G99 Equipment Certificates and Compliance Statements

What G99 evidence a DNO expects: type-test reports and ENA registration, Forms A2, family approach, manufacturer's information and declarations by type.

By Shadai García, CEO and protection engineer at Tiza Group.

Manufacturer type tests the unitreport Form A2-1, A2-2 or A2-3ENA Type Test Registersystem reference (cl. 16.1.2)Application quotes the reference;results not attached (cl. 16.2.1)Installed model, firmware,settings = registered?yesType-tested route:installation checks onlynoSite tests,studies, formslimit: 2 x 100 kW = 200 kWfrequency range result carries over unchangedharmonic current scales: 3.0 x 150 / 100 = 4.5 Aplant: 8 x 150 kW = 1,200 kW = 1.2 MW, Type B100 kW: type tested150 kW: joins the family200 kW: joins, at the limit250 kW: outside the family200 kWharmonic current: 3.0 A at 100 kW4.5 A at 150 kWillustrative family of invertersEvidenceType testRegisterSystem referenceApplicationSite check© tizagrp.comManufacturer type tests the unitreport Form A2-1, A2-2 or A2-3ENA Type Test Registersystem reference (cl. 16.1.2)Application quotes the reference;results not attached (cl. 16.2.1)Installed model, firmware,settings = registered?yesType-tested route:installation checks onlynoSite tests,studies, formslimit: 2 x 100 kW = 200 kWfrequency range result carries over unchangedharmonic current scales: 3.0 x 150 / 100 = 4.5 Aplant: 8 x 150 kW = 1,200 kW = 1.2 MW, Type B100 kW: type tested150 kW: joins the family200 kW: joins, at the limit250 kW: outside the family200 kWharmonic current: 3.0 A at 100 kW4.5 A at 150 kWillustrative family of invertersEvidenceType testRegisterSystem referenceApplicationSite check© tizagrp.com
G99 statements of compliance: the type test report, ENA Type Test Register and system reference route with the check that the installed model, firmware and settings match the registered ones, and a family of inverters tested at 100 kW with a limit of 200 kW, 150 and 200 kW units joining, 250 kW outside, and a harmonic current scaled from 3.0 A to 4.5 A. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

G99 Issue 2 lets a generator prove compliance with manufacturer evidence plus site checks. The manufacturer submits a Type Test Verification Report on Form A2-1, A2-2 or A2-3 and registers a system reference on the ENA Type Test Register. A fully type-tested module then needs installation checks only. Type B and above also submit a Power Generating Module Document with a statement of compliance, and the generator signs a compliance declaration. Evidence must match the model, firmware and settings installed on site.

Short answer: G99 equipment certificates and statements of compliance

G99 does not use a single “certificate”. The evidence is a Type Test Verification Report made by the manufacturer on Form A2-1, A2-2 or A2-3. It is registered under a system reference on the Energy Networks Association (ENA) Type Test Register (clauses 16.1.2 and 16.1.3). A module that meets G99 in this way is considered approved for connection to the network (clause 16.1.5). For Type B and above, the generator also submits a Power Generating Module Document that contains a statement of compliance, and signs a compliance declaration. The source is ENA Engineering Recommendation G99 Issue 2, 10 March 2025, made openly available by the ENA.

For the document as a whole see the G99 overview. The process around the forms is in compliance and commissioning, and the wider frame is in the UK electrical codes and grid connection guide.

Fully type tested versus type tested

G99 separates two levels (clause 16.1.1 and the matrix in section 22.1).

  • Fully type tested: the complete module, inverter and interface protection included, has a registered compliance report. Connection is simpler, the protection arrangements are fixed, and commissioning is reduced to installation checks. For Type A, an assessment against EREC G5 (harmonics) and EREC P28 (voltage fluctuations) is still needed. It generally allows connection without mitigation, except where fault level is unusually low.
  • Type tested: parts of the module, such as the inverter or the relay, have registered reports. The remaining requirements are shown by the generator with site tests, studies and the extra forms.

For Type B, C and D, the matrix lists three situations: type-tested equipment, a one-off installation, and combinations. In every one the module document (Form B2-1 or C2-1) covers what type testing does not. Installation checks go on Form B3 or C3. Additional site compliance checks (Form B2-2 or C2-2) may be required.

Which form for which equipment

EquipmentCompliance Verification Report
Synchronous unit up to and including 50 kWForm A2-1
Synchronous unit above 50 kW; induction unitsForm A2-2
Inverter-connected and other asynchronous units, any sizeForm A2-3
Site compliance and commissioning testsForm A2-4 (Type A), Form B2-2, Form C2-2

Form A2-3 does not cover conventional induction generating units (clause 16.1.3). Annex A.7 guides manufacturers on the tests behind each report.

