ENA Engineering Recommendation P2 is the security of supply standard used to plan GB distribution networks. Issue 8 was approved by Ofgem in 2023 and replaces P2/7. It sets how much demand must be restored, and how quickly, after circuit outages, so it drives the redundancy that network operators build and the capacity they offer to customers.
Short answer: what ENA EREC P2 sets
ENA EREC P2 is the security of supply standard for GB distribution networks, and it decides how much redundancy a network operator builds for a given amount of demand. The current edition is Issue 8, which Ofgem approved in 2023 under Distribution Code proposal DCRP/22/03. It replaces P2/7 of 2019. In plain terms, P2 states the minimum demand that must be supplied again, and within what time, in different outage scenarios. A companion document, Engineering Report 130 (Issue 4, 2023), explains how to assess whether a network meets the standard.
The standard belongs to the ENA layer in the UK electrical codes and grid connection guide. It is a planning rule for the operator’s network. It matters to a customer because it shapes how a connection is offered: the number of circuits, the firm capacity and the reinforcement.
The idea behind it
A network is made of circuits and transformers that can fail or be taken out for maintenance. P2 asks the planner to test the network against outages and to check that a defined part of the demand stays supplied or is restored in a defined time. The larger the group of customers behind a point in the network, the stronger the standard that applies to it, because an outage there affects more people.
In design terms this is the N-1 idea: with one element out, the remaining elements carry the load. The guide on N-1 contingencies in a load flow shows how the check is run. The numbers a planner must meet, such as the demand classes and the restoration times, are set in P2 itself.
What it means for a customer
- A single-circuit connection is cheaper but can be lost for the duration of a repair. If the load cannot accept that, the customer asks for a second route or an alternative supply.
- Firm capacity is the capacity left after the largest element is out of service. The operator offers capacity on the basis of the firm capacity of the substation behind the connection.
- Generation and storage can count towards security in some arrangements, subject to the rules and the contract, and they can also reduce the capacity available if the offer restricts them.
- Critical loads need their own arrangement behind the connection. See critical loads: power supply structures and supply disturbances and their effect on protection.
How the check is run
- List the group of demand that depends on the substation, at the time of maximum demand, with growth.
- List the outage scenarios: one transformer or circuit out, and other cases the standard defines.
- For each scenario, find the demand that remains supplied by the other elements, including transfers from neighbouring networks.
- Compare with what the standard requires, including the time allowed to restore.
- If it fails, plan reinforcement: more capacity, another circuit, automatic switching or demand transfer.
Worked example: firm capacity of a primary substation
All figures are illustrative. The cyclic rating is assumed equal to the nameplate for simplicity, which a real study would not do.
- Two transformers of 20 MVA each.
- Present maximum demand: 14 MW at power factor 0.95.
- Growth: 3 % per year, for 5 years.
- Present apparent power: 14 ÷ 0.95 = 14.74 MVA.
- Demand in 5 years: 14.74 × 1.03^5 = 14.74 × 1.1593 = 17.08 MVA.
- With one transformer out, the remaining one carries the whole demand. Firm capacity is 20 MVA.
- Loading after one outage today: 14.74 ÷ 20 = 74 %. In 5 years: 17.08 ÷ 20 = 85 %.
The substation stays within the remaining transformer’s rating in both cases. A new load connection would change the sum. If a 10 MW load connected at the same power factor, the new total in 5 years would be 17.08 + 10 ÷ 0.95 = 17.08 + 10.53 = 27.61 MVA, above the 20 MVA firm capacity. The shortfall is 7.61 MVA. The operator would then offer reinforcement, a transfer scheme or a restriction. The customer reads that in the offer as a condition or a cost.
Reading the result in a connection offer
The effect of P2 reaches a customer in three ways. A connection may be offered on a single circuit with a stated loss of supply time for a fault. It may be offered on two circuits where the demand is large enough to need that security. Or it may carry a condition that the operator can restrict the load when an element is out, a so-called curtailment arrangement, which the customer must be able to accept.
An engineer reads the offer for these points and compares them with the load. A data centre, a hospital or a process plant will usually need more than the minimum the standard requires for its group of demand, and the extra security is the customer’s design and cost. The guide on critical loads covers that arrangement behind the connection.
Checklist for the engineer
- Ask the operator which issue of P2 it applies and what it assumes for your group of demand.
- State the maximum demand, growth and power factor you use.
- Identify the firm capacity of the substation behind your connection.
- Check whether your connection is single-circuit and what an outage means for the load.
- Define the loads that need a second supply and the arrangement behind the connection.
- Ask whether any generation or storage counts towards security in the arrangement.
- Compare the offer’s reinforcement conditions with your own sums.
- Send the supply arrangement to your chartered engineer for review.
Related guides
The studies that sit beside this are in maximum and minimum short-circuit current and the sister guide on fault levels. For the connection process see solar farm grid connection.
From the standard to a power-system study your chartered engineer can review
We run the power-system studies behind a supply arrangement: load flow in normal and outage states, firm capacity and the effect of new load or generation, with the assumptions written down. The report is ready for your chartered engineer to review and sign off. Tiza does not sign, seal or certify studies in the UK. Contact us with the demand data and the network operator’s information.
Frequently asked questions
What is ENA EREC P2?
It is the Energy Networks Association engineering recommendation that sets the security of supply standard for GB distribution networks. It states the minimum demand a network must be able to supply, and how quickly, in different outage scenarios. Network operators use it to plan and reinforce their networks.
Which issue of P2 is current?
Issue 8, approved by Ofgem in 2023 under Distribution Code proposal DCRP/22/03, which replaces P2/7 of 2019. The companion Engineering Report 130 describes how to assess a network against it. Confirm with the network operator which issue it applies.
Does P2 apply to a customer's own substation?
P2 is a planning standard for the network operator's system. It does not apply to a customer's internal network. It matters to the customer because it shapes the supply arrangements, the firm capacity and the reinforcement the network operator offers.