Solar Farm Grid Connection UK: Process and Timeline

How a solar farm connects to the GB electricity grid: application, queue reform, Gate 2, the offer, G99 or Grid Code compliance and a programme example.

By Shadai García, CEO and protection engineer at Tiza Group.

1Site and capacitydeveloper2ApplicationDNO or NESO3Queue positionreformed queue, Gate 24Offer and acceptancenetwork operator5Design and approvalsdeveloper, operator approves6Construction and compliancedeveloper7Energisation and operationafter approval45 MW at 33 kV: between 10 and 50 MW, Type C45,000 / (1.732 x 33) = 787 A at unity PFat 0.95: 47,368 kVA = 829 A; DC/AC 1.16procurement ends at month 2 + 9 = 11construction to 19, commissioning to month 21transformer 3 months late: month 2404111921monthdesign and approval, 4procurement, 9 months (critical path)construction, 8commissioning, 2energisationmonth 24assumed durations for the example, not typical timesRouteCapacityApplicationOfferBuildEnergise© tizagrp.com1Site and capacitydeveloper2ApplicationDNO or NESO3Queue positionreformed queue, Gate 24Offer and acceptancenetwork operator5Design and approvalsdeveloper, operator approves6Construction and compliancedeveloper7Energisation and operationafter approval45 MW at 33 kV: between 10 and 50 MW, Type C45,000 / (1.732 x 33) = 787 A at unity PFat 0.95: 47,368 kVA = 829 A; DC/AC 1.16procurement ends at month 2 + 9 = 11construction to 19, commissioning to month 21transformer 3 months late: month 2404111921monthdesign and approval, 4procurement, 9 months (critical path)construction, 8commissioning, 2energisationmonth 24assumed durations for the example, not typical timesRouteCapacityApplicationOfferBuildEnergise© tizagrp.com
Solar farm connection route in seven stages: site and capacity, application, queue position, offer and acceptance, design and approvals, construction and compliance, energisation, with the 45 MW example at 33 kV of 787 A and 829 A at 0.95 power factor and the programme of 4 months design, 9 months procurement from month 2, 8 months construction and 2 months commissioning, energisation at month 21. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

A solar farm in Great Britain connects through its distribution network operator or, for the largest plants, through the National Energy System Operator. The route runs from application to an offer, acceptance, design, compliance evidence and energisation, and the connections reform decides when a project can move.

Short answer: the route from site to energisation

A solar farm in Great Britain connects by applying to its network operator, accepting a connection offer, designing and building to the technical rules, proving compliance and then energising. The queue reform decides when a project can move through that route. The route has seven stages, and delays usually come from the stage that waits on someone else’s decision.

The technical documents behind these stages are explained in the UK electrical codes and grid connection guide. Below are the process and the time each stage takes.

The stages

  1. Site and capacity. The developer fixes the export capacity in MW, the voltage level and the likely point of connection. These three set the route and the Type under ENA EREC G99.
  2. Application. The application goes to the distribution network operator (DNO) or, at transmission level, to the National Energy System Operator (NESO). It carries site data, capacity and a single-line diagram.
  3. Queue position. Under the connections reform, the position in the queue and the readiness evidence decide when an offer is issued. Gate 2 is the step in which projects are assessed for their place in the reordered queue.
  4. Offer and acceptance. The offer sets the point of connection, capacity, works, charges and conditions. Acceptance starts the delivery of the works.
  5. Design and approvals. The developer finishes the design, submits the protection and control details and gets the network operator’s approval.
  6. Construction and compliance. The plant is built, tested and documented. The compliance evidence goes to the network operator.
  7. Energisation and operation. After approval the plant is energised and operates under the agreement.

Where the queue reform fits

The connections reform run by NESO reorders the queue so that projects that are ready move first. Ofgem agreed an alternative timetable on 3 June 2026 under which offers are issued in batches, with the last batch expected by mid-March 2027. For a developer this means an offer may arrive on a revised date and with changed terms. The status of a project is what counts, so confirm it with the network operator and not from a general summary.