The system reference

The manufacturer submits the report to the ENA Type Test Register and allocates a reference number that is registered as the system reference (clause 16.1.2). Applicants quote it in the application, and the compliance results need not be attached (clause 16.2.1).

Three practical points follow from the wording:

  • The report details the type and model tested, the test conditions and the results.
  • Interface protection settings in a type-tested relay are set at the factory (clause 10.1.4), so the evidence only holds if the installed firmware and settings match the registered ones.
  • Where components are wired together on site, a wiring schedule and function tests are needed to keep type-tested status (clause 15.2).

The family approach

Clause 15.6 lets a manufacturer cover a range of units with one test. Units of the same model and design that differ in electrical output can be treated as type tested once one unit in the family has been shown to comply. For non-synchronous units, the upper limit is twice the tested nameplate rating (clause 15.6.1 also sets a lower limit).

Results transfer in two ways (clause 15.6.2). Absolute values, such as operating range tests, carry over directly. Relative results tied to design power or current, such as flicker, scale by the ratio of nameplate ratings. The manufacturer must register each unit of the family and justify, for example by showing the same control systems, that results transfer (clause 15.6.3).

Manufacturer’s information and simulation models

Section 21 of G99 covers information a manufacturer gives about its generating units, such as fault ride through capability and the mathematical model of a power park module. A generator that relies on it quotes the reference in the forms. Quoting a reference does not by itself show compliance (clause 21.3). The generator remains responsible for the accuracy of the reference it uses (clause 21.5). It must also make sure the manufacturer has told the DNO about any variation in plant specification. The DNO can contact the manufacturer directly and can declare a reference invalid.

Statements and declarations by type

  • Type A: the declaration at the bottom of the Installation Document (Form A3-1 or A3-2), completed by the installer or the generator. It also covers Form A2-4 where used (clause 16.2.6).
  • Type B and C: the declaration on Form B3 or C3, signed and dated, plus the Power Generating Module Document. For the Final Operational Notification, the generator signs the compliance declaration (clause 17.4.1).
  • All types: the simulation models used to show compliance must be validated before the final submission (clause 6.3.8.1).

Each declaration is the generator’s or installer’s statement. Tiza does not sign or certify these documents.

Worked example: a family of inverters

Illustrative data. A manufacturer type tests a 100 kW inverter and registers a family with the same design and control.

  1. Upper limit. Twice the tested rating: 2 × 100 kW = 200 kW. A 150 kW unit and a 200 kW unit can join the family. A 250 kW unit cannot.
  2. Absolute result. The operating frequency range test result carries over unchanged to the 150 kW unit.
  3. Relative result. A harmonic current measured as 3.0 A on the tested unit scales by the nameplate ratio: 3.0 × 150 ÷ 100 = 4.5 A for the 150 kW unit.
  4. Plant evidence. A Type B plant of 8 × 150 kW has 8 × 150 = 1,200 kW = 1.2 MW. It quotes the system references of the registered units. For what type testing does not cover, it supplies the Module Document, studies and site tests.

Checklist for the engineer

  • Identify the exact model, firmware and rating of every inverter, generator and relay.
  • Check each against the ENA Type Test Register and note the system reference.
  • Confirm the report form fits the technology (A2-1, A2-2 or A2-3).
  • Check whether the family approach covers the rating you will install.
  • Confirm firmware and protection settings on site match the registered ones.
  • List the requirements type testing does not cover and plan the studies and site tests.
  • Collect manufacturer’s information references, and check they are current.
  • Prepare the installer and generator declarations and keep dated copies.

From the evidence list to a review your engineer can rely on

An application is only as complete as its evidence pack. We prepare the engineering design and the studies that complete the compliance documents. The package is ready for your chartered engineer (CEng) or the responsible designer to review and sign. Tiza does not stamp, sign or certify designs in the UK. Contact us with the equipment list and the DNO’s requirements.

Related guides: PV inverter standards, IEEE 519 with inverters, interconnection relays and commissioning tests for solar plants.

Frequently asked questions

Is there a G99 equipment certificate?

The evidence is a Type Test Verification Report on Form A2-1, A2-2 or A2-3, prepared by the manufacturer and registered on the Energy Networks Association Type Test Register under a system reference. G99 treats compliance as approval for connection, though the DNO still assesses the application.

Which form does an inverter use?

Form A2-3, which covers all inverter-connected and asynchronous technologies of any size, except conventional induction generating units. Synchronous units up to 50 kW use Form A2-1, and larger synchronous units, or induction units, use Form A2-2.

Can one test report cover a range of inverter sizes?

Yes, through the family approach in clause 15.6. Models from the same manufacturer with the same design but different ratings can be type tested once the tested unit complies, within a range up to twice the tested nameplate rating. The manufacturer registers each member of the family and justifies that results transfer.