BS 7430 Earthing Code of Practice: 2026 Edition

BS 7430 earthing code of practice explained: the 2026 edition, electrode design, HV-derived supplies and generators, and an electrode resistance example.

By Shadai García, CEO and protection engineer at Tiza Group.

TT installation: own electrodeMETground levelρ = 100 Ω·m2.4 mØ 16 mm4.8 m: twice the lengthmutual effect 3.3 ΩEarthing conductorR = ρ / (2πL) × (ln(8L/d) − 1)100 / (2π × 2.4) = 6.63 Ωln(1,200) − 1 = 6.09one rod: 6.63 × 6.09 = 40.4 Ωmutual: 100 / (2π × 4.8) = 3.3 Ω(40.4 + 3.3) / 2 = 21.9 Ω, not 20.2× 1.5 seasonal margin = 33 Ωlimit at 100 mA: 500 Ω; a 5 Ω target: noone rod 40.4 Ωtwo rods ignoring mutual 20.2 Ωtwo rods 21.9 Ωwith seasonal margin 33 ΩΩ010203040illustrative values; soil assumedElectrodeSoilRodSecond rodParallelMargin© tizagrp.comTT installation: own electrodeMETground levelρ = 100 Ω·m2.4 mØ 16 mm4.8 m: twice the lengthmutual effect 3.3 ΩEarthing conductorR = ρ / (2πL) × (ln(8L/d) − 1)100 / (2π × 2.4) = 6.63 Ωln(1,200) − 1 = 6.09one rod: 6.63 × 6.09 = 40.4 Ωmutual: 100 / (2π × 4.8) = 3.3 Ω(40.4 + 3.3) / 2 = 21.9 Ω, not 20.2× 1.5 seasonal margin = 33 Ωlimit at 100 mA: 500 Ω; a 5 Ω target: noone rod 40.4 Ωtwo rods ignoring mutual 20.2 Ωtwo rods 21.9 Ωwith seasonal margin 33 ΩΩ010203040illustrative values; soil assumedElectrodeSoilRodSecond rodParallelMargin© tizagrp.com
BS 7430 earthing code of practice: two earth rods of 2.4 m and 16 mm driven 4.8 m apart in soil of 100 ohm metres and joined in parallel to the main earthing terminal of a TT installation, with one rod at 40.4 ohm, a mutual effect of 3.3 ohm giving 21.9 ohm and not 20.2 ohm, and 33 ohm with a seasonal margin of 1.5, against a limit of 500 ohm with a 100 mA RCD. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

BS 7430 is the British code of practice for protective earthing of electrical installations. A new edition, BS 7430:2026, took effect on 31 May 2026 and replaced BS 7430:2011+A1:2015, which was withdrawn. According to the ECA, the update adds earthing guidance for supplies derived from high voltage, revises the recommendations for generators on TN-S and IT systems, and covers protective neutral bonding and earth electrodes. Below, the code is placed next to BS 7671 and an electrode resistance example is worked.

Earthing has a reputation for being solved by banging a rod into the ground. The engineering is more careful: the soil decides what is possible, the system decides what is needed, and the measurements decide whether the design worked. BS 7430 is the British code that brings the three together. The legal and requirement side is in BS 7671 Chapter 54 and in the UK electrical codes and grid connection guide.

Short answer: what is the BS 7430 earthing code of practice?

BS 7430 is the British Standards code of practice for protective earthing of electrical installations. It gives recommendations on how to design, install and maintain earthing, from soil resistivity and electrode types to the earthing of supplies derived from high voltage. The edition in force is BS 7430:2026, which came into effect on 31 May 2026 and replaced BS 7430:2011+A1:2015. A code of practice does not carry the force of a requirement the way BS 7671 does, but it is the reference most designers and reviewers use for good practice.

What the 2026 edition changes

According to the Electrical Contractors’ Association (ECA), the revised standard includes updated earthing guidance for supplies derived from high voltage, covering public and private transformers, combined HV and LV earthing, and HV/LV and LV/LV separation. It revises the recommendations for generators on TN-S and IT systems, and it covers the application of protective neutral bonding and earth electrode recommendations. It also deals with more complex or higher-risk environments and removes the section on special installations. The reasoning behind the revision, as the ECA puts it, is that installations now include EV charging, storage and distributed generation. Use the standard itself for the detail.

Where BS 7430 fits with other documents

A site often meets all of them. A factory fed at 11 kV has a substation earth under the network rules and an installation earth under BS 7671 and BS 7430, and the two must be coordinated; see industrial earthing and the equipotential bonding network.