Which technical route applies

Size and levelDocumentWho checks
Up to 16 A per phase per installationENA EREC G98DNO
Above that on the distribution networkENA EREC G99, Types A to DDNO
Larger plants covered by the Grid CodeGrid Code compliance processNESO and the network owner

G99 sorts generating modules into Types A to D by capacity and connection voltage. The thresholds are in the guide on G99 Types A to D: Type A from 0.8 kW, B from 1 MW, C from 10 MW, and D from 50 MW or at 110 kV and above. The Type decides how much evidence the network operator asks for.

Documents the engineer prepares

Worked example: capacity and a programme

All figures are illustrative. The durations are assumptions for the example, not typical or promised times.

Capacity check.

  • Export capacity: 45 MW at 33 kV. That lies between 10 and 50 MW, so it is a G99 Type C module.
  • Rated current at unity power factor: 45 000 kW ÷ (√3 × 33 kV) = 45 000 ÷ 57.16 = 787 A.
  • At 0.95 power factor: 45 000 ÷ 0.95 = 47 368 kVA, and 47 368 ÷ 57.16 = 829 A. The cable, switchgear and transformer ratings follow the higher figure.
  • Installed DC capacity of 52 MWp gives a DC-to-AC ratio of 52 ÷ 45 = 1.16.

Programme after acceptance of the offer (assumed durations).

  • Detailed design and network operator approval: 4 months.
  • Procurement of the main transformer and switchgear: 9 months, running in parallel with the design after month 2.
  • Civil and electrical construction: 8 months, starting when the equipment arrives.
  • Commissioning and compliance evidence: 2 months.
  1. The procurement ends at month 2 + 9 = month 11.
  2. Construction runs from month 11 to month 11 + 8 = month 19.
  3. Commissioning ends at month 19 + 2 = month 21.

The critical path is procurement, not design. A one-month delay in design would change nothing, but a three-month delay in the transformer moves energisation to month 24. If the offer’s connection works by the network operator finish after month 21, those works become the critical path. The offer states its own dates, and that is why a developer reads them before fixing the plan.

Checklist for the engineer

  • Confirm the capacity, voltage level and G99 Type or Grid Code route in writing with the network operator.
  • Check the queue status and the dates in the offer against your programme.
  • List the network operator’s works and who carries them out.
  • Set the point of connection, metering and protection on the single-line diagram.
  • Prepare the compliance documents for the Type, and keep the equipment certificates.
  • Identify long-lead equipment and place orders against the programme.
  • Add a margin to the programme for approvals that depend on the network operator.
  • Send the design to your chartered engineer for review before submission.

The wider design of a plant is in solar park engineering and design, and the connection of storage on the same site is in the sister guide on battery storage connection under G99 and the Grid Code. For the studies that follow an application see DNO protection requirements for a substation.

From the process to engineering your chartered engineer can review

We prepare the engineering package for a UK connection: single-line diagram, protection philosophy, earthing and the documents the network operator asks for, arranged to follow the stages above. It is ready for your chartered engineer to review and sign off. Tiza does not sign, seal or certify designs in the UK. Contact us with the site capacity and the status of your offer.

Frequently asked questions

Who do I apply to for a solar farm grid connection in Great Britain?

For most solar farms connecting to the distribution network, the application goes to the local distribution network operator. For plants connecting at transmission level, the connection offer is made by the National Energy System Operator. The size and the voltage level set the route.

What is Gate 2 in the connections reform?

Gate 2 is part of the reform run by the National Energy System Operator to reorder the queue so that projects that are ready and needed move first. Ofgem agreed a timetable on 3 June 2026 with offers issued in batches and the last batch expected by mid-March 2027. Check your project's status with the network operator.

Which documents govern a solar farm connection?

The connection offer and the connection agreement set the commercial and technical terms. Technically, ENA EREC G99 applies to generation on the distribution network, and the Grid Code applies to the larger plants that it covers. Your network operator confirms which applies.