Tiza Group

Home / Guides / Codes and grid connection: US, UK, CA, AU

G99 Reactive Power Capability and Voltage Control

G99 Issue 2 reactive power capability by type: 0.95 power factor for Types A and B, 0.92 for C and D, control agreement with the DNO, and a sizing example.

By Shadai García, CEO and protection engineer at Tiza Group.

11 kV connection pointCTVTplant controllerPF 0.95 at theconnection point2.5 MVA6 %=~inverters2.4 MWPowerMeasure / controlQ = 2.4 x 0.3287 = 0.789 Mvar at 0.95S = 2.4 / 0.95 = 2.526 MVAtransformer loss: 1.021 x 0.15 = 0.153 Mvarinverters: 0.789 + 0.153 = 0.942 MvarS = 2.578 MVA, about 7 % above 2.4 MWType C, 12 MW at 0.92: Q = 5.11 MvarMvarMW120.7890.942leadingCPinvertersillustrative; cable and filter effects not includedReactiveCT and VTControllerSet pointInvertersCapability© tizagrp.com11 kV connection pointCTVTplant controllerPF 0.95 at theconnection point2.5 MVA6 %=~inverters2.4 MWPowerMeasure / controlQ = 2.4 x 0.3287 = 0.789 Mvar at 0.95S = 2.4 / 0.95 = 2.526 MVAtransformer loss: 1.021 x 0.15 = 0.153 Mvarinverters: 0.789 + 0.153 = 0.942 MvarS = 2.578 MVA, about 7 % above 2.4 MWType C, 12 MW at 0.92: Q = 5.11 MvarMvarMW120.7890.942leadingCPinvertersillustrative; cable and filter effects not includedReactiveCT and VTControllerSet pointInvertersCapability© tizagrp.com
G99 reactive power: a 2.4 MW power park module at 11 kV behind a 2.5 MVA 6 percent transformer with the CT and VT at the connection point feeding the plant controller that sets the inverters, and the P-Q plane with 0.789 Mvar at 0.95 at the connection point and 0.942 Mvar needed at the inverters, 2.578 MVA. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

G99 Issue 2 requires Type A and Type B modules to operate between 0.95 power factor lagging and 0.95 leading at registered capacity. Type C and D synchronous modules must reach 0.92, within 0.95 to 1.05 pu voltage, and power park modules have a lozenge or bow-tie envelope depending on connection voltage. In all types, the control scheme and set points are agreed with the distribution network operator and recorded in the connection agreement. Losses in the transformer and cables count toward the requirement.

Short answer: G99 reactive power capability and voltage control

Under ENA Engineering Recommendation G99 Issue 2 (10 March 2025), Type A and Type B modules must run anywhere between 0.95 power factor lagging and 0.95 leading. This applies while supplying registered capacity (clauses 11.1.5 and 12.5.1). Type C and D synchronous modules must reach 0.92 at the connection point, within 0.95 to 1.05 pu voltage (clause 13.5.1). In all cases, the voltage, power factor or reactive power control scheme and its set points are agreed with the distribution network operator (DNO) in the connection application. The Energy Networks Association makes G99 openly available.

The classification is in the guide to Types A to D. The document overview is in the G99 overview. The UK frame is in the UK electrical codes and grid connection guide.

Requirements by type

Annex D.4 of G99 gives a summary table, and the table below follows it.

TypeCapability at registered capacityVoltage range for the capabilityControl
A0.95 lagging to 0.95 leading (11.1.5)Nominal voltageTypically power factor control; scheme agreed bilaterally (11.1.6)
B0.95 lagging to 0.95 leading (12.5.1)Nominal voltageTypically power factor control; control point is the connection point unless agreed otherwise (12.4.3)
C and D, synchronous0.92 lagging to 0.92 leading (13.5.1)0.95 to 1.05 puAgreed bilaterally in the connection process (13.4.5)
C and D, power park module up to 33 kVLozenge envelope (13.5.5)As in the figureAgreed; voltage, reactive power or power factor control as required
C and D, power park module above 33 kVBow-tie envelope (13.5.4)As in the figureAgreed; voltage, reactive power or power factor control as required

For Type C and D synchronous modules, the module keeps its reactive output and power factor outside 0.95 to 1.05 pu as far as its performance chart permits (clause 13.5.3).

What the requirement means below full output

Type A and B requirements are stated at registered capacity. At lower output, synchronous modules and the units in a power park module must run anywhere inside the limits of their generator performance chart (clause 12.5.2). The chart must account for auxiliary supplies and the losses of the generator or station transformer, unless the DNO says otherwise.

An installation can contain both demand and generation. The DNO may then advise that the power factor be specified at the module terminals instead of the connection point (clause 12.5.3). Any specific requirement goes in the connection agreement.

Voltage control, in practice

The final responsibility for network voltage stays with the DNO (clauses 11.4.3 and 12.4.4). A generator must not harm the voltage profile or the DNO’s control scheme (clause 12.4.2). Four practical points follow:

  1. Synchronous units need a permanent automatic excitation system able to hold terminal voltage at a selectable set point over the whole operating range (clause 12.4.3.1).
  2. Set points for voltage, power factor or reactive power control are agreed during the application and recorded in the connection agreement. Changes need agreement too (clause 12.4.3.3).
  3. Network voltage control can be affected by export. Automatic voltage control schemes often assume power flows from high to low voltage. Reverse flows can confuse schemes using load current compounding or line drop compensation (clauses 12.4.5 and 12.4.6).
  4. Remote sites may need to withstand voltages outside the normal statutory limits. Immunity to changes of +/-10% of the declared voltage is recommended, subject to design appraisal (clause 12.4.1).

Worked example: sizing for 0.95 at the connection point

Illustrative data. A 2.4 MW power park module connects at 11 kV through a 2.5 MVA transformer with 6% reactance. The DNO has agreed a requirement of 0.95 at the connection point.

  1. Reactive power at 0.95: Q = P × tan(arccos 0.95) = 2.4 × 0.3287 = 0.789 Mvar.
  2. Apparent power at the connection point: S = 2.4 ÷ 0.95 = 2.526 MVA.
  3. Transformer reactive loss, treating it as purely reactive: Q_loss = (2.526 ÷ 2.5)² × 0.06 × 2.5 MVA = 1.021 × 0.15 = 0.153 Mvar.
  4. Reactive power the inverters must supply, on the LV side: 0.789 + 0.153 = 0.942 Mvar.
  5. Apparent power the inverters must be able to deliver: √(2.4² + 0.942²) = 2.578 MVA, about 7% above the 2.4 MW active rating.

If the requirement were met at the inverter terminals, the inverters would need 2.526 MVA, a difference of 0.052 MVA. Where the point of measurement sits matters, which is why clause 12.5.1 says “as agreed with the DNO”. The example leaves out cable and harmonic filter reactive effects, which add to the figure.

For a Type C synchronous unit at 12 MW and 0.92: Q = 12 × tan(arccos 0.92) = 12 × 0.426 = 5.11 Mvar at the connection point.

Checklist for the engineer

  • Confirm the type and the point of measurement with the DNO.
  • Calculate reactive capability at the connection point, including transformer and cable losses.
  • Check inverter or generator capability charts across the voltage range.
  • Agree the control mode (power factor, voltage or reactive power) and set points in writing.
  • Record agreed set points and any changes in the connection agreement.
  • For synchronous units, check the excitation system and the performance chart.
  • Ask the DNO about voltage control schemes near the site and the effect of reverse flow.
  • Keep capability evidence for the Power Generating Module Document of Type B and above.

From the requirement to studies your engineer can review

Reactive power capability depends on network data, the transformer, the cables and the control design. We prepare power-system studies and the engineering design behind a G99 application, including load-flow and capability calculations. The package is ready for your chartered engineer (CEng) or the responsible designer to review and sign. Tiza does not stamp, sign or certify designs in the UK. Contact us with the plant data and the DNO’s requirements.

Related guides: solar panels and power factor, harmonics and resonance in solar plants, short circuit and protection coordination in solar plants and interconnection relays.

Frequently asked questions

What reactive power capability does G99 require for Type A and Type B?

Operation anywhere between 0.95 power factor lagging and 0.95 leading when supplying registered capacity, at nominal voltage. The point of measurement is the connection point or the generating unit terminals, as agreed with the DNO.

Who decides the power factor or voltage set point?

It is agreed with the DNO as part of the connection application. Typically the generator chooses a power factor, but all control schemes, set points and later changes are agreed bilaterally and recorded in the connection agreement.

Is the requirement measured at the inverter or at the connection point?

For Type B it is at the connection point or generating unit terminals as appropriate and agreed with the DNO. In an installation with demand and generation, the DNO advises if the requirement is better specified at the module terminals (clause 12.5.3).

WhatsApp