Tiza Group

Home / Guides / Codes and grid connection: US, UK, CA, AU

ENA G100: Export Limitation Schemes Explained

ENA G100 sets the technical rules for customer export limiting schemes. How a scheme works, the fail-safe behaviour it needs, and a worked power example.

By Shadai García, CEO and protection engineer at Tiza Group.

DNO networkCTPCCVTsite busload 120 kW=~=~export limit controllerlimit 200 kWset-point 314 kWfixed limit 200 kWPVbattery500 kW AC in total: PV and battery invertersfixed limit 200 kW stored in the invertersPowerMeasure / controlCommunicationsallowed: 120 + 200 = 320 kW; cut 180 kWerror 6 kW: target 194 kW, set-point 314 kWcommunications lost: fixed limit 200 kWworst case, no load: export 200 kWkW5003142000500 kW installedlink lost314 kW (320 kW less 6 kW)200 kW: loses 114 kW, never above the limitillustrative: 500 kW AC, 200 kW export limitExport limitMeasureControllerSet-pointInvertersLimit© tizagrp.comDNO networkCTPCCVTsite busload 120 kW=~=~export limit controllerlimit 200 kWset-point 314 kWfixed limit 200 kWPVbattery500 kW AC in total: PV and battery invertersfixed limit 200 kW stored in the invertersPowerMeasure / controlCommunicationsallowed: 120 + 200 = 320 kW; cut 180 kWerror 6 kW: target 194 kW, set-point 314 kWcommunications lost: fixed limit 200 kWworst case, no load: export 200 kWkW5003142000500 kW installedlink lost314 kW (320 kW less 6 kW)200 kW: loses 114 kW, never above the limitillustrative: 500 kW AC, 200 kW export limitExport limitMeasureControllerSet-pointInvertersLimit© tizagrp.com
G100 export limitation scheme: a 500 kW PV and battery site with 120 kW of load, the CT and VT at the point of connection feeding the controller, the set-point sent to the inverters over a communications link, and the fixed limit of 200 kW stored in the inverters when the link fails, with the set-point of 314 kW falling to 200 kW. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

ENA Engineering Recommendation G100 covers customer export limiting schemes: a controller measures the power at the connection point and holds the export below the figure agreed with the network operator. The part reviewers read closest is fail-safe behaviour: if the measurement, the communications or the controller power fail, the plant must fall back to the agreed limit.

Short answer: what ENA G100 covers

ENA G100 sets the technical requirements for customer export limiting schemes. A scheme measures the power flowing at the connection point and cuts generation or battery output so that the export stays at or below a limit agreed with the distribution network operator (DNO). This lets a site connect with an export capacity that is smaller than its installed capacity, which is useful where the network cannot take more. Issue 2 of G100, with its amendments, is the issue in use. It also covers import limitation, and DNO application forms refer to it. For the wider framework, see the UK electrical codes and grid connection guide.

How a scheme works

Four elements make up a scheme:

  1. Measurement of the power at the point of connection, with a meter or current and voltage transformers.
  2. Controller that compares the measurement with the agreed limit and calculates a set-point.
  3. Communications that carry the set-point to the inverters and storage converters.
  4. Output devices, the inverters or battery converters that reduce output when told.

The control loop runs continuously. When the site load falls, the surplus rises and the controller lowers the set-point. When the load rises again, the set-point comes back up. The principle is the same as in zero export control in solar plants; G100 applies it with a limit above zero and with the rules the DNO expects.

The part that decides acceptance: fail-safe behaviour

A scheme that works well in normal conditions is not enough. In normal operation, G100 requires the scheme to bring an excursion back to the agreed export capacity or less within 5 seconds. The question the DNO asks is what happens when something breaks. DNO application forms for G100 ask for test results for loss of communications and for loss of the controller’s power supply, and they expect the plant to fall back to the agreed limit in both cases.

