G99 Issue 2 sets a different compliance route per type. Type A applies on Form A1 or the DNO's standard form, supplies compliance reports (Forms A2) and, after commissioning, an Installation Document (Form A3) within 28 days if the DNO did not witness the tests. Type B sends a Power Generating Module Document at least 28 days before first synchronisation, commissions under Form B3 and B2-2, and receives a Final Operational Notification. Until the paperwork is done there is no permanent right to operate.
Short answer: the G99 compliance process
The G99 compliance process has the same backbone for every type: apply, get the DNO’s approval, build, commission with the required tests, and notify the DNO with the forms. What changes with the type is the evidence. A Type A module with a fully type-tested inverter needs installation checks and one document. A Type B module needs studies, a test schedule and a Final Operational Notification from the distribution network operator (DNO). The source is ENA Engineering Recommendation G99 Issue 2, 10 March 2025, sections 6, 15, 16 and 17, which the Energy Networks Association makes openly available.
For the document as a whole see the G99 overview. For the evidence behind the forms see statements of compliance and equipment certificates. The wider UK frame is in the UK electrical codes and grid connection guide.
Step 1: the application
Discuss the project with the DNO at the earliest opportunity (clauses 16.2.1 and 17.2.1). Connection is allowed only after the DNO has approved the application and finished any network works.
- Type A below 50 kW three-phase (17 kW single-phase): Form A1-1.
- Small generation installations: Form A1-2, which covers procedures up to 32 A per phase (clause 6.2.2).
- Type A above 50 kW: the DNO’s standard application form.
- Type B, C and D: the standard application form, which also carries planning data, and system studies will almost certainly be needed (clause 6.2.4.1).
If the module is fully type tested and registered with the ENA Type Test Register, the application quotes the manufacturer’s reference (the system reference). The compliance test results then need not be sent with it.
Step 2: what the DNO assesses
On receipt, the DNO looks at whether studies are needed, whether network works must precede the connection, and whether it wants to witness commissioning (clause 16.2.2). For Type A at LV with fully type-tested equipment, the DNO does not normally witness. It may do so, for example, for a new installer in its area, or on a random quality check (clause 16.3.1).
Step 3: Type A, from compliance report to Installation Document
- If the module is not fully type tested, send the Compliance Verification Report (Form A2-1, A2-2 or A2-3) before commissioning starts (clause 16.2.4).
- Do the installation checks and tests of clause 15.3 at every installation, type tested or not. They include inspection against BS 7671, lockable isolation, safety labels, interlocking, a visual check of protection settings, synchronisation and disconnection tests, and a loss-of-supply test of the interface protection.
- If the DNO will witness, send the scope, date and time of the tests at least 15 days before (clause 16.3.2).
- Complete the Installation Document: Form A3-1 for Type A, Form A3-2 for small generation installations. If tests were not witnessed, send it within 28 days of commissioning. If witnessed, give a copy at the time.
- Where the plant is not fully type tested, Form A2-4 covers site compliance and commissioning tests.
The generator has no permanent right to operate until the tests are done and the Installation Document is complete and sent (clause 16.4.3).
Step 4: Type B, from module document to Final Operational Notification
- At least 28 days before first synchronisation, send the Power Generating Module Document (Form B2-1). The DNO can agree a shorter period, and must not unreasonably withhold approval of the test start date (clauses 17.2.2 and 17.2.5).
- The document includes updated planning data, special protection details and a schedule of tests (clause 17.2.3). It also holds simulation studies per Annex B.4 for frequency capability, fault ride through, reactive capability and fast fault current injection, plus any manufacturer’s information relied upon.
- The generator makes arrangements for the DNO to witness commissioning, and carries the responsibility for safety during the tests (clause 17.3.1). Results go on Form B3 (installation and commissioning) and Form B2-2 where applicable, with the declaration signed and dated.
- The DNO and the generator may agree an interim operating regime, with an Interim Operational Notification, while tests continue (clause 17.3.6).
- For the Final Operational Notification, send updated planning data, evidence that the simulation models represent the plant, test results, and the compliance declaration signed by the generator (clause 17.4.1). Synchronous modules normally submit within 28 days of first synchronisation. For power park modules, compliance testing is expected to take no more than six months, though a longer period may be agreed (clause 17.4.2).
Type B owners have no permanent right to operate without a valid Final Operational Notification (clause 6.2.4.4). Types C and D follow longer routes in sections 18 and 19, and Type D has an energisation notification, an interim one, and a final one.
What happens on commissioning day
The common checks and tests in clause 15.3 apply to every facility. Non-type-tested interface protection needs more: voltage and frequency pick-up and timing tests, and the vector shift and RoCoF stability tests, without trip (clause 15.4). See loss of mains under G99 for what those tests apply. Settings can only change later by written agreement with the DNO.
Worked example: a dated timeline
Illustrative dates. The first synchronisation of a Type B power park module is planned for 15 March 2027.
- Module Document due at least 28 days before: 15 March - 28 days = 15 February 2027.
- A separate Type A module on the site is commissioned on 16 March with the DNO witnessing. The scope, date and time go to the DNO at least 15 days before: 16 March - 15 days = 1 March 2027.
- If instead a Type A module is commissioned unwitnessed on 15 March, the Installation Document is due within 28 days: 12 April 2027.
- The final submission for the power park module is expected within six months of first synchronisation: 15 September 2027.
The dates are working targets. The DNO’s offer can set other dates, and a shorter notice may be agreed.
Checklist for the engineer
- Confirm the type and the application form with the DNO.
- Collect the ENA Type Test Register references for each unit.
- Prepare the Module Document, studies and test schedule for Type B.
- Plan commissioning dates around the 28-day and 15-day periods.
- Complete the clause 15.3 installation checks and the protection test results.
- Agree who witnesses and who is charged for attendance.
- Complete the declarations on Forms A3 or B3 and the compliance declaration.
- Keep the whole record: application, settings, tests, notifications and dates.
From the process to a package your engineer can review
A G99 connection can stall on missing evidence even when the technology is sound. We prepare the engineering design and the studies that feed the module document. The package is ready for your chartered engineer (CEng) or the responsible designer to review and sign. Tiza does not stamp, sign or certify designs in the UK. Contact us with the DNO’s requirements and the design status.
Related guides: commissioning tests for solar plants, protective relay commissioning, BESS commissioning and interconnection relays.
Frequently asked questions
Which G99 forms does a Type A generator need?
An application on Form A1-1 below 50 kW three-phase or 17 kW single-phase, Form A1-2 for small generation installations, or the DNO's standard form above that. Then compliance reports in Forms A2-1 to A2-3 if the equipment is not fully type tested, and the Installation Document in Form A3-1 or A3-2 after commissioning.
How long do I have to send the installation document?
If the DNO did not witness the commissioning, within 28 days of the commissioning date. If it did witness, a copy goes to the DNO at the time of commissioning. Without the completed document the generator has no permanent right to operate.
What does a Type B project submit before first synchronisation?
A Power Generating Module Document, Form B2-1, not less than 28 days before first synchronisation, with updated planning data, special protection details, simulation studies, and a schedule of the tests to be done for the Final Operational Notification. The DNO can accept a shorter period.