ENA EREC G81 is a framework of documents for the design, materials and installation of underground electricity networks that serve new developments in Great Britain. It lets a developer or independent connection provider design and build the network to a common standard that the network operator then adopts.
Short answer: what ENA EREC G81 covers
ENA EREC G81 is the framework that sets how underground networks for new developments in Great Britain are designed, specified and installed, so that a network built by someone other than the operator can be adopted by it. It is published in parts. One part covers design and planning for low-voltage networks in housing developments. Others cover materials specifications, underground connections to industrial and commercial loads, and installation and records. Each network operator adds its own company-specific appendices. Part 1, the design and planning part for low-voltage housing developments, is at Issue 3 (2016). Each part has its own issue, so the one to apply is the issue the network operator’s design standard names.
The framework sits in the ENA layer in the UK electrical codes and grid connection guide. Its scope is mostly new load. Generation on the new network follows G98 or G99, and electric vehicle charging adds to the demand.
Who is involved
- The network operator specifies the point of connection, its appendices and the adoption conditions.
- The developer needs the connection for a site and pays for the works.
- An independent connection provider (ICP) designs and builds the new network under the operator’s approval. The operator can also do the work.
- Your design engineer produces the layout, calculations and records.
The designer’s duties under health and safety law apply to this work too. See the CDM 2015 guide.
What the design covers
- Demand. The diversified maximum demand of the development, with allowance for heat pumps and vehicle chargers where the operator’s data asks for it.
- Network arrangement. Substation positions, feeders, normally open points and the use of ring or radial layouts. The security level is set by the operator’s planning rules. See the security of supply guide.
- Cable and substation ratings. Current ratings, voltage drop and fault levels at the substation and at the ends of feeders. See maximum and minimum short-circuit current.
- Earthing and protection. The arrangement at the substation and on the low-voltage network, including the earth potential rise where it matters. See ground potential rise.
- Materials and installation. Cable types, trench depths, ducts, jointing and the records handed over for adoption.
- Generation and charging. Connection of small generation, which follows the G98 and G99 documents, and the effect of vehicle charging on loading.
The material specifications and installation rules are set in the parts of G81 and in the operator’s appendices.
Worked example: demand, substation and cable check
All values are illustrative. The diversified demand per dwelling is an assumption for the example, standing in for the figure from the network operator’s data.
- Development: 120 dwellings, one new 500 kVA ground-mounted substation.
- Assumed diversified demand: 1.5 kW per dwelling.
- Vehicle chargers: 36 dwellings with a 7 kW charger, with an assumed diversity of 0.2.
- Power factor of the combined load: 0.97.
- Low-voltage side: 400 V, three-phase.
- Dwelling demand: 120 × 1.5 = 180 kW.
- Charger demand: 36 × 7 × 0.2 = 50.4 kW.
- Total: 180 + 50.4 = 230.4 kW.
- Apparent power: 230.4 ÷ 0.97 = 237.5 kVA.
- Loading of the substation: 237.5 ÷ 500 = 47.5 %.
- Current on the main low-voltage output: 237 500 ÷ (√3 × 400) = 237 500 ÷ 692.8 = 343 A.
The substation is lightly loaded, so there is room for growth. If the charger diversity were 0.5 in place of 0.2, the charger demand would be 36 × 7 × 0.5 = 126 kW, the total 306 kW and the apparent power 315.5 kVA, which is 63 % of 500 kVA. A design that assumes a low diversity today should say what growth it covers and what the operator accepts. The 343 A is the total at the low-voltage board. It splits between the feeders, and each feeder cable is checked for its own share, the installation conditions and the voltage drop along the run.
Adoption and records
A network built under G81 is meant to become part of the operator’s system. That makes the records as important as the cable. The operator needs to know where each cable, joint and substation is, which materials were used and how the installation was tested. A design that is correct but handed over with poor records can delay adoption. The designer plans the records from the start: drawing standards, joint schedules, test sheets and as-built layouts, all in the form the operator asks for.
The operator also decides the adoption conditions, such as inspection stages during installation and a check before energisation. Agree them with the operator at the start, with dates, so that the programme includes them.
What to submit
- Site layout with substation and feeder routes.
- Demand schedule with the assumptions and their source.
- Single-line diagram for the new network.
- Load flow, voltage drop and fault level results at key points.
- Earthing design where required by the operator.
- Materials list against the operator’s approved materials.
- Installation drawings and the records the operator needs for adoption.
Checklist for the engineer
- Confirm the G81 issue and the operator’s appendices that apply.
- Obtain the point of connection and the fault level at it.
- Use the operator’s demand data, or state and justify yours.
- Include allowances for heat pumps, vehicle charging and generation where asked.
- Check substation loading, cable ratings and voltage drop on the worst feeder.
- Check fault level against equipment ratings at the substation and the feeder ends.
- Prepare the records needed for adoption from the start.
- Send the design to your chartered engineer for review before submission.
Related guides
The sister guide on fault levels explains the check in step 3. For the earthing of the substation see ENA TS 41-24.
From the framework to a design your chartered engineer can review
We prepare the engineering for a new underground network: demand schedule, single-line diagram, load flow and fault level results, and the layout the operator asks for. It is ready for your chartered engineer to review and sign off before it goes to the network operator. Tiza does not sign, seal or certify designs in the UK. Contact us with the site plan and the operator’s requirements.
Frequently asked questions
What is ENA EREC G81?
It is the Energy Networks Association framework for the design, materials specification and installation of underground low-voltage and some high-voltage networks serving new developments. It is published in several parts, and network operators add company-specific appendices.
Who uses G81?
Network operators, developers and independent connection providers who design and build the network for a new site and hand it to the operator. The design follows G81 and the operator's appendices, and the operator approves it.
Does G81 give one cable size or one demand figure for every site?
No. The framework sets how the design is done, and each network operator publishes its own appendices and data. The demand and cable ratings come from those documents and from the site data, not from a fixed figure.