G98 vs G99: Which One Applies to a Project

How to choose between ENA G98 and G99 for a UK generation project: the 16 A per phase test, Types A to D, worked examples and the process of each route.

By Shadai García, CEO and protection engineer at Tiza Group.

Every unit that can exportCurrent per phase: P / 230 V, or P / 690 Vthree-phase; add units on the same phaseEvery phase 16 A or less,units type tested?yesG98: notifyafter installationnoRegistered capacity of the module(all units) and connection voltageType A0.8 kW tobelow 1 MWType B1 MW tobelow 10 MWType C10 MW tobelow 50 MWType D50 MW+ or110 kV and uptest 1: current per phase against 16 Atest 2: registered capacity and voltage16 A per phase1 3.6 kW, one phase: 15.7 A, G982 6 kW battery, one phase: 26.1 A, Type A3 10 kW three-phase: 14.5 A, G983 + 5 kW battery on one phase: 36.2 A, Type A4 3 x 33 kW = 99 kW: 143.5 A, Type A5 14 x 330 kW at 11 kV = 4.62 MW: Type Billustrative; bar 4 is cut at the scale endDecisionPer phase16 A testG98CapacityType© tizagrp.comEvery unit that can exportCurrent per phase: P / 230 V, or P / 690 Vthree-phase; add units on the same phaseEvery phase 16 A or less,units type tested?yesG98: notifyafter installationnoRegistered capacity of the module(all units) and connection voltageType A0.8 kW tobelow 1 MWType B1 MW tobelow 10 MWType C10 MW tobelow 50 MWType D50 MW+ or110 kV and uptest 1: current per phase against 16 Atest 2: registered capacity and voltage16 A per phase1 3.6 kW, one phase: 15.7 A, G982 6 kW battery, one phase: 26.1 A, Type A3 10 kW three-phase: 14.5 A, G983 + 5 kW battery on one phase: 36.2 A, Type A4 3 x 33 kW = 99 kW: 143.5 A, Type A5 14 x 330 kW at 11 kV = 4.62 MW: Type Billustrative; bar 4 is cut at the scale endDecisionPer phase16 A testG98CapacityType© tizagrp.com
G98 or G99 decision tree: the current per phase test against 16 A with type-tested units leading to G98, otherwise the registered capacity and connection voltage placing the module in Type A, B, C or D, with the five example projects of 15.7 A, 26.1 A, 14.5 A, 143.5 A and 4.62 MW and the 5 kW battery that takes one phase from 14.5 A to 36.2 A. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

Two numbers decide between G98 and G99: the current per phase of everything that can export, compared with 16 A, and the registered capacity of the module in kW or MW. Up to 16 A per phase with type-tested equipment follows G98 with notification after installation. Above that, G99 applies, and the module is sorted into Type A, B, C or D by capacity and connection voltage.

Short answer: G98 or G99

G98 applies to generation up to 16 A per phase; G99 applies above that. Within G99, the project is placed in Type A, B, C or D by registered capacity and connection voltage. Both are ENA Engineering Recommendations, both reach the project through the distribution network operator (DNO), and the choice changes the work: G98 is a notification after installation, G99 is an application before it. The wider UK framework is in the UK electrical codes and grid connection guide.

The two tests in order

Test 1: current per phase. Add the exportable power of every unit on each phase, including batteries and inverters added later, and convert to current. For a 230 V single-phase unit: current = power ÷ 230 V. For a balanced three-phase unit: current = power ÷ (3 × 230 V). If every phase is at 16 A or less and the units are type tested, G98 applies.

Test 2: registered capacity and voltage. If test 1 fails, the project follows G99. The registered capacity of the power generating module places it in a type:

TypeRegistered capacityConnection voltage
A0.8 kW and above, below 1 MWbelow 110 kV
B1 MW and above, below 10 MWbelow 110 kV
C10 MW and above, below 50 MWbelow 110 kV
D50 MW and above at any voltageany capacity connected at 110 kV or above

The capacity is that of the whole module: for a solar farm, all inverters of the park together, not one inverter.

