Electricity at Work Regulations 1989 explained: who the duty holders are, what regulations 4, 5, 13, 14 and 16 require and a worked equipment rating check.

By Shadai García, CEO and protection engineer at Tiza Group.

DNO transformerPENPE and N linked800 kVA, 5 %400 Vboardoutgoing16 kA25 kAPENLineN, PE800,000 / (√3 x 400) = 1,155 A1,155 / 0.05 = 23,094 A = 23.1 kAexisting breakers: 16 kA, below 23.1 kAreplace with at least 25 kA before energisingsame check for every upgradekA010202523.1 kAexisting breaker: 16 kAreplacement: 25 kAillustrative values; infinite source assumedFault level1,155 A23.1 kA16 kAReplace25 kA© tizagrp.comDNO transformerPENPE and N linked800 kVA, 5 %400 Vboardoutgoing16 kA25 kAPENLineN, PE800,000 / (√3 x 400) = 1,155 A1,155 / 0.05 = 23,094 A = 23.1 kAexisting breakers: 16 kA, below 23.1 kAreplace with at least 25 kA before energisingsame check for every upgradekA010202523.1 kAexisting breaker: 16 kAreplacement: 25 kAillustrative values; infinite source assumedFault level1,155 A23.1 kA16 kAReplace25 kA© tizagrp.com
Electricity at Work Regulations 1989: an 800 kVA transformer of 5 % impedance on a TN-C-S supply feeding a 400 V board with outgoing breakers, a prospective fault current of 23.1 kA exceeding the 16 kA breaking capacity of the existing breakers, and the replacement breakers of 25 kA clearing the fault. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

The Electricity at Work Regulations 1989 are short, public regulations made under the Health and Safety at Work etc. Act 1974. They put duties on employers, the self-employed and employees to keep electrical systems and work activities safe, within their control. They state outcomes, not methods: systems built and maintained to prevent danger so far as is reasonably practicable, work on dead equipment as the rule, live work only under three conditions, and competent people.

These regulations are short, but they are the legal root of nearly everything else in electrical safety in the UK. The technical standards say how to build; the regulations say what must be achieved and who answers for it. They sit in the first layer of the framework described in the UK electrical codes and grid connection guide. For the network side, see the ESQCR 2002 guide.

Short answer: what do the Electricity at Work Regulations 1989 require?

The Electricity at Work Regulations 1989 (EAWR), statutory instrument 1989 number 635, were made under the Health and Safety at Work etc. Act 1974. They require electrical systems to be built and maintained so as to prevent danger, so far as is reasonably practicable, and work activities to be carried out so as not to give rise to danger. They put the duty on employers, the self-employed and employees for the matters within their control. They are public law on legislation.gov.uk.

Structure

The regulations have four parts: introduction (1 to 3), general duties (4 to 16), mines only (17 to 28) and miscellaneous provisions (29 to 33). The general duties in regulations 4 to 16 apply to most workplaces, and the revised text on legislation.gov.uk is the one to cite.

Duty holders

Regulation 3 sets out who is bound. Employers and the self-employed must comply as far as the matter is within their control. Employees at work must cooperate with their employer so that the employer can meet the duties, and must comply with the regulations as far as the matters are within their own control. Two points follow for a project. The duty follows control: the owner of a site, the maintenance contractor and the designer each hold duties for the part they control. And a duty can fall on an individual engineer as an employee.

The regulations that matter in design and maintenance

RegulationTitleIn plain terms
4Systems, work activities and protective equipmentSystems are built and maintained to prevent danger, and work is done without danger, so far as is reasonably practicable. Protective equipment must be suitable, maintained and used properly
5Strength and capability of electrical equipmentEquipment must not be used where it could be overloaded beyond its strength or capacity in a way that causes danger
6Adverse or hazardous environmentsEquipment suits its environment: weather, mechanical damage, dust, flammable atmospheres
7Insulation, protection and placing of conductorsLive conductors are covered or placed so as to prevent danger
8Earthing or other suitable precautionsMetalwork that could become live in a fault is earthed or otherwise made safe
11Means for protecting from excess of currentProtection against overcurrent
12Means for cutting off the supply and for isolationEquipment can be switched off and isolated
13Precautions for work on equipment made deadDead equipment is proved dead and kept so while people work on it
14Work on or near live conductorsLive work only under three conditions
16Persons to be competent to prevent danger and injuryPeople with the right knowledge or experience, or properly supervised

Regulations 4(1) to 4(3) carry the qualifier “so far as is reasonably practicable”. Regulation 4(4), on protective equipment, does not. Regulation 29 gives a defence for breaches of regulations 4(4), 5, 8 to 16 and 25 to a person who took all reasonable steps and exercised due diligence to avoid the offence.