Soil and electrode design

The resistance of an electrode is set by the soil resistivity around it and by its geometry. Resistivity varies by location, depth and season: wet clay is low, dry sand or rock is high, and the top layer changes with rain and frost. A designer measures resistivity on site, models the soil in layers where it matters, and keeps a seasonal margin. Common electrodes are vertical rods, horizontal tapes, plates and the foundation steel of a building. Deeper rods or more rods in parallel lower the resistance, with diminishing returns when they are too close together, because their fields overlap. The measurement methods are in the earth analyser guide and the equipotential bonding guide.

Worked example: a rod electrode

The numbers are illustrative and the data are assumed. A TT installation needs an electrode. The measured soil resistivity is 100 Ω·m. The rod is 2.4 m long and 16 mm in diameter. For a single vertical rod, a common engineering formula is R = ρ / (2πL) × (ln(8L/d) − 1).

  1. Geometry factor: ρ / (2πL) = 100 / (2π × 2.4) = 6.63 Ω.
  2. Logarithm term: ln(8 × 2.4 / 0.016) = ln(1,200) = 7.09, minus 1 is 6.09.
  3. One rod: R = 6.63 × 6.09 = 40.4 Ω.
  4. A second rod is driven 4.8 m away, twice the length. The mutual effect of the first on the second is about ρ / (2π × 4.8) = 3.3 Ω.
  5. Two rods in parallel with that mutual effect: (40.4 + 3.3) / 2 = 21.9 Ω, not 20.2 Ω.
  6. Apply a seasonal margin of 1.5 for dry weather: 21.9 × 1.5 = 33 Ω.

With a 100 mA residual current device (RCD) on a TT supply, the limit that keeps the touch voltage below 50 V is 500 Ω, so the electrode passes with a large margin, and even one rod would do. If the same electrode had to serve an HV-derived system with a target of, say, 5 Ω, this soil would need a different solution: a grid, a deeper rod or soil treatment. The same soil gives a different answer because the target comes from the system.

Figure: a single-line diagram of two earth rods in parallel connected to a main earthing terminal, with the soil resistivity and the rod spacing marked.

Common problems in practice

  • Using one resistivity reading taken in a wet month as if it held all year.
  • Placing rods closer together than their length, so the parallel resistance drops much less than expected.
  • Taking the old edition’s recommendation into a design without checking the current edition.
  • Joining the installation earth and an HV substation earth without a study.
  • No test link or inspection pit, so the electrode can never be measured.
  • Using an electrode resistance from a nearby site with different soil.

Checklist for the engineer

  • State which edition of the code is followed, and the edition of BS 7671.
  • Measure the soil resistivity, with a record of the date and the season.
  • Define the target resistance from the system and not from habit.
  • Choose the electrode type and layout, and compute the resistance with a seasonal margin.
  • Check touch and step voltages where the HV system is involved.
  • Specify test links, labels and a maintenance interval.
  • Plan the measurement of the finished electrode; see the inspection and testing guide.

In the UK there is no statutory stamp for earthing designs. A chartered engineer or other competent person reviews the design and signs it under their own responsibility. The duty to keep the system safe is in the Electricity at Work Regulations 1989, and the supply side is covered by the ESQCR 2002.

How Tiza can help

If your project needs an earthing design, Tiza prepares the engineering remotely and in English: soil model and electrode calculations, touch voltage checks and the documents that go with them. Tiza does not stamp, sign or certify designs in the UK; we deliver engineering ready for your chartered engineer to review and sign. Contact us with the soil data and the single-line diagram.

Frequently asked questions

What is the current edition of BS 7430?

BS 7430:2026 is current. It came into effect on 31 May 2026 and replaced BS 7430:2011+A1:2015, which is withdrawn. A design done under the old edition is not wrong because of the change, but new designs and reviews should record which edition they follow.

How does BS 7430 differ from BS 7671?

BS 7671 sets the requirements for the safety of an installation, including the earthing arrangements of Chapter 54. BS 7430 is a code of practice that gives recommendations and design guidance on how to achieve protective earthing, including electrode design, soil, and special supplies. A code of practice is recommendations and not a requirement of law, but it is the usual reference for good practice.

How low does an earth electrode resistance need to be?

There is no single number. On a TT installation, the electrode resistance and the RCD rating must keep the touch voltage under 50 V, which allows high values with a sensitive RCD. For an HV-derived supply or a substation, the limit comes from the network operator's rules and a touch voltage study. The target comes from the system, not from the code in the abstract.