A solar farm in Great Britain connects through its distribution network operator or, for the largest plants, through the National Energy System Operator. The route runs from application to an offer, acceptance, design, compliance evidence and energisation, and the connections reform decides when a project can move.
Short answer: the route from site to energisation
A solar farm in Great Britain connects by applying to its network operator, accepting a connection offer, designing and building to the technical rules, proving compliance and then energising. The queue reform decides when a project can move through that route. The route has seven stages, and delays usually come from the stage that waits on someone else’s decision.
The technical documents behind these stages are explained in the UK electrical codes and grid connection guide. Below are the process and the time each stage takes.
The stages
- Site and capacity. The developer fixes the export capacity in MW, the voltage level and the likely point of connection. These three set the route and the Type under ENA EREC G99.
- Application. The application goes to the distribution network operator (DNO) or, at transmission level, to the National Energy System Operator (NESO). It carries site data, capacity and a single-line diagram.
- Queue position. Under the connections reform, the position in the queue and the readiness evidence decide when an offer is issued. Gate 2 is the step in which projects are assessed for their place in the reordered queue.
- Offer and acceptance. The offer sets the point of connection, capacity, works, charges and conditions. Acceptance starts the delivery of the works.
- Design and approvals. The developer finishes the design, submits the protection and control details and gets the network operator’s approval.
- Construction and compliance. The plant is built, tested and documented. The compliance evidence goes to the network operator.
- Energisation and operation. After approval the plant is energised and operates under the agreement.
Where the queue reform fits
The connections reform run by NESO reorders the queue so that projects that are ready move first. Ofgem agreed an alternative timetable on 3 June 2026 under which offers are issued in batches, with the last batch expected by mid-March 2027. For a developer this means an offer may arrive on a revised date and with changed terms. The status of a project is what counts, so confirm it with the network operator and not from a general summary.
Which technical route applies
| Size and level | Document | Who checks |
|---|---|---|
| Up to 16 A per phase per installation | ENA EREC G98 | DNO |
| Above that on the distribution network | ENA EREC G99, Types A to D | DNO |
| Larger plants covered by the Grid Code | Grid Code compliance process | NESO and the network owner |
G99 sorts generating modules into Types A to D by capacity and connection voltage. The thresholds are in the guide on G99 Types A to D: Type A from 0.8 kW, B from 1 MW, C from 10 MW, and D from 50 MW or at 110 kV and above. The Type decides how much evidence the network operator asks for.
Documents the engineer prepares
- The single-line diagram with the point of connection, metering and protection.
- Equipment data: inverters, transformers, cables and certificates.
- Protection and interface settings. See interconnection relays for generation.
- Short-circuit data and fault contribution. See maximum and minimum short-circuit current for how the two cases are used.
- A commissioning plan. See solar plant commissioning tests.
- An earthing design for the substation and the collector system. See grounding of a solar plant.
Worked example: capacity and a programme
All figures are illustrative. The durations are assumptions for the example, not typical or promised times.
Capacity check.
- Export capacity: 45 MW at 33 kV. That lies between 10 and 50 MW, so it is a G99 Type C module.
- Rated current at unity power factor: 45 000 kW ÷ (√3 × 33 kV) = 45 000 ÷ 57.16 = 787 A.
- At 0.95 power factor: 45 000 ÷ 0.95 = 47 368 kVA, and 47 368 ÷ 57.16 = 829 A. The cable, switchgear and transformer ratings follow the higher figure.
- Installed DC capacity of 52 MWp gives a DC-to-AC ratio of 52 ÷ 45 = 1.16.
Programme after acceptance of the offer (assumed durations).
- Detailed design and network operator approval: 4 months.
- Procurement of the main transformer and switchgear: 9 months, running in parallel with the design after month 2.
- Civil and electrical construction: 8 months, starting when the equipment arrives.
- Commissioning and compliance evidence: 2 months.
- The procurement ends at month 2 + 9 = month 11.
- Construction runs from month 11 to month 11 + 8 = month 19.
- Commissioning ends at month 19 + 2 = month 21.
The critical path is procurement, not design. A one-month delay in design would change nothing, but a three-month delay in the transformer moves energisation to month 24. If the offer’s connection works by the network operator finish after month 21, those works become the critical path. The offer states its own dates, and that is why a developer reads them before fixing the plan.
Checklist for the engineer
- Confirm the capacity, voltage level and G99 Type or Grid Code route in writing with the network operator.
- Check the queue status and the dates in the offer against your programme.
- List the network operator’s works and who carries them out.
- Set the point of connection, metering and protection on the single-line diagram.
- Prepare the compliance documents for the Type, and keep the equipment certificates.
- Identify long-lead equipment and place orders against the programme.
- Add a margin to the programme for approvals that depend on the network operator.
- Send the design to your chartered engineer for review before submission.
Related guides
The wider design of a plant is in solar park engineering and design, and the connection of storage on the same site is in the sister guide on battery storage connection under G99 and the Grid Code. For the studies that follow an application see DNO protection requirements for a substation.
From the process to engineering your chartered engineer can review
We prepare the engineering package for a UK connection: single-line diagram, protection philosophy, earthing and the documents the network operator asks for, arranged to follow the stages above. It is ready for your chartered engineer to review and sign off. Tiza does not sign, seal or certify designs in the UK. Contact us with the site capacity and the status of your offer.
Frequently asked questions
Who do I apply to for a solar farm grid connection in Great Britain?
For most solar farms connecting to the distribution network, the application goes to the local distribution network operator. For plants connecting at transmission level, the connection offer is made by the National Energy System Operator. The size and the voltage level set the route.
What is Gate 2 in the connections reform?
Gate 2 is part of the reform run by the National Energy System Operator to reorder the queue so that projects that are ready and needed move first. Ofgem agreed a timetable on 3 June 2026 with offers issued in batches and the last batch expected by mid-March 2027. Check your project's status with the network operator.
Which documents govern a solar farm connection?
The connection offer and the connection agreement set the commercial and technical terms. Technically, ENA EREC G99 applies to generation on the distribution network, and the Grid Code applies to the larger plants that it covers. Your network operator confirms which applies.