G99 Issue 2 asks for interface protection that detects under voltage, over voltage in two stages, under frequency in two stages, over frequency and loss of mains. Table 10.1 gives the settings for Type A, B and C modules, with separate voltage values for low-voltage and high-voltage connections. Relays that are type tested leave the factory with fixed frequency and loss of mains settings, and any later change needs written agreement between the generator and the distribution network operator.
Short answer: the G99 protection settings for Type A and B
G99 asks for interface protection with five functions: under voltage (1 stage), over voltage (2 stages), under frequency (2 stages), over frequency (1 stage) and loss of mains (clause 10.3.1). The settings for Type A, B and C modules are in Table 10.1 of ENA Engineering Recommendation G99 Issue 2 (10 March 2025). They differ for low-voltage (LV) and high-voltage (HV) connections. The ENA makes the document openly available.
For the document as a whole see the G99 overview, and for the UK picture the UK electrical codes and grid connection guide. Loss of mains has its own guide: ROCOF and vector shift.
What the protection is for
The aim, in clause 10.1.1, is to stop the generating module from supporting an islanded part of the network where that could harm the network or other customers. The settings follow a two-stage idea: a long delay for small excursions that happen in normal operation, and a faster trip for larger ones. That avoids nuisance trips while still clearing real problems.
Generators install, own and maintain the protection (clause 10.1.2). The network operator can add its own protection after its connection study, such as neutral voltage displacement, over-current, earth fault or reverse power (clause 10.5). That is outside what the generator sets.
The settings table in plain terms
The values below come from Table 10.1 for Type A, B and C modules. Delays are the settings on the relay.
| Function | LV connection | HV connection |
|---|---|---|
| Under voltage | -20%, 2.5 s | -20%, 2.5 s |
| Over voltage stage 1 | +14%, 1.0 s | +10%, 1.0 s |
| Over voltage stage 2 | +19%, 0.5 s | +13%, 0.5 s |
| Under frequency stage 1 | 47.5 Hz, 20 s | 47.5 Hz, 20 s |
| Under frequency stage 2 | 47.0 Hz, 0.5 s | 47.0 Hz, 0.5 s |
| Over frequency | 52.0 Hz, 0.5 s | 52.0 Hz, 0.5 s |
| Loss of mains | RoCoF 1 Hz/s, 0.5 s | RoCoF 1 Hz/s, 0.5 s |
Points that matter in practice:
- Use the LV set when the protection takes its voltage reference from an LV source, and the HV set when it takes it from an HV source. For LV the percentages apply to 230 V.
- The table’s note says the 2.5 s under voltage delay might need to be reduced if auto-reclose times are shorter than 3 s (clause 10.2.1).
- Over voltage and under voltage must operate independently on all three phases (clause 10.6.8).
- Total operating time from detection to breaker opening is typically about 100 ms longer than the delay setting.
- The relay must measure voltage to within +/-1.5% and frequency to within +/-0.2% of nominal.
- Type D modules and facilities above 50 MW have their own column, where intertripping is expected for loss of mains.
Settings other than these need a valid justification and the DNO’s agreement, and the agreed values go in the connection agreement (clause 10.6.9).
Type-tested interface protection
A relay counts as type tested only under the conditions of clause 10.1.4 (new in Issue 2). Frequency and loss of mains settings are set in firmware at the factory to the table values and cannot be changed outside the factory. Voltage settings are factory-set too, but can be changed by agreement with the DNO by personnel the generator has instructed, behind a password, pin or sealable switch.
Once the plant is commissioned, settings change only after written agreement between the DNO and the generator (clause 10.1.5). Reconnection after a trip needs healthy voltage and frequency inside the interface protection ranges for at least 20 s (clause 10.3.4). For Type B, automatic reconnection systems need prior DNO authorisation (clause 10.3.3).
Worked example: settings for a 400 V and an 11 kV connection
Illustrative figures for a Type A plant at 400 V (230 V per phase) and a Type B plant at 11 kV.
LV connection, 230 V per phase:
- Under voltage: 230 × (1 - 0.20) = 184.0 V, 2.5 s.
- Over voltage stage 1: 230 × 1.14 = 262.2 V, 1.0 s.
- Over voltage stage 2: 230 × 1.19 = 273.7 V, 0.5 s.
- Total clearing time for stage 2 is about 0.5 s + 0.1 s = 0.6 s.
- Relay accuracy of +/-1.5% on 262.2 V is +/-3.9 V, so the measuring error is part of the margin; set the table value itself.
HV connection, 11 kV, relay fed from a 11,000 V / 110 V voltage transformer (ratio 100):
- Under voltage: 11,000 × 0.80 = 8,800 V, so 88.0 V on the secondary.
- Over voltage stage 1: 11,000 × 1.10 = 12,100 V, so 121.0 V secondary, 1.0 s.
- Over voltage stage 2: 11,000 × 1.13 = 12,430 V, so 124.3 V secondary, 0.5 s.
Whether the relay measures phase-to-phase or phase-to-neutral changes the base, so set it from the nominal that matches the connected quantity.
Checklist for the engineer
- Confirm with the DNO the G99 issue and whether its own requirements add to Table 10.1.
- Select the LV or HV settings set by where the voltage reference is taken.
- Check that the relay is registered as type tested, or plan the non-type-tested tests of clause 15.4.
- Record every setting in a settings schedule and send it for agreement.
- Check voltage and frequency accuracy, and the independent three-phase voltage elements.
- Provide a suitable place for the protection where settings and trip indicators are visible and secure (clause 10.3.2).
- Check the trip supply is monitored (clause 10.3.8).
- Test the 20 s reconnection delay and the auto-reclose coordination.
From the table to a settings plan your engineer can approve
The table is short, but turning it into a settings schedule that matches the relay, the voltage transformers and the DNO’s requirements takes care. We provide remote relay configuration, with the settings schedule based on the values your DNO approves. The package is ready for your chartered engineer (CEng) or the responsible designer to review and sign. Tiza does not stamp, sign or certify designs in the UK. Contact us with the relay model and the DNO’s requirements.
Related guides: interconnection relays, 81 frequency trip with on-site generation, 59 over voltage trip in solar plants and protection coordination step by step.
Frequently asked questions
What protection does G99 require at the connection of a Type A or Type B module?
Under voltage with one stage, over voltage with two stages, under frequency with two stages, over frequency with one stage, and loss of mains. Over and under voltage must work independently on all three phases. Table 10.1 of G99 Issue 2 gives the values.
Can I change the interface protection settings after commissioning?
Only with the written agreement of the DNO. The agreed settings are recorded in the connection agreement. Type-tested relays also keep their frequency and loss of mains settings fixed from the factory, so site changes there are not allowed.
Are the voltage settings the same for a low-voltage and a high-voltage connection?
No. They are expressed as percentages of nominal, and the percentages differ: for example, the first over voltage stage is +14% at low voltage and +10% at high voltage. The set to use depends on the voltage at which the protection takes its reference.