G100 vs Active Network Management: Flexible Connections

G100 export limits sit at the customer's site, active network management sits in the network. How flexible connections differ, with a curtailment example.

By Shadai García, CEO and protection engineer at Tiza Group.

DNO networkDNO ANMPCC: 3 MW=~5 MW plantG100 schemecustomer, fixed 3 MWplant controllerone set-pointANM signalPowerMeasure / controlCommunicationsno limit: 31.0 MWh in ten hoursfixed 3 MW: 7.4 MWh curtailed = 23.9 %flexible, hours 5 to 7 only: 5.5 MWh = 17.7 %MW035123456789103 MW limithourillustrative; magenta = energy not exportedControl pathMeasureG100 schemeANM signalControllerOutput© tizagrp.comDNO networkDNO ANMPCC: 3 MW=~5 MW plantG100 schemecustomer, fixed 3 MWplant controllerone set-pointANM signalPowerMeasure / controlCommunicationsno limit: 31.0 MWh in ten hoursfixed 3 MW: 7.4 MWh curtailed = 23.9 %flexible, hours 5 to 7 only: 5.5 MWh = 17.7 %MW035123456789103 MW limithourillustrative; magenta = energy not exportedControl pathMeasureG100 schemeANM signalControllerOutput© tizagrp.com
G100 against active network management: a 5 MW solar plant with a customer G100 scheme measuring at the connection point and a DNO ANM signal over a communications link reaching the same plant controller, and the hourly output of ten hours with 7.4 MWh curtailed by a fixed 3 MW limit, 23.9 percent, against 5.5 MWh, 17.7 percent, under a flexible connection. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

G100 export limiting is a fixed ceiling controlled inside the customer's site. Active network management (ANM) is a control system run by the network operator that curtails generators when the network is constrained. A flexible connection is the agreement that lets a generator connect earlier or larger on the condition that it accepts that curtailment. The three are separate, and one project can use more than one.

Short answer: where each control sits

G100 is a limit inside the customer’s site. Active network management (ANM) is a control inside the network. A flexible connection is the contract that lets a generator accept curtailment. All three reduce what a generator exports. They differ in who owns the control, how often the limit changes and what happens when communications fail. The wider framework is in the UK electrical codes and grid connection guide, and the details of customer schemes are in the G100 guide.

The three, side by side

G100 export limitActive network managementFlexible connection
What it isA scheme at the customer’s siteA control system of the network operatorA connection agreement
Who owns the controlThe customerThe distribution network operator (DNO)Set in the agreement
The limitA fixed value agreed with the DNOChanges with network conditionsThe terms of the agreement
What triggers itThe measured power at the connection pointA network constraint such as a thermal or voltage limitThe same constraints, written as terms
Customer’s taskBuild, test and maintain the schemeReceive and obey the signalAccept the terms and the risk of curtailment

A flexible connection describes the commercial and technical terms. ANM is often the tool that applies them. G100 is the customer-side tool and does not depend on ANM.

When each one appears

  • The network can take the generator most of the time but not always. The DNO may offer a flexible connection with ANM, so that the generator can connect at its full capacity and be curtailed during the hours when the network is constrained.
  • The network can take only part of the capacity at any time. A fixed export limit under G100 keeps the connection inside what is available. The customer carries out the control.
  • A site with large local load. The load absorbs part of the generation, and a G100 scheme only has to act when the surplus would cross the limit. See zero export control for the control principle.

The terms, limits and signals of an ANM scheme belong to the DNO’s own offer, not to a general document. Read the offer before assuming how any of these work at your site.

Worked example: how much energy is curtailed

All values are illustrative. A 5 MW solar plant has a connection with a 3 MW limit, either as a fixed G100 ceiling or as an ANM constraint that stays at 3 MW for the hours below.

Hourly output, if there were no limit, for ten daylight hours (MW): 0.5, 1.5, 2.8, 4.0, 4.8, 5.0, 4.7, 3.9, 2.6, 1.2.

Step 1. Energy without a limit. Sum = 0.5 + 1.5 + 2.8 + 4.0 + 4.8 + 5.0 + 4.7 + 3.9 + 2.6 + 1.2 = 31.0 MWh.

Step 2. Energy above 3 MW, hour by hour. Hours 4 to 8 exceed the limit: (4.0 − 3) + (4.8 − 3) + (5.0 − 3) + (4.7 − 3) + (3.9 − 3) = 1.0 + 1.8 + 2.0 + 1.7 + 0.9 = 7.4 MWh.

Step 3. Share curtailed. 7.4 ÷ 31.0 = 23.9 % of the energy on that day.

Step 4. What changes with flexible terms. If the same plant had a flexible connection where the network is constrained only in 3 of those 5 hours, curtailment is limited to those hours. Take hours 5, 6 and 7: 1.8 + 2.0 + 1.7 = 5.5 MWh, or 17.7 % of the day. The plant connects at 5 MW, and gives up 5.5 MWh on that day instead of 7.4 MWh.

The days of the year differ, so a real assessment uses the network operator’s data. The example shows the reading: a fixed limit costs energy every hour above the ceiling, while a flexible connection costs energy only when the constraint is active.

Reading the agreement

Whichever control applies, the agreement should answer the same questions: what is the limit, who can change it, how fast must the plant respond, what is the fall-back when communications fail, and what happens to the energy that was not exported. If any answer is missing, ask the DNO before the design is frozen.

Practical differences for the design

  • Metering and control. G100 needs the customer’s own measurement and controller. ANM needs a communications link to the DNO and the ability to follow its signal.
  • Fail-safe. Both need a defined behaviour when communications fail. Which value the plant falls back to is stated in the DNO’s requirements.
  • Evidence. Both need test records. The details of a customer scheme are in the G100 guide; those of a network-side scheme come from the DNO.
  • Classification. The generation is still classified under G98 or G99, whatever the limit.
  • Cybersecurity. A link to the network operator is a new access path. See power plant controller (PPC) and SCADA cybersecurity.

Checklist for the engineer

  • Read the connection offer and find which control it uses: customer limit, ANM or both.
  • Write down the limit, who sets it and how it can change.
  • Ask what the plant does when the signal or the link fails.
  • Estimate the energy lost under each option with the operator’s data.
  • Plan the measurement, controller and communications needed on the customer side.
  • Plan the tests and keep the records with the settings.
  • Check that the plant controller can follow set-points within the response time required.
  • Review the commercial terms with the party that signs the agreement.

From the connection offer to a design your chartered engineer can review

Choosing between a fixed limit and a flexible connection depends on the network studies and on the plant’s own design. We prepare the engineering design and the power-system studies behind that choice, ready for your chartered engineer to review and sign. Tiza does not stamp, sign or certify designs in the UK. Contact us with the connection offer and the site data.

Frequently asked questions

What is the difference between G100 and active network management?

G100 limits export through a scheme the customer owns, at a fixed value agreed with the network operator. Active network management is run by the network operator, which curtails generators in real time when a network limit is reached. The first is a ceiling on one site, the second is a shared control of the network.

What is a flexible connection?

A flexible connection is a connection agreement in which the generator accepts that its output can be reduced when the network is constrained, in exchange for connecting earlier or at a larger capacity than a firm connection would allow.

Can a project use an export limit and a flexible connection together?

Yes. A customer scheme under G100 can hold a fixed export ceiling, while the network operator's system can reduce output further when the network needs it. Each has its own set-point, communications and tests.