G99 Fault Ride Through and Frequency Response (LFSM-O)

G99 Issue 2 fault ride through for Type B, frequency withstand ranges and LFSM-O over-frequency response, with section references and a worked example.

By Shadai García, CEO and protection engineer at Tiza Group.

11 kV networkinterfacebreakerVT81 / 27interface relayCTplant controllerLFSM-O=~2 MW power park modulePowerMeasure / controlfrequency bands: stay connectedRoCoF withstand: 1 Hz/s over 500 ms140 ms fault: 0.1 pu = 1.1 kV at 11 kVpre-fault 1.2 MW: back to 1.08 MW within 0.5 sLFSM-O at 50.7 Hz: 3 x 2 % = 6 % = 120 kWat 50.9 Hz: 10 % = 200 kW; half within 10 s20 s90 mincontinuous90 min15 min47.049.051.052.0Hzinterface trips: 47.5 Hz 20 s, 47.0 Hz 0.5 s, 52.0 Hz 0.5 sput (s)012.20.10.851.0140 ms0.85 pu at 2.2 spre-fault 1.0 pukWHz50.050.450.750.92,0001,8801,800start 50.4 Hz, 2 % per 0.1 Hzillustrative: 2 MW module at full outputRide-throughFrequency bandsRoCoF 1 Hz/s140 ms faultRecoveryLFSM-O© tizagrp.com11 kV networkinterfacebreakerVT81 / 27interface relayCTplant controllerLFSM-O=~2 MW power park modulePowerMeasure / controlfrequency bands: stay connectedRoCoF withstand: 1 Hz/s over 500 ms140 ms fault: 0.1 pu = 1.1 kV at 11 kVpre-fault 1.2 MW: back to 1.08 MW within 0.5 sLFSM-O at 50.7 Hz: 3 x 2 % = 6 % = 120 kWat 50.9 Hz: 10 % = 200 kW; half within 10 s20 s90 mincontinuous90 min15 min47.049.051.052.0Hzinterface trips: 47.5 Hz 20 s, 47.0 Hz 0.5 s, 52.0 Hz 0.5 sput (s)012.20.10.851.0140 ms0.85 pu at 2.2 spre-fault 1.0 pukWHz50.050.450.750.92,0001,8801,800start 50.4 Hz, 2 % per 0.1 Hzillustrative: 2 MW module at full outputRide-throughFrequency bandsRoCoF 1 Hz/s140 ms faultRecoveryLFSM-O© tizagrp.com
G99 fault ride through and frequency response: a 2 MW power park module at 11 kV with its interface breaker, CT and VT, the 81 and 27 interface relay that does not trip, and the plant controller that reduces output above 50.4 Hz, with the frequency bands, the 140 ms voltage envelope at 0.1 pu rising to 0.85 pu at 2.2 s and the LFSM-O curve with 1,880 kW at 50.7 Hz and 1,800 kW at 50.9 Hz. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

G99 Issue 2 asks every module to stay connected through set frequency bands, to withstand a rate of change of frequency of 1 Hz/s over 500 ms, and to reduce output when frequency rises above 50.4 Hz (LFSM-O, with a 10% droop). Type B modules must also ride through transmission faults of up to 140 ms under a voltage-against-time curve and, for power park modules, inject reactive current. Type A modules have no fault ride through duty unless the DNO agrees one for network security.

Short answer: G99 fault ride through and frequency response

Under ENA Engineering Recommendation G99 Issue 2 (10 March 2025), a Type B module must stay connected and stable through balanced and unbalanced faults lasting up to 140 ms. The voltage-against-time curve is in clause 12.3. Every module must also stay connected across the frequency bands in clauses 11.2.1 and 12.2.1. It must withstand a rate of change of frequency of 1 Hz/s measured over 500 ms. It must reduce active power when frequency rises above 50.4 Hz (limited frequency sensitive mode over-frequency, LFSM-O). The Energy Networks Association makes G99 openly available.

For the document as a whole see the G99 overview. The type limits are in the guide to Types A to D, and the wider UK frame is in the UK electrical codes and grid connection guide.

Frequency ranges: how long you must stay connected

Clauses 11.2.1 (Type A) and 12.2.1 (Type B) set the same bands. The module must keep operating in parallel with the network for at least:

Frequency bandMinimum time
47.0 to 47.5 Hz20 s each time
47.5 to 49.0 Hz90 minutes each time
49.0 to 51.0 HzContinuous
51.0 to 51.5 Hz90 minutes each time
51.5 to 52.0 Hz15 minutes each time

The interface protection settings sit inside these bands: under frequency trips at 47.5 Hz after 20 s and at 47.0 Hz after 0.5 s, and over frequency at 52 Hz after 0.5 s.

Two further requirements apply. The module keeps its active power constant between 49.5 and 50.5 Hz. Below 49.5 Hz, output may fall along a linear characteristic, but no more than 5% in total at 47 Hz (clause 11.2.3.1). Electricity storage that is importing has its own response to falling frequency in clause 11.2.3.3, in force from 1 March 2026.

RoCoF withstand

A module must stay connected through rates of change of frequency up to 1 Hz/s, measured over 500 ms (clauses 11.2.2 and 12.2.2). The exception is when a RoCoF-type loss of mains relay trips it, or when the module’s own protection trips for an internal fault. The new Issue 2 forms add a RoCoF withstand test to the type-test and commissioning forms.

