Tiza Group

Home / Guides / Codes and grid connection: US, UK, CA, AU

ENA EREC G99 Explained: Connecting Generation in GB

What ENA EREC G99 requires for generation above 16 A per phase in Great Britain: scope, Types A to D, protection, compliance forms and a worked example.

By Shadai García, CEO and protection engineer at Tiza Group.

DNO networkinterfacebreakerVT27 / 59 / 81interface protection=~power generating modulePowerMeasure / control90 kW at 400 V: 90,000 / (1.732 x 400) = 129.9 Aabove 16 A: G98 does not apply, Type A1.2 MW (5 x 240 kW): Type B12 MW (6 x 2 MW): Type C55 MW: Type D, embedded medium power stationABCD0.8 kW1 MW10 MW50 MWlog scale90 kW1.2 MW12 MW55 MWillustrative projects; the limits are the same across Great BritainProcessApplyDNO assessmentBuildCommissionNotify© tizagrp.comDNO networkinterfacebreakerVT27 / 59 / 81interface protection=~power generating modulePowerMeasure / control90 kW at 400 V: 90,000 / (1.732 x 400) = 129.9 Aabove 16 A: G98 does not apply, Type A1.2 MW (5 x 240 kW): Type B12 MW (6 x 2 MW): Type C55 MW: Type D, embedded medium power stationABCD0.8 kW1 MW10 MW50 MWlog scale90 kW1.2 MW12 MW55 MWillustrative projects; the limits are the same across Great BritainProcessApplyDNO assessmentBuildCommissionNotify© tizagrp.com
ENA EREC G99 overview: a generating module connected to the distribution network through an interface breaker tripped by the 27, 59 and 81 interface protection fed by a VT, and the registered capacity scale with Type A below 1 MW, Type B to 10 MW, Type C to 50 MW and Type D from 50 MW with four example projects of 90 kW, 1.2 MW, 12 MW and 55 MW. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

ENA Engineering Recommendation G99 is the technical and procedural rulebook that a distribution network operator (DNO) applies to generation connected in parallel with its network in Great Britain, above the 16 A per phase limit of G98. It sorts every generating module into Type A, B, C or D by registered capacity and connection voltage, sets protection and grid-support requirements for each, and defines the forms and notifications that end in permission to operate. Issue 2 was published on 10 March 2025; storage requirements in it apply from 1 March 2026.

Short answer: what ENA EREC G99 is

ENA EREC G99 is the document a Great Britain network operator uses to decide whether your generator may connect. It also says what the generator must do once connected and what evidence the operator needs. It covers any source of electrical energy, including solar, wind, engines, hydro and batteries that can export. It applies when the installation is above the micro-generation limit of 16 A per phase handled by G98, or is not suitable for G98 type testing.

The text discussed here is ENA Engineering Recommendation G99 Issue 2, published 10 March 2025 by the Energy Networks Association (ENA). The ENA makes it openly available. Clause numbers below refer to that issue.

If you are still deciding between the UK documents, start with the UK electrical codes and grid connection guide. This guide goes one level deeper into G99 itself.

What G99 covers

Section 2 of G99 gives the scope. It applies to Type A, B, C and D power generating modules connected to the networks of licensed DNOs in Great Britain. A power generating module is either a synchronous machine set or a power park module, which is a group of inverter-connected or asynchronous units that act as one plant.

Three groups sit outside it:

  • Generators connected before 27 April 2019 follow the older EREC G59.
  • Generators that had a binding purchase contract for the main plant before 17 May 2018 also follow G59, if they notified the DNO in time.
  • Generators with a relevant derogation from the regulator follow that derogation.

Northern Ireland has its own G99/NI and is a separate regime.

How G99 is organised

The document is long, but its structure is simple. Learn the map and you can find any answer in minutes.

Part of G99What it holds
Sections 4 to 6Definitions, legal aspects, the connection application
Sections 7 and 8Operating modes, phase balance, earthing
Section 9Network connection design, voltage steps, power quality, islanding
Section 10Interface protection, loss of mains, settings table
Sections 11 to 13Technical requirements for Type A, Type B, and Types C and D
Sections 14 and 15Installation, labelling, and the common commissioning checks
Sections 16 to 19Compliance, commissioning and operational notification, one section per type
Annexes A to CThe forms, type-test requirements and simulation study rules

The sibling guides in this series take one topic each: Types A to D, protection for Types A and B, loss of mains protection, fault ride through and frequency response, reactive power and voltage control, compliance and commissioning and equipment certificates.

The four types in one table

G99 sorts modules by registered capacity and connection voltage (section 4.1). These limits are the same across Great Britain.