Live working under regulation 14

The default is to work dead. Regulation 14 allows work on or near live conductors only if three things are true together. First, it is unreasonable for the conductor to be dead. Second, it is reasonable for the person to work on it live. Third, suitable precautions, including protective equipment, are taken to prevent injury. For arc flash and protective clothing, see arc flash PPE categories, and for isolation in practice, lockout and tagout in solar plants.

Competence under regulation 16

Nobody may take part in a work activity that needs technical knowledge or experience to prevent danger unless they have it, or are supervised to a degree appropriate to the work. In practice, that includes the engineer who designs, the person who tests and the person who switches.

Worked example: regulation 5 in a transformer upgrade

The numbers are illustrative. A site has a 400 V board with outgoing circuit breakers rated for a breaking capacity of 16 kA. The owner replaces a 500 kVA transformer with an 800 kVA unit of 5% impedance. Regulation 5 asks whether the equipment’s strength and capability could be exceeded.

  1. Rated current of the new transformer on the 400 V side: 800,000 / (√3 × 400) = 1,155 A.
  2. Prospective short-circuit current at the transformer terminals, assuming an infinite source: 1,155 / 0.05 = 23,094 A, which is 23.1 kA.
  3. The existing breakers can break 16 kA. 23.1 kA is above that, so the breaking capacity is exceeded in the foreseeable fault.
  4. The outgoing breakers must be replaced by devices of at least 25 kA, or the fault level must be limited by another means, before the new transformer is energised.

The same logic applies to every upgrade of the supply, the load or the generation on a site. Method and data for the calculation are in the guides on maximum and minimum short-circuit current and breaking capacity and limitation in LV circuit breakers.

Figure: a single-line diagram of a transformer feeding a 400 V board with outgoing breakers, with the prospective fault current and the breaking capacity of each device marked.

Common problems in practice

  • Treating the regulations as a checklist, when they require judgement on the facts.
  • Updating a supply without recalculating the fault level at the existing boards.
  • Live working justified by convenience.
  • Records of competence that do not match the work given to a person.
  • Assuming a contractor’s competence relieves the owner of a duty for the systems under the owner’s control.

Checklist for the engineer

  • Identify who has control of each system and activity, and so who holds the duty.
  • Check the strength and capability of each device against the foreseeable fault, after every change.
  • Show how isolation and proving dead are achieved for each maintenance task.
  • If live work is proposed, document each of the three conditions.
  • Match the task to the competence and supervision of the people assigned.
  • Keep the records that show the reasoning for the reviewing engineer.

In the UK there is no statutory stamp for electrical design drawings. A chartered engineer or other competent person reviews the design and signs it under their own responsibility. For a legal reading of a specific case, take advice from a qualified adviser. The technical rules that designers use to show the duty is met are in BS 7671, including protection against electric shock.

How Tiza can help

Your project may have to show that the equipment copes with the foreseeable fault and that isolation and protection are sound. Tiza prepares the engineering design and studies remotely and in English: fault-level calculations, device ratings and the protection logic. Tiza does not stamp, sign or certify designs in the UK; we deliver engineering ready for your chartered engineer to review and sign. Contact us with the single-line diagram and the equipment ratings.

Frequently asked questions

Who is a duty holder under the Electricity at Work Regulations?

Regulation 3 puts duties on employers and self-employed people for matters within their control, and on employees at work, who must cooperate with their employer and comply as far as matters are within their control. Control, not ownership, decides who the duty holder is.

When may someone work on live conductors?

Regulation 14 bars work on or near live conductors where danger may arise, unless three conditions all apply: making them dead is unreasonable in the circumstances, it is reasonable for the person to work live, and suitable precautions are taken, including protective equipment where necessary.

Does following BS 7671 satisfy the regulations?

It is a recognised way to show that the duty on installation design and construction is met, but the regulations are wider. They also cover how systems are maintained and how work is done. Compliance with the regulations is judged on the facts of each case.