LFSM-O: reducing power when frequency is high

Each module must be able to reduce active power when frequency rises above 50.4 Hz (clause 11.2.4, repeated for Type B). The main points:

  • The response is at least 2% of output per 0.1 Hz above 50.4 Hz, which is a 10% droop. A steeper droop is allowed, but not below 2%.
  • The response must start as fast as possible. A delay above 2 s needs technical evidence for the DNO.
  • Up to 50.9 Hz, at least half of the proportional reduction must be achieved within 10 s.
  • Beyond 50.9 Hz, output must fall faster than 0.5% of the initial output per second.
  • When frequency falls again, the response reduces. The module continues the response until frequency is at or below 50.4 Hz.
  • At minimum stable operating level, the module keeps operating stably there.

If a module has a contract to operate in frequency sensitive mode, the LFSM-O response applies above 50.5 Hz instead.

Fault ride through for Type B

Clause 12.3 applies to faults on the network of up to 140 ms. The module must stay connected and stable for balanced and unbalanced faults. This holds while the connection point voltage stays on or above the heavy curve in Figure 12.5 (synchronous) or Figure 12.6 (power park modules). The curve parameters are in Tables 12.1 and 12.2. For power park modules, the retained voltage during the fault is 0.1 pu for 140 ms, and the curve rises back to 0.85 pu at 2.2 s.

Other conditions in clause 12.3.1.7:

  • The pre-fault voltage is 1.0 pu and the post-fault voltage is at least 0.9 pu.
  • The module must meet the requirement at registered capacity and maximum leading power factor.
  • For faults of 140 ms or less, active power must return to at least 90% of its pre-fault level. The time limit is 0.5 s after voltage recovers to 90% of nominal.
  • Power oscillations after recovery must be damped and deliver at least the energy a constant output would.
  • Switched capacitors or reactors in a power park module must not switch during the fault.

Clause 12.3.4 lists exceptions. The requirements do not apply when a power park module runs below 5% of registered capacity. They also do not apply when an emergency sequence has shut down more than half its units.

Fast fault current injection (clause 12.6) applies to power park modules for transmission faults cleared within 140 ms. If voltage at the connection point falls below 0.9 pu, the module must inject reactive current above the locus in Figure 12.7. Reactive current has priority over active current.

The DNO publishes fault level data in its long-term development statements, and provides generic values on request, so that the generator can model ride-through performance (clause 12.3.1.7). Type B simulation studies were simplified in Issue 2, although the DNO can still ask for more (clause 17.2.3).

Type A has no equivalent duty. Clause 11.3 applies only where the DNO and the generator have agreed that the facility supports network security, for example for compliance with EREC P2.

Worked example: a 2 MW Type B plant

Illustrative data. A 2 MW power park module connects at 11 kV and is at full output.

  1. LFSM-O at 50.7 Hz. Deviation above 50.4 Hz is 0.3 Hz. At 2% per 0.1 Hz the minimum reduction is 3 × 2% = 6%. That is 2,000 kW × 0.06 = 120 kW, so output falls to 1,880 kW.
  2. LFSM-O at 50.9 Hz. Deviation is 0.5 Hz, giving 5 × 2% = 10%, or 200 kW; output falls to 1,800 kW. At least half of the 10% reduction, which is 100 kW, must be in place within 10 s of frequency passing 50.4 Hz.
  3. Fault ride through. At 11 kV a retained voltage of 0.1 pu is 1.1 kV during the 140 ms fault.
  4. Power recovery. If pre-fault output was 1.2 MW, the module must be back at 90% × 1.2 MW = 1.08 MW. The time limit is 0.5 s after voltage reaches 90% of nominal.

Checklist for the engineer

  • Confirm the type and whether the DNO has agreed any fault ride through duty for Type A.
  • Obtain fault level data from the DNO for the study.
  • Check inverter or generator data against the voltage-against-time curve in Tables 12.1 and 12.2.
  • Verify the LFSM-O droop and response times, and the 50.4 Hz start point.
  • Check protection settings do not trip the module inside the frequency bands and ride-through curve.
  • Check that RoCoF-type relays and withstand requirements are coordinated.
  • Prepare simulation models and results for the Power Generating Module Document.
  • Keep the type-test evidence and test records for the compliance file.

From the requirement to studies your engineer can review

Ride-through and frequency response are shown with dynamic studies and model data, and they feed the module document the DNO assesses. We prepare power-system studies and the engineering design behind them. The package is ready for your chartered engineer (CEng) or the responsible designer to review and sign. Tiza does not stamp, sign or certify designs in the UK. Contact us with the plant data and the DNO’s fault level information.

Related guides: 81 frequency trip with on-site generation, ROCOF 81R protection, interconnection relays and loss of mains protection under G99.

Frequently asked questions

What fault ride through does G99 require for a Type B module?

The module must stay connected and stable for balanced and unbalanced faults of up to 140 ms where the connection point voltage stays above the curve in clause 12.3. Power output must return to at least 90% of its pre-fault level within 0.5 s of voltage recovering to 90%. Power park modules also inject reactive current.

What is LFSM-O in G99?

Limited frequency sensitive mode over-frequency. Above 50.4 Hz the module reduces active power with a droop of at least 2% per 0.1 Hz of deviation, which is a 10% droop. The response must continue until frequency is back at or below 50.4 Hz.

Does a Type A module have to ride through faults?

Not by default. Clause 11.3 applies only where the DNO and the generator have specifically agreed that the facility contributes to network security, for example for compliance with the security of supply standard EREC P2.