TypeRegistered capacityConnection point
A0.8 kW or more, below 1 MWBelow 110 kV
B1 MW or more, below 10 MWBelow 110 kV
C10 MW or more, below 50 MWBelow 110 kV
D50 MW or moreAny, or 110 kV and above

A different set of thresholds does vary by region: the Grid Code definition of a large power station (section 2). It is 10 MW in the north of Scotland, 30 MW in the south of Scotland and 100 MW in England and Wales. A facility that reaches it must also meet the relevant parts of the Grid Code. In England and Wales, a facility of 50 MW or more is an embedded medium power station, with its own requirements in sections 6.4.4 and 13.8.

What changed in Issue 2

The amendment record at the front of the document lists dozens of changes. The ones most designers notice:

  • New mandatory requirements for modules that include electricity storage, in force from 1 March 2026. Storage that is importing must respond to falling frequency (clause 11.2.3.3).
  • Clearer wording on type-tested interface protection (clause 10.1.4).
  • A rate of change of frequency (RoCoF) withstand test added to the type-test and commissioning forms.
  • Simplified simulation studies for Type B modules, with the DNO still able to ask for more.
  • Clarified connection process for Type B, C and D modules.

Storage commissioned before 1 September 2022 is treated under Annex A.4.2.

The path from idea to permission to operate

  1. Discuss the project with the DNO early. Small installations up to 32 A per phase can use the Small Generation Installation procedures (clause 6.2.2).
  2. Apply on the DNO’s form. Type A below 50 kW three-phase (17 kW single-phase) uses Form A1-1. Larger modules use the DNO’s standard application form.
  3. The DNO assesses the network impact, which can lead to studies and network works.
  4. Build, then commission. Type A needs the installation checks of clause 15.3. Type B and above need a Power Generating Module Document with studies and a test schedule.
  5. Notify the DNO. Type A completes an Installation Document. Types B and C receive a Final Operational Notification. Type D has staged notifications.

You have no permanent right to operate until the DNO has the paperwork it needs (clauses 6.2.4.4 and 16.4.3).

Worked example: four illustrative projects

All figures are illustrative. Supply is 400 V three-phase.

  1. 90 kW rooftop solar: 3 inverters of 30 kW. Current per phase is 90,000 ÷ (1.732 × 400) = 129.9 A, far above 16 A, so G98 does not apply. At 90 kW it is a Type A power park module. It is above 50 kW, so the application is on the DNO’s standard form rather than Form A1-1.
  2. 1.2 MW solar plant: 5 inverters of 240 kW at 11 kV. 5 × 240 = 1,200 kW = 1.2 MW, so Type B.
  3. 12 MW plant at 33 kV: 6 units of 2 MW. 6 × 2 = 12 MW, so Type C. In the north of Scotland 12 MW is above the 10 MW Grid Code threshold, so Grid Code provisions apply as well. In England, Wales and the south of Scotland it does not.
  4. 55 MW plant at 33 kV in England: 55 MW is Type D and an embedded medium power station. Interface protection of the rate-of-change type is not installed at sites of 50 MW or more (clause 10.6.2), and the DNO decides on any loss of mains protection.

Checklist for the engineer

  • Confirm with the DNO which issue of G99 applies and obtain its generation connection requirements in writing.
  • Calculate registered capacity and classify each module as Type A, B, C or D.
  • Check the Grid Code large-station threshold for the project’s region.
  • List the equipment that is type tested and registered with the ENA, and what needs site testing.
  • Agree interface protection settings with the DNO before ordering relays.
  • Prepare the forms for your type: Form A1-1, A2 and A3 for Type A; the Power Generating Module Document and Forms B2 and B3 for Type B.
  • Plan commissioning dates around the notice periods the DNO requires.
  • Keep every submission, setting record and test result for the compliance file.

From the recommendation to a design your chartered engineer can sign off

A G99 application moves faster when the design package matches what the DNO asks for. We prepare the engineering design and the power-system studies behind it: single-line diagram, protection and settings approach, fault level and load-flow inputs, and the equipment data. The package is ready for your chartered engineer (CEng) or the responsible designer to review and sign. Tiza does not stamp, sign or certify designs in the UK. Contact us with the site data and the DNO’s requirements.

Related technical background: interconnection relays, ROCOF 81R protection, 81 frequency trip with on-site generation and commissioning tests for solar plants.

Frequently asked questions

What is ENA EREC G99?

It is the Energy Networks Association engineering recommendation that sets the requirements for connecting generation, including batteries that export, to licensed distribution networks in Great Britain. It covers technical performance, protection, and the compliance process. It applies when the installation is not covered by G98.

Which issue of G99 is current?

Issue 2, published on 10 March 2025. Its new mandatory requirements for modules that include electricity storage apply from 1 March 2026. The rest applies from the publication date. Always confirm with the DNO which issue it applies to your application.

Does G99 replace G59?

For generation first installed on or after 27 April 2019, yes. G59 still applies to modules connected before that date, and to some projects that had a binding equipment purchase contract before 17 May 2018. The foreword and section 2 of G99 list the exceptions.

WhatsApp