR 2,240 VEPR 1,120 Vtouch 448 Vlimit 300 Vtouch 224 Vlimit 300 Vcarried out by thetelecom cableillustrative; touch = 20 % of the riseAssessmentFaultSheathGridEPRTouch© tizagrp.com11 kV sourcesubstationbusbarfeeder 8,000 Asheath return 5,200 A (65 %)earth grid, Rg 0.8 Ωearth grid, Rg 0.4 Ω2,800 A intothe soilremote earthtelecom cableremotetransferredPowerEarth / sheathTelecomIg = 8,000 x (1 − 0.65) = 2,800 AEPR = 2,800 x 0.8 = 2,240 Vtouch 20 % = 448 V, above 300 V: failsRg 0.4 Ω: EPR 1,120 V, touch 224 V: passestransferred voltage still to assessVdistance01,1202,240gridEPR 2,240 VEPR 1,120 Vtouch 448 Vlimit 300 Vtouch 224 Vlimit 300 Vcarried out by thetelecom cableillustrative; touch = 20 % of the riseAssessmentFaultSheathGridEPRTouch© tizagrp.com
ENA S34 earth potential rise: an 8,000 A earth fault at an 11 kV substation with 65 percent returning by the cable sheaths and 2,800 A entering the earth grid of 0.8 ohm for a rise of 2,240 V, the touch voltage of 448 V against the 300 V limit, the grid improved to 0.4 ohm for 1,120 V and 224 V, and the voltage carried out by a telecom cable. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

ENA EREC S34 is the UK guide for assessing the rise of earth potential at substations. A fault current flowing into the earth grid lifts its potential above remote earth. The designer finds the earth fault current that actually flows into the grid, multiplies by the grid resistance to get the rise, and compares the touch, step and transferred voltages with the tolerable limits the network operator applies.

Short answer: what ENA EREC S34 covers

ENA EREC S34 is the UK guide for assessing the rise of earth potential at substations. When an earth fault current flows through a substation’s earth grid into the ground, the grid rises in potential above remote earth. S34 gives methods to assess the maximum rise and the potentials around the site. It also addresses the effect on neighbouring networks and telecommunications. Issue 2, approved in 2018, aligns S34 with BS EN 50522. The earthing system itself (design, conductor ratings, installation and testing) follows ENA Technical Specification (TS) 41-24, revised at the same time and explained in the guide on ENA TS 41-24. The UK term is earth potential rise (EPR). The wider framework is in the UK electrical codes and grid connection guide.

The physics is the same as in the guide on ground potential rise. The UK frame adds what to assess, what the answer is compared with and what the network operator needs.

The chain from fault to voltage

The assessment follows a chain, in this order:

  1. Earth fault current. The highest single-phase earth fault current at the site, taken from the network operator’s fault level data, including future growth.
  2. Share into the grid. Part of the fault current returns by metallic paths, such as the cable sheath or an overhead earth wire, and does not enter the soil through the grid. Only the current that does is used for the rise. The guide on partial currents to earth explains the split.
  3. Grid resistance. The resistance of the earth system to remote earth, calculated and then measured. See grid resistance formulas and the ground resistance test.
  4. Rise of earth potential. Current into the grid times grid resistance.
  5. Touch, step and transferred voltages. A fraction of the rise appears between a person’s hand and feet, or across their feet, or is carried away by a metallic route to another place. See transferred voltage.
  6. Comparison with tolerable limits. The limits depend on how long the fault lasts and on the person’s body path. The basis is in tolerable body current.

The limits and factors, such as the treatment of sites with a high rise, come from S34, TS 41-24 and the network operator, who is the authority for its network.

Neighbours: telecoms and low-voltage supplies

A rise of potential at a substation does not stay inside the fence. Metallic telecommunications cables, pipes, and the earth of nearby low-voltage supplies can carry the voltage out, so the assessment looks at third parties as well as at the site. A substation where the rise is high needs more measures at the boundary and for any supply that crosses it, and the network operator involves the owners concerned. The low-voltage earthing arrangement of a customer supplied from the site is explained in TT, TN and IT systems.

Worked example

All values are illustrative.

Data. A single-phase earth fault of 8,000 A at an 11 kV substation. Of this, 65 % returns by the cable sheaths and does not enter the soil through the grid. The grid resistance to remote earth is 0.8 Ω. Assume that the touch voltage at the worst point is 20 % of the rise, and that the tolerable touch voltage for the fault duration is 300 V.

Step 1. Current into the grid. I_g = 8,000 × (1 − 0.65) = 2,800 A.

Step 2. Rise of earth potential. EPR = I_g × R_g = 2,800 × 0.8 = 2,240 V.

Step 3. Touch voltage. 20 % × 2,240 = 448 V. This is above the assumed tolerable value of 300 V, so the design fails and needs improvement.

Step 4. Improve the grid. Extend the grid and add electrodes until R_g = 0.4 Ω. EPR = 2,800 × 0.4 = 1,120 V. Touch voltage = 20 % × 1,120 = 224 V, below 300 V. The design passes, with a margin of 76 V.

Step 5. Check the other effects. The rise is still 1,120 V. The assessment of the transferred voltage to telecommunications and neighbouring supplies is therefore still needed. A passing touch voltage does not settle that question.

Step 6. Alternative. Faster fault clearing allows a higher tolerable touch voltage, so a protection study that shortens the fault duration is a second lever. It is checked against the actual protection and breaker times, which the study must state.

What to measure on site

A calculated rise is only as good as the soil model. After construction, measure the grid resistance and compare it with the calculated value, and check the continuity between the grid, the fences and the bonded metalwork. A large difference between calculation and measurement means the soil model is wrong, and the assessment is repeated with the measured values.

Checklist for the engineer

  • Take the maximum earth fault current and future growth from the network operator.
  • Calculate the split between the metallic return paths and the current into the grid.
  • Calculate the grid resistance, then plan to measure it on site.
  • Calculate the earth potential rise and the touch, step and transferred voltages.
  • Compare them with the limits that the operator applies for the fault duration.
  • Assess the effect on telecommunications, pipes and neighbouring supplies.
  • Record the soil model and the assumptions behind it.
  • Plan the commissioning measurements and keep the records with the design.

The other UK network documents that DNO studies use are G5 on harmonics, P28 on flicker and G98 versus G99. For a method used elsewhere, see the IEEE 80 substation grounding design. For the physical layout, read the substation grounding grid, grounding of distribution substations and the equipotential bonding network. For cable shields, see cable shield bonding.

From the rules to a study your chartered engineer can review

An earthing assessment needs the fault data, a soil model and the comparison with the operator’s limits. We prepare the earthing design and the power-system studies behind it, ready for your chartered engineer to review and sign before they go to the network operator. Tiza does not stamp, sign or certify designs in the UK. Contact us with the fault levels and the site layout.

Frequently asked questions

What is ENA EREC S34?

S34 is the ENA Engineering Recommendation for assessing the rise of earth potential at substation sites. It sets out methods to assess the maximum rise and the local potentials around the installation, and its effect on neighbouring networks and telecommunications.

What is ground potential rise?

It is the voltage that appears between a substation's earth grid and remote earth when an earth fault current flows into the ground through the grid. It equals the current into the grid times the grid resistance, and it is the starting point for touch, step and transferred voltages.

Is S34 the same as IEEE 80?

No. Both address the same physics: fault current into earth, rise of potential, touch and step voltages. They differ in methods and in how tolerable limits are set. A UK project follows the documents the network operator names, S34 and the ENA technical specification for substation earthing.