In practice this means:

  • Loss of measurement or communications. The inverters hold a fixed limit stored in them, equal to the agreed export limit, until the link returns.
  • Loss of controller power. The fall-back is built into the output devices, so a dead controller cannot leave them at full output.
  • Fixed limit with no load credit. In the fall-back state the plant assumes that the site load is zero, because it cannot measure it. This costs energy, but it keeps the limit.

Tests should show each of these. Disconnect the communications and record that output drops to the fixed limit, switch off the controller supply and record the same, then restore each and record the recovery time.

Worked example: set-points and fall-back

All values are illustrative.

Data. A site has 500 kW of AC generation. The DNO agreement allows an export of 200 kW. The measured site load at one moment is 120 kW. The measuring chain has an error of ±1 % of a 600 kW full scale.

Step 1. Generation the site may run. Allowed generation = load + export limit = 120 + 200 = 320 kW. The controller sets the inverters to 320 kW, of a possible 500 kW. Curtailment is 500 − 320 = 180 kW.

Step 2. Measurement error. ±1 % of 600 kW = ±6 kW. To keep the export at or below 200 kW even when the error works against the site, the controller targets 200 − 6 = 194 kW of export. The set-point becomes 120 + 194 = 314 kW.

Step 3. Fall-back. If the communications fail, the inverters go to the fixed limit of 200 kW, which assumes that the load is zero. Output falls from 314 kW to 200 kW. The site loses 114 kW of generation compared with normal control, but the export cannot exceed 200 kW.

Step 4. Check. In the worst case the load is 0 kW at the moment of failure. Export = 200 kW, equal to the limit. If the fixed limit were set at 250 kW to save energy, the export could reach 250 kW and break the agreement, so the fall-back is not adjusted for convenience.

Choosing the margin

The margin that the controller keeps below the limit depends on three things: the accuracy of the measurement, the speed of the loop and the size of the load swings. A site with a large, fast-changing load needs more margin than a site with a steady one. The margin is paid for in lost energy, so it is calculated and not guessed; the DNO’s requirements say whether a particular margin is accepted.

G100 and the other documents

An export limit changes how the DNO sees a project, but it does not remove the other requirements. The generation is still classified under G98 or G99, protection still follows the connection offer, and the plant controller needs the cybersecurity attention described in power plant controller (PPC) and SCADA cybersecurity. For how a limit differs from network-side control by the DNO, see G100 versus active network management. Testing of plant controllers is covered in PPC testing.

Checklist for the engineer

  • State the export limit in kW and the document in which the DNO agreed it.
  • Draw the measurement point and name the meter or transformers used.
  • Calculate the measurement error and the margin the controller keeps.
  • Store the fixed limit inside the output devices, not only in the controller.
  • Test loss of communications and loss of controller power, and record the results.
  • Record the recovery behaviour when the link or power returns.
  • Keep the settings, the test records and the single-line diagram together.
  • Check that the controller and its network are protected against remote tampering.

From the scheme to a design your chartered engineer can review

An export limiting scheme is accepted on its design and its evidence. We prepare the engineering design: single-line diagram, measurement and control architecture, fall-back settings and the test plan. The package is ready for your chartered engineer to review and sign before it goes to the network operator. Tiza does not stamp, sign or certify designs in the UK. Contact us with the DNO’s limit and the site data.

Frequently asked questions

What is ENA G100?

G100 is the ENA Engineering Recommendation for customer export limiting schemes. It sets out how a scheme at the customer's site limits the power exported to the network, so that a generator or battery can connect with a limit below its installed capacity.

What must a G100 scheme do when its controller or communications fail?

The generation and storage must fall back to the export limit that was agreed. A scheme that keeps exporting at full output when it loses its measurement or its power would not hold the limit, so the failure tests are part of the evidence the network operator expects.

Does an export limit mean a smaller inverter?

No. An export limit holds the power at the connection point, while the plant can be larger. The site load uses what is generated first, and the controller reduces output only when the surplus would exceed the limit.