What each route asks of the project

G98G99
Before the workNothing to apply forApplication to the DNO
EquipmentType tested to G98Equipment with compliance evidence; the type sets the extent
Protection settingsFixed in the equipmentAgreed with the DNO for the site
After the workNotify the DNOCommissioning evidence and the DNO’s compliance process
StudiesNone by the installerDNO assessment; from Type B, studies and models from the generator

Types B, C and D add requirements of their own, including frequency response, fault ride through and reactive power capability, and in the case of Types C and D, more steps under the connection process. The guide on interface protection covers the protection side for all types.

Worked example: five projects

All values are illustrative. Supply is 400 V three-phase (230 V per phase).

  1. A 3.6 kW single-phase PV inverter. 3,600 ÷ 230 = 15.7 A. G98.
  2. A 6 kW single-phase battery inverter. 6,000 ÷ 230 = 26.1 A. G99, Type A.
  3. A 10 kW balanced three-phase inverter. 10,000 ÷ 690 = 14.5 A per phase. G98.
  4. A rooftop array of 3 inverters of 33 kW. Registered capacity = 3 × 33 = 99 kW. Per phase the current is 99,000 ÷ 690 = 143.5 A, far above 16 A. G99, Type A (0.8 kW to below 1 MW).
  5. A ground-mount solar park of 14 inverters of 330 kW at 11 kV. Registered capacity = 14 × 330 = 4,620 kW = 4.62 MW. G99, Type B (1 MW to below 10 MW, below 110 kV).

A battery added to project 3 later is a trap: a 5 kW single-phase inverter on one phase adds 5,000 ÷ 230 = 21.7 A to that phase, taking it from 14.5 A to 36.2 A. The route changes from G98 to G99 even though the original project did not need one.

How the route can change

  • Add storage later. The capacity counted may differ between export and import. Ask the DNO which one it uses for the Type, and make the decision when the whole project is known.
  • Phase another unit. On a three-phase supply, moving a single-phase unit to another phase can bring each phase under 16 A. The registered capacity is still the sum of all units.
  • Grow the array. Moving from 990 kW to 1.1 MW changes the Type from A to B, with extra requirements, though the voltage and site stay the same.

Elsewhere, IEEE 1547 in the United States and AS/NZS 4777 in Australia sort inverter projects by other criteria, so a UK decision cannot be carried over to another country.

Why the line is drawn at 16 A

A home or small business connects to the low-voltage network, where each feeder serves many customers and a few kilowatts of generation hardly change the voltage. Above 16 A per phase, the generation can change voltage and fault levels on the feeder, so the operator wants to see the design first. The same reasoning explains why the Types rise with capacity: a larger plant has a larger effect on the network, so the operator asks for more evidence.

Checklist for the engineer

  • List every unit that can export, with its AC rating and the phase it connects to.
  • Calculate the current per phase and compare with 16 A.
  • If above 16 A, calculate the registered capacity of the module and find the Type.
  • Check the connection voltage: 110 kV or above is Type D at any size.
  • Ask the DNO which capacity it uses for storage and for hybrid inverters.
  • Plan the commissioning evidence for the route chosen.
  • Record the issue of G98 or G99 that the DNO applies.
  • Revisit the decision when any unit is added.

For export limits that keep a site inside a connection capacity, see G100 export limitation schemes. The comparison with active network management covers what happens when the network cannot take the full capacity. For the standards behind type testing, see PV inverter standards.

From the decision to a design your chartered engineer can review

The choice of route sets the studies, the protection plan and the evidence required at commissioning. We prepare the engineering design and the power-system studies for G98 and G99 projects, ready for your chartered engineer to review and sign before they go to the network operator. Tiza does not stamp, sign or certify designs in the UK. Contact us with the project data.

Frequently asked questions

What decides whether G98 or G99 applies?

The current per phase of the generation at the connection. Up to 16 A per phase with type-tested equipment follows G98. Anything above that follows G99, which needs an application to the network operator before the work starts.

What are the G99 Types A to D?

G99 sorts power generating modules by registered capacity and connection voltage: Type A from 0.8 kW to below 1 MW, Type B from 1 MW to below 10 MW, Type C from 10 MW to below 50 MW, all connected below 110 kV, and Type D at 50 MW or above, or at 110 kV or above.

Can a project start under G98 and move to G99?

Yes. Adding a battery, a second inverter or a larger array can lift the current per phase above 16 A. The project then needs a G99 application, so the final capacity should be settled before the route is